Active SLED Opportunity · WASHINGTON · CITY OF SEATTLE

    26-014QP-FHWA AAC East Marginal Way Construction Management Services (FHWA)

    Issued by City of Seattle
    cityRFPCity of SeattleSol. 283684
    Open · 7d remaining
    DAYS TO CLOSE
    7
    due Aug 12, 2026
    PUBLISHED
    Jul 15, 2026
    Posting date
    JURISDICTION
    City of
    city
    NAICS CODE
    237310
    AI-classified industry

    AI Summary

    The City of Seattle seeks construction management services for the AAC East Marginal Way pavement preservation project, including key staff roles. The project involves a $11M construction contract with federal funding and requires expertise in urban infrastructure and federal standards. Proposals are due by August 12, 2026.

    Opportunity details

    Solicitation No.
    283684
    Type / RFx
    RFP
    Status
    open
    Level
    city
    Published Date
    July 15, 2026
    Due Date
    August 12, 2026
    NAICS Code
    237310AI guide
    Jurisdiction
    City of Seattle
    Agency
    City of Seattle

    Description

    Project Description:

    The City of Seattle, through Seattle Department of Transportation (SDOT), requests Statements of Qualifications, with the goal of contracting for the following key staff:

    1 full time Resident Engineer, 2 full time Construction Inspectors, ¾ time Change Order/Scheduling specialist, ½ time Office Engineer, ½ Doc Control/Contract Admin, and 1 part time Outreach support to provide Construction Management (CM) services on the AAC East Marginal Way project, as part of the overall CM team managing the construction contract for the project.

    AAC East Marginal Way

    The AAC East Marginal Way Project includes pavement preservation work (a 2" asphalt mill & overlay) on the southern portion of E Marginal Wy S. This pavement preservation project (a mill & overlay) is intended to extend the life of the existing pavement structure by 10 to 20 years. The project was awarded a $6.87M PSRC preservation grant. Scope of AAC work is typical of completed projects.  Base repairs, ADA curb ramps, Stormwater Code mandated drainage improvements, striping & signal loop restoration, and the final surfacing course will all covered by AAC.  Additional improvements and funding for those will be identified during the Complete Streets planning process.

    • Construction Contract Information Estimated construction contract value: $11 million
    • Estimated pre-construction services (contract document review): December 2026
    • Estimated construction duration: February 2027 – February 2028
    • Estimated construction closeout: February 2028 – July 2028

    Work will be accomplished in accordance with the FHWA reviewed project Plans and Specifications advertised for construction. 

    For additional project information, please see the project website:

    E Marginal Way S Paving and Safety Improvements - Transportation | seattle.gov

    The successful initiation and completion of this project are contingent on receiving federal funding.


    The Seattle Department of Transportation intends to execute the consultant construction management contract in December 2026, and the contract is expected to be completed in July 2028. Completion date may be extended if additional phases are added. Construction closeout is anticipated to last six (6) months.

    The City anticipates possibly awarding an initial contract amount of $2,000,000 and an initial duration of 2 years. The initial contract value and duration may be increased in varying contract dollar amounts and time. This project is anticipated to be federally funded in part through FHWA, administered in part through the Washington State Department of Transportation, and may be funded through other federal funds or Agencies.

     

    Project Details

    • Reference ID: 26-014QP
    • Department: Department of Transportation
    • Department Head: Adiam Emery (Interim Director)

    Important Dates

    • Questions Due: 2026-08-05T23:00:00.000Z
    • Pre-Proposal Meeting: 2026-07-23T20:00:00.000Z — https://teams.microsoft.com/l/meetup-join/19%3ameeting_YTEwODVlNjUtMzNiNi00YzVmLWIyYTAtZGZhZGIxNjFjZTc5%40thread.v2/0?context=%7b%22Tid%22%3a%2278e61e45-6beb-4009-8f99-359d8b54f41b%22%2c%22Oid%22%3a%224829c2f3-1ac9-46cc-934f-84c046bee391%22%7d

