Closed Solicitation · DEPT OF DEFENSE

    BRANDON ROAD INTERBASIN PROJECT INDUSTRY DAY - 7 APRIL 2026

    Sol. W912EK26BRIPIDSpecial NoticeROCK ISLAND, IL
    Closed
    STATUS
    Closed
    closed Apr 7, 2026
    POSTED
    Mar 27, 2026
    Publication date
    NAICS CODE
    237990
    Primary industry classification
    PSC CODE
    Y1QA
    Product & service classification

    AI Summary

    The U.S. Army Corps of Engineers is hosting an Industry Day on April 7, 2026, for the Brandon Road Interbasin Project, focusing on Increment II. This event will provide insights into the project scope, timeline, and requirements, while allowing contractors to ask questions and offer feedback. Participants will also have networking opportunities with potential partners.

    Contract details

    Solicitation No.
    W912EK26BRIPID
    Notice Type
    Special Notice
    Posted Date
    March 27, 2026
    Response Deadline
    April 7, 2026
    NAICS Code
    237990AI guide
    PSC / Class Code
    Y1QA
    Primary Contact
    Samantha Johanson
    State
    IL
    ZIP Code
    61299-5001
    AI Product/Service
    service

    Description

    The U.S. Army Corps of Engineers, Rock Island District invites you to an Industry Day on Tuesday 7 April 2026 from 8:30am – 12:00pm for the Brandon Road Interbasin Project.

    Agenda
    8:30 - 9:00 a.m.    Check-In
    9:30 - 11:30 a.m.  Presentation and Question and Answer Session

    Location: 
    Davenport River Center - Arkansas Room
    136 E 3rd St
    Davenport, Iowa 52801

    **Please see the following link for registration for the Brandon Road Interbasin Project Industry Day.**

    https://forms.osi.apps.mil/r/EGBRszaBQX


    This is your opportunity to learn about this significant infrastructure project and how your company can be a part of it.

    Project Overview:

    The Brandon Road Interbasin Project is a critical control point in preventing Invasive Species, including Invasive Carp fish, from becoming established in the Great Lakes. This project will construct a series of deterrent measures in the lock chamber and approach channel. Once complete, a series of electric, hydroacoustic, and bubble deterrents will be operational while facilitating river navigation traffic. The project is broken into 3 construction increments (shown below). This presentation will focus on Increment II – Flushing Lock and Right Descending Bank Construction Contract. The purpose of this engagement is to provide contractors awareness of the upcoming contract and also to solicit feedback during this presentation regarding ways to improve the design to allow for more efficient and cost-effective construction.


    The project is designed in 3 construction increments, as follows:

    Increment I - Leading Edge

    • Automated Barge Clearing (ABC) Deterrent
    • Bubble Curtain Deterrent
    • Acoustic Deterrent (Leading Edge)
    • Leading Edge Support Facilities
    • Upstream Boat Ramp
    • Channel Rock Excavation

    Increment II – Flushing Lock and Right Descending Bank

    • Flushing Lock (FL)
    • Right Descending Bank (RDB) Wall
    • Channel Rock Excavation

    Increment III - Engineered Channel

    • Electric Deterrent
    • Acoustic Deterrent (Eng Channel)
    • Support Facilities Building
    • Engineered Channel Floor & Walls
    • Downstream Boat Ramp


    Industry Day Highlights:

    • Attend the presentation with detailed information about the project scope, timeline, and specific requirements for each phase.
    • Get your questions answered by USACE representatives and project engineers during Q&A.
    • Provide feedback on how to improve design to allow for more efficient and cost-effective construction.
    • Network with potential prime contractors, subcontractors, and suppliers to explore partnerships and innovative solutions.

    Presentation will include:

    • Project Background
    • Construction Phasing and Sequencing
    • Status of Increment II Design
    • Details of Increment II Design
    • Industry Questions

    **Draft Plan Sets for the Flushing Lock and RDB Wall are attached below in the Attachments/Links section**

    Key dates

    1. March 27, 2026Posted Date
    2. April 7, 2026Proposals / Responses Due

    AI search tags

    Frequently asked questions

    BRANDON ROAD INTERBASIN PROJECT INDUSTRY DAY - 7 APRIL 2026 is a federal acquisition solicitation issued by DEPT OF DEFENSE. Review the full description, attachments, and submission requirements on SamSearch before the response deadline.

    SamSearch Platform

    Stop searching. Start winning.

    AI-powered intelligence for the right opportunities, the right leads, and the right time.