Closed Solicitation · DEPARTMENT OF TRANSPORTATION
AI Summary
The HI STP 360 Hana Highway Bridges project seeks information from contractors regarding a potential Project Labor Agreement. This is a Sources Sought Notice, not a solicitation. The project involves improvements to six bridges along Hana Highway in Maui, Hawaii, with an estimated cost of $35 million to $45 million. Responses are due by March 4, 2026.
This is a Special Notice and is for information purposes only regarding project HI STP 360 Hana Highway Bridges project, Sources Sought Notice 6982AF-26-SS-000001. THIS IS NOT A REQUEST FOR PROPOSALS, QUOTATIONS, OR BIDS. NO SOLICITATION IS CURRENTLY AVAILABLE. The purpose of this announcement is to determine the following:
SUBMITTAL INFORMATION:
SUBMITTALS SHOULD BE MADE IN ELECTRONIC FORMAT
ISSUE DATE: February 20, 2026
DUE DATE FOR RESPONSES: March 4, 2026, 4:00 PM MST
SUBMIT RESPONSES TO: Stephanie Navarro at cflacquisitions@dot.gov
HI STP 360 Hana Highway Bridges
This project will provide improvements to 6 of the 59 existing bridges along State Route 360, also referred to as Hana Highway, between mile markers 6.0 and 28.4. This project is located along the northeast coast of the island of Maui in the State of Hawaii. The purpose of the project is to improve the existing bridges to 16-ft curb-to-curb minimum widths, meet HL-93 loading capacities, meet current seismic criteria, and meet MASH TL-2 crash-tested railings while maintaining historic and rural character of the bridges and existing roadway alignment.
The existing six bridges to be improved are: Bridge #2 – Kailua Stream, Bridge #5 – Makanali Stream, Bridge #8 – Puohokamoa Stream, Bridge #19 – Kopiliula Stream, Bridge #39 – Ula’ino Stream and Bridge #40 – Mokulehua Stream. Bridge #19 – Kopiliula Stream will be built on a new alignment while the other five bridges will be kept on the existing alignment of Hana Highway.
SCOPE OF THE WORK: The scope of this project includes replacement of 6 existing bridges along Hana Highway. The proposed bridges range in length from 23 feet to 85 feet. Five of the proposed bridges will be single span bridges with one bridge being a two-span bridge. Proposed abutments will be constructed behind existing cement rubble masonry (CRM) abutments while protecting existing CRM in place. Location of the bridges along Hana Highway will present accessibility and materials and equipment delivery challenges. It is anticipated that numerous night closures and multi-day closures of Hana Highway will be required to construct proposed improvements. Public outreach during construction will be paramount to keep the residents and the traveling public updated about construction activities and roadway closures.
PRINCIPAL WORK ITEMS: Approximate quantities of principal work items include:
The Federal Highway Administration (FHWA), Central Federal Lands Highway Division (CFLHD), anticipates awarding a Best Value- Tradeoff Approach construction contract in July 2026. The contract is anticipated to be under construction between August 2026 and November 2029.
The cost of the entire project is estimated to be between $35,000,000 and $45,000,000.
HI STP 360 HANA HIGHWAY BRIDGES is a federal acquisition solicitation issued by DEPARTMENT OF TRANSPORTATION. Review the full description, attachments, and submission requirements on SamSearch before the response deadline.
SamSearch Platform
AI-powered intelligence for the right opportunities, the right leads, and the right time.