    Evaluation Criteria

    • Qualifications/Expertise of Proposed Project Manager & Key Personnel  (15 pts)

      (1) 

      Qualifications/Expertise of Proposed Project Manager & Key Personnel 

      15 points 

       

      (1a) 

      Project Manager 

      5 points 

       

      Provide a short resume of your proposed Project Manager. Describe how their background and experience align with the proposed project. Include (1) applicable licensures, (2) experience in their proposed role on this solicitation, (3) experience working on FHWA, FTA, and/or WSDOT funded projects, and (4) experience working with municipality or large urbanized transportation agencies. 

      (1b) 

      Key Personnel 

      10 points 

       
      1. Provide short resumes of your proposed Key Leads along with a table showing their availability/timeframes. Describe how their background and experience align with the proposed project. Include, if applicable, (1) applicable licensures, (2) experience in their proposed role on this solicitation, (3) experience working on FHWA, FTA, and/or WSDOT/state funded projects, (4) experience working with municipality or large urbanized transportation authorities, and (5) a concise list of projects within the past seven years comparable to the services required on this project. 

       

      1. Describe the capacity of the project team to support and complete the work as described. Include organizational depth demonstrating your team’s flexibility to provide staffing based on project demands, emergent project needs, and the anticipated availability of key individuals for the year of this project (prime and subconsultants). Consider the project team’s current and planned workload, and any concurrent SDOT projects to determine if staff are sufficiently available. Provide an organizational chart outlining the team’s structure and reporting relationship between individual team members. 
    • Qualifications/Expertise of Firm (45 pts)

      (2) 

      Qualifications/Expertise of Firm 

      45 points 

      (2a) 

      Resident Engineer’s Experience 

      10 points 

      Describe the Resident Engineer’s experience in a RE role on large urban construction projects, including at least one (1) FHWA funded project and one (1) project of $5M or greater. 

       

      (2b) 

      Inspectors’ Experience 

      10 points 

       

      Describe the Inspectors’ backgrounds and experience delivering projects in complex urban communities and experience on projects with federal funding. (10 Points) 

       

      (2c) 

      Schedule Review Expert Experience 

      5 points 

       

      Describe your Schedule Review Expert’s experience using schedule software such as Microsoft Project or other similar construction scheduling software on public works projects. 

       

      (2d) 

      Change Order Specialist Experience 

      5 points 

       

      Describe your Change Order Specialist’s experience reviewing, substantiating, and negotiating contractor’s change order proposals, along with their experience  writing change orders. 

      (2e) 

      Outreach Experience 

      5 points 

       

      Describe your teams Outreach Support experience on public works projects and on projects of similar size and duration. 

       

      (2f) 

      Office Engineering/Contract Admin Experience 

      5 points 

       

      Describe your Office Engineer/Document Control Specialist experience executing projects, similar to size and with FHWA or WSDOT funding, on behalf of a Public Agency that must comply with municipal code in executing the public works projects and its approach to monitoring cost and managing risk. 

       

      (2g) 

      Office Engineering/Document Control Experience 

      5 points 

       

      Describe your Office Engineer/Document Control Specialist specific background and experience verifying quantities and costs for multiple funding sources, creating/reviewing Field Construction Records for payment backup, creating/reviewing change order backup, and processing monthly Contractor progress payment estimates and processing submittals and RFI’s. 

       

    • Ability to meet schedule (15 pts)

      (3a) 

      Team Coordinator Experience 

      5 points 

      Describe your team’s experience in successful delivery and coordination on projects with a complex mix of internal and external stakeholders, including large public agencies such as WSDOT, SDOT, Seattle Public Utilities, Seattle City Light, King County Metro Transit and adjacent property owners, businesses, and the public. Give examples of issues you encountered and how you were able to successfully coordinate and stay on schedule. 

