The U.S. Army Corps of Engineers is seeking small business bidders for the F.E. Walter Dam Rehabilitation project in White Haven, PA, with a response deadline of February 10, 2025. The work includes repairing rocker bearings, replacing corroded anchor bolts, lubricating bearings, and addressing concrete spalls. Traffic control will be necessary as the project affects a service bridge adjacent to a public roadway.
24 January 2025
Action Code: Pre-Solicitation/Synopsis
Subject: Market Research – F.E. Walter Dam Repairs
Solicitation No.: W912BU25R0019 – F.E. Walter Dam Rehabilitation
Set-Aside Code: Small Business
Response Date: 10 February 2025
Place of Performance: White Haven, PA
The U.S. Army Corps of Engineers, Philadelphia District, intends to award a firm fixed contract to perform repair work of the Francis E Walter Dam located in White Haven, PA.
The FE Walter Dam repair work will consist of:
a. The rocker bearings at Pier 2 have rocked off their keeper key (Photographs and Inspection report to be provided with Solicitation). The bearings would be repaired by temporarily jacking the bridge girders, removing the existing anchor bolts, sliding the keeper plate back (or fabricate a new one, or modify the existing one), and reset the bearings.
b. The anchor bolts at the fixed bearings at pier 2 are corroded and have no washers (Photographs and Inspection report to be provided with Solicitation). Remove the nuts and install new nuts and washers.
c. Lubricate all bearings.
d. Numerous concrete spalls and delaminations are noted on the piers and abutments (Photographs and Inspection report to be provided with Solicitation). The deteriorated concrete will be removed and replaced with new concrete.
e. The deck is in satisfactory condition, but the top surface is moderately scaled (Photographs and Inspection report to be provided with Solicitation). A thin overlay will be applied to restore the surface and seal the deck from any water intrusion.
Traffic control is anticipated as all work will be conducted on a service bridge adjoining a public roadway. Although the physical bridge is considered a restricted area, the adjoining roadway will be open to public travel and construction activities will need to be given special consideration depending on the time of the year this work is conducted.
The Period of Performance is 180 calendar days. Work on the project is anticipated to begin 30 calendar days after contract award and completed 180 calendar days after commencement of work.
Solicitation Number W912BU25R0019 will be issued on or about 28 February 2025, with proposals due on or about 31 March 2025. The estimated cost range of this project is between $500,000 and $1,000,000.
The NAICS Code for this project is 237310 Highway, Street, and Bridge Construction and the small business size standard is $45 Million.
Responses to this Sources Sought Announcement will be used by the Government to make appropriate acquisition decisions. Narratives are requested with the following information, which shall not exceed a total of eight (8) pages.
Responses should be sent to Frederick Conway, at frederick.conway@usace.army.mil on or before February 10, 2025, at 2:00 PM EST.