    INDUSTRY DAY WEB MEETING FOR FIBER REINFORCED POLYMER (FRP) COMPOSITE GATES, BULKHEADS, AND VARIOUS LOCK COMPONENTS SUCH AS CONCRETE REBAR, PLATE, LADDERS, AND HANDRAIL FOR THE BRANDON ROAD INTERBASIN PROJECT (BRIP)

    Federal procurement opportunity
    Sol. W912EK26Z0001Special Notice
    Closed
    STATUS
    Closed
    closed Dec 2, 2025
    POSTED
    Nov 24, 2025
    Publication date
    NAICS CODE
    326199
    Primary industry classification
    PSC CODE
    Product & service classification

    AI Summary

    The US Army Corps of Engineers is hosting a virtual Industry Day on December 4, 2025, to discuss the fabrication and delivery of fiber reinforced polymer composite gates, bulkheads, and various lock components for the Brandon Road Interbasin Project. Interested parties are encouraged to provide feedback and attend to shape upcoming requirements.

    Contract details

    Solicitation No.
    W912EK26Z0001
    Notice Type
    Special Notice
    Posted Date
    November 24, 2025
    Response Deadline
    December 2, 2025
    NAICS Code
    326199AI guide
    Primary Contact
    Jake Anderson
    AI Product/Service
    both

    Description

    Description of Project:  The US Army Corps of Engineers, Rock Island District, is hosting a VIRTUAL Industry Day on Thursday, December 4, 2025, at 10:00 a.m. CST, regarding the fabrication and delivery of fiber reinforced polymer (FRP) valves, bulkheads, and many auxiliary components for the Brandon Road Lock and Dam (BRLD) megaproject (https://www.mvr.usace.army.mil/brip/).  The project will include the design, fabrication, and supply of the following fiber reinforced polymer (FRP) composite structures:

    • Two filling and emptying valves nominally 14 feet long by 14 feet tall.  These two valves are located at the upstream filling and emptying system, one on the land wall and one on the river wall.
    • Two filling and emptying bulkheads nominally 14 feet long by 14 feet tall.  These two bulkheads are located downstream of the upstream filling and emptying system.
    • Two flushing valves nominally 8 feet long by 8 feet tall and 12 inches thick. These two flushing valves are located just upstream of the FRP composite filling and emptying valves.
    • Two dam head gates nominally 16 feet long by 16 feet tall and 12 inches thick. These two head gates are located on the dam before the spillway section.
    • Auxiliary components include large quantities of FRP plate, concrete reinforcement/rebar, ladders, handrail, and other shapes that could be pultruded.

    The Government seeks feedback from engineers, manufacturers, and fabricators with experience overseeing similar projects, which will be used for planning purposes. Draft plans and specifications are forthcoming and will be provided through an amendment to this announcement.

    This Industry Day will be an excellent opportunity for contractors with the anticipated NAICS codes 326199, 325999, and 237990.  This effort is to help shape upcoming requirements and to virtually meet the USACE team. Manufacturing, Construction and Engineering firms with experience in the design and fabrication of bulkheads are highly encouraged to attend. There will also be discussion where the Government will be seeking feedback regarding design, fabrication, delivery, USACE or contractor installation, and site preparation for this work.

    ADDITIONAL Information Required:

    All interested parties must contact Contract Specialist Jake Anderson at jake.t.anderson@usace.army.mil and Contracting Officer Ryan Larrison at ryan.r.larrison@usace.army.mil No Later than 02DEC2025, 10:00AM CST, your email subjectline should be addressed as Industry Day Request (Company Name) – W912EK26Z0001, “Fiber Reinforced Polymer (FRP) Composite Gates, Bulkheads, and Various Lock Components such as Concrete Rebar, Plate, Ladders, and Handrail for the Brandon Road Interbasin Project (BRIP)” to ensure the request is handled in a timely manner.  

    Please provide your company information by filling out the excel spreadsheet labeled “2. Vendor Info Sheet”  and capability statements to Jake Anderson at jake.t.anderson@usace.army.mil and Ryan Larrison at ryan.r.larrison@usace.army.mil no Later than 02DEC2025, 10:00AM CST.

    All interested offerors are required to access SAM.gov for future updates.  The link to access the Industry Day Presentation will be sent via Email prior to 02DEC2025

    Failure to contact Jake Anderson and Ryan Larrison on the above date may result in your inability to attend the Industry Day for the Fiber Reinforced Polymer (FRP) Composite Gates, Bulkheads, and Various Lock Components such as Concrete Rebar, Plate, Ladders, and Handrail for the Brandon Road Interbasin Project (BRIP).

    A meeting recording will also be available upon request for those not able to attend live, please mention this in your email if able to attend or not.

    A round table discussion will be available at a later date upon request from . Send the request to Jake Anderson at jake.t.anderosn@usace.army.mil and Ryan Larrison at ryan.r.larrison@usace.army.mil. 

    Notes:

    DO NOT SUBMIT PROPRIETARY AND/OR BUSINESS CONFIDENTIAL DATA.

    NO REIMBURSEMENT WILL BE MADE FOR ANY COST ASSOCIATED WITH PROVIDING INFORMATION IN RESPONSE TO SAID NOTICE, ATTENDANCE AT THE INDUSTRY DAY EVENT OR ANY FOLLOW-UP INFORMATION SUBSEQUENTLY REQUESTD.

    Key dates

    1. November 24, 2025Posted Date
    2. December 2, 2025Proposals / Responses Due

    AI search tags

    Frequently asked questions

    INDUSTRY DAY WEB MEETING FOR FIBER REINFORCED POLYMER (FRP) COMPOSITE GATES, BULKHEADS, AND VARIOUS LOCK COMPONENTS SUCH AS CONCRETE REBAR, PLATE, LADDERS, AND HANDRAIL FOR THE BRANDON ROAD INTERBASIN PROJECT (BRIP) is a federal acquisition solicitation. Review the full description, attachments, and submission requirements on SamSearch before the response deadline.

    SamSearch Platform

    Stop searching. Start winning.

    AI-powered intelligence for the right opportunities, the right leads, and the right time.