      (3b) 

       

      10 points 

      Describe your team’s experience with difficult contractors and how you ensure they stay on schedule during a long duration project.  Include examples of how a contractor’s schedule might be commented on if it’s showing delays, software that may be used for review, and any other approaches to ensure schedule compliance. 

    • Approach to Project (15 pts)

      (4a) 

      Cost Monitoring 

         10 points 

      1. Provide recommended approach to working with Discipline Leads to successfully complete the project (i.e. Planning, Design, Traffic Engineering, Environmental, etc.), including recommended approach to monitor and report project progress in relation to scope, schedule, budget, and change management. 

       

      1. Describe your team’s approach to cost monitoring, managing risk, and change order negotiation. Include your team’s recommended approach to monitor and report project progress in relation to scope, schedule, budget, and change management. 

       

      (4b) 

      Coordination 

          5 points 

      Describe your understanding of the project objectives and what you consider to be the critical success factors. Provide a recommended approach to successfully managing a multimodal corridor improvement project that involves extensive agency coordination. Include your team’s experience in successful coordination on projects with a complex mix of internal and external stakeholders, including large public agencies such as WSDOT, Seattle Public Utilities, Seattle City Light, Port of Seattle, Burlington Northern Santa Fe, Union Pacific, King County Metro Transit, and adjacent property owners, businesses, and the public.  Include your teams outreach support experience. 

    • Familiarity with WSDOT/FHWA standards (5 pts)

      Describe your proposed team’s familiarity with federal standards and describe your team’s specific experience with SDOT (or other large public agencies) as it relates to submittals, RFI’s, Design Changes, Change Order’s, Field Memos, Field Records, and payment supporting documentation on FHWA, WSDOT, FTA, or USDOT funded projects.

    • Approach to Voluntary FSBE goal (SBE plan) (5 pts)

      A. Describe the Prime Consultant’s approach to SBE outreach for this solicitation, noting that while the mandatory SBE goal is 0%, there is a 10% voluntary SBE goal. Provide a clear explanation of the efforts your team will undertake to demonstrate meaningful outreach. Also describe the methodology used in developing your SBE Participation Plan.
       B. Describe your approach to meaningfully engaging SBE firms, monitoring their performance, and supporting SBE commitments throughout the contract life in a way that reflects the full contract budget. A Directory of Certified SBE firms is available at: www.omwbe.wa.gov.

      C. List the SBE firms you are partnering with and the services you anticipate they will provide.

    • Interviews (100 pts)

    Submission Requirements

    • Consultant Questionaire (required)

      Please download the below documents, complete, and upload.

    • Letter of Interest (required)
      1. Page limit 1 single-sided, 8 ½ by 11 inches pages.
    • Proof of Legal Business Name (required)

      Provide a certificate or documentation from the Secretary of State in which you incorporated that shows your company legal name. Many companies use a “Doing Business As” name or nickname in daily business; the City requires the legal name for your company. When preparing all forms below, use the proper company legal name. Your company’s legal name can be verified through the State Corporation Commission in the state in which you were established, which is often located within the Secretary of State’s Office for each state. see http://www.secstate.wa.gov/corps/ for corporations and https://www.sos.wa.gov/corporations-charities for non-profits.

    • Federal Small Business Enterprise Requirements (required)

      Please download the below documents, complete, and upload.

    • Proposal Submittal (required)

      Please upload your complete proposal response excluding pricing. 

      Page limit 15 single-sided, 8 ½ by 11 inches pages.

      .

    • Indirect Cost Rate Information (required)

      The Consultant team is required to provide documentation of 48 CFR Part 31 of the Federal Acquisition Regulation compliant Indirect Cost Rates (ICR) if awarded this contract. For this submittal, the Prime Consultant must confirm that the proposed team all have a current ICR prepared or reviewed by WSDOT, or are participating in the WSDOT Safe Harbor program, or are currently working with WSDOT to obtain their ICR. Please confirm that the Prime Consultant