Closed Solicitation · DEPT OF DEFENSE
AI Summary
The United States Air Force is seeking bids for a Firm-Fixed Price contract to expand the non-potable water distribution system for irrigation at Morón Air Base, Spain. The project includes civil and mechanical works, with an estimated value between $500,000 and $1,000,000 and a performance period of approximately 570 days.
The United States Air Force intends to issue solicitation FA5575-26-B-0003 to solicit Bids for a Firm-Fixed Price contract to expand the non-potable water distribution system to cover irrigation areas and provisions for the future connection of buildings to the non-potable water distribution system at Morón Air Base, Spain. The magnitude of construction for this project is estimated to be between $500,000 and $1,000,000 U.S. Dollars. The period of performance for this project is estimated at 570 calendar days.
A solicitation package will be available on the SAM website at www.sam.gov on or after 6 May 2026.
In accordance with the Agreement of Defense and Cooperation between the Kingdom of Spain and the United States of America, any contract resulting from this notice/solicitation can only be entered into with companies authorized to carry out these activities in Spain under Spanish law. Companies must meet the requirements established by Spanish legislation for execution of Government works. In addition, in accordance with the Agreement of Defense Cooperation between the U.S.A. and the Kingdom of Spain, Annex 6, Article 1 (3) "The contractors must meet the requirements established by Spanish legislation for execution of government works. A breach of contract on the part of a contractor shall have the same consequences for the contractor for purposes of future contracting with the Spanish government as would occur with a breach of a contract with the Spanish public administration." and (5) " Spanish material, labor, and equipment shall be used whenever feasible and consistent with the requirements".
The construction works consist of, but are not limited to, the items indicated below, including the testing to be performed by independent laboratories for quality control:
1. Site investigation
The Contractor shall be verifying existing utility locations, within the area of work. Scan the construction site with Ground Penetrating Radar (GPR), electromagnetic, or sonic equipment, and mark the surface of the ground or paved surface where existing underground utilities are located. Verify the elevations of existing piping, utilities, and any type of underground obstruction discovered during scanning, in locations to be traversed by piping and other work to be conducted or installed. Verify elevations before installing new utilities close to manholes or other adjacent structures.
2. CLIN´S
CLIN #1: BASE BID: AREA #1 (BRANCH LINE Nº18) + INSTALLATIONS OF PROGRAMMERS IN EXISTING SPRINKLER IRRIGATION SYSTEM + MODIFICATION OF NON-POTABLE WATER SYSTEM AT POTABLE WATER TREATMENT FACILITY
1.1 Civil works:
1. Excavations and fill for trenches utilities routing.
2. Fill vegetation area.
1.2 Mechanical Works
1.2.1 Modification of non-potable water system at potable water treatment facility
1. Provide all piping and valves as indicated in the drawings for non potable water system.
1.2.2 Installations of programmers in existing sprinkler irrigation system
1. Provide all piping and valves as indicated in the drawings for non potable water system.
2.Provide hose bibb, hose connection vacuum breaker 3/4", water meter, pressure gauge, solenoid valve, programmer with solar panel as indicated in the drawings including cabinet.
1.2.3 Irrigation System area #1 branch line nº18
1. Provide hose bibbs with water meter, pressure gauge as indicated in the drawings including cabinet.
2. Provide all piping and valves as indicated in the drawings for non potable water system.
CLIN #2: OPTION #1: AREA #2 (BRANCH LINES 08, 09, 11, 12 (building #302) and Running Track
1.1 Civil works:
1.Excavations and fill for trenches utilities routing.
2. Fill vegetation area
1.2 Mechanical Works
1.2.1 Irrigation System area #2 branch line nº 08, 09, 11, 12 (building #302) and running track
1. Provide all piping and valves as indicated in the drawings for non potable water system.
2. Provide hose bibbs with water meter, pressure gauge as indicated in the drawings including cabinet.
3. Provide handhole connections for buildings.
CLIN #3: OPTION#2: AREA #3 (BRANCH LINES 06 AND 07)
1.1 Civil works:
1.Excavations and fill for trenches utilities routing.
2. Fill vegetation area
1.2 Mechanical Works
1.2.1 Irrigation System area #3 branch line nº 06 and 07
1. Provide all piping and valves as indicated in the drawings for non potable water system.
2. Provide hose bibbs with water meter, pressure gauge as indicated in the drawings including cabinet.
CLIN #4: OPTION #3: AREA #4 (BRANCH LINES 05, 15, 15.1 AND 17. Building #208 and #202 )
1.1 Civil works:
1.Excavations and fill for trenches utilities routing.
2. Fill vegetation area
1.2 Mechanical Works
1.2.1 Irrigation System area #4 branch line nº 05, 15, 15.1 and 17. Building #208 and #202
1. Provide all piping and valves as indicated in the drawings for non potable water system.
2. Provide hose bibbs with water meter, pressure gauge as indicated in the drawings including cabinet.
3. Provide handholes connections for buildings.
CLIN #5: OPTION #4: AREA #5 (BRANCH LINES 01, 02, 03, 04, 16 and 19)
1.1 Civil works:
1.Excavations and fill for trenches utilities routing.
2. Fill vegetation area
1.2 Mechanical Works
1.2.1 Irrigation System area #5 branch line nº 01, 02, 03, 04, 16 and 19
1. Provide all piping and valves as indicated in the drawings for non potable water system.
2. Provide hose bibbs with water meter, pressure gauge as indicated in the drawings including cabinet.
CLIN #6: OPTION #5: UPGRADES
1. Polyethylene pipe HDPE PN10 DN200, connection fittings and excavation and filling of trench 30m
2. Polyethylene pipe HDPE PN10 DN160, connection fittings, excavation and filling of trench 40m
3. Polyethylene pipe HDPE PN10 DN63, connection fittings and excavation and filling of trench 40m
4. Polyethylene pipe HDPE PN10 DN110, connection fittings and excavation and filling of trench 40m
5. Gate Valve Ø160mm and accessories (valve box) 2ud.
6. Gate Valve Ø110mm and accessories (valve box) 2ud
7. Road crossing (drilled) RC-01 for pipe Ø160mm 10m
8. Road crossing (drilled) RC-02 for pipe Ø110mm 11m
9. Cabinet including hose bibb, hose connection vacuum breaker 3/4" water meter, pressure gauge solenoid valve, programmer with solar panel and accessories 4ud
CLIN #7: OPTION #6: EXPANSION NPW – DISTRIBUTION OF NON-POTABLE
WATER FOR BUILDINGS #106, #110, #119, #192 AND #203
1.1 Civil works:
1.Excavations and fill for trenches utilities routing.
2. Fill vegetation area
1.2 Mechanical Works
1. Provide all piping and valves as indicated in the drawings for non potable water system.
2. Provide handholes connections for buildings.
The certification requirements are as follows:
CERTIFICATION OF CLASSIFICATION: Bidders and/or their subcontractors must hold an updated Certificate of Classification issued by the "Registro Oficial de Licitadores y Empresas Clasificadas del Estado", covering the following groups, subgroups, and categories. The certificate holder must execute the activities related to the certificate.
GROUP SUBGROUP CATEGORY
C 1 2
E 1 3
Any other technical requirments will be listed in the solicitation.
ADD NON-POTABLE WATER DIST LINES TO IRRIGATION AREAS, MULTI is a federal acquisition solicitation issued by DEPT OF DEFENSE. Review the full description, attachments, and submission requirements on SamSearch before the response deadline.
SamSearch Platform
AI-powered intelligence for the right opportunities, the right leads, and the right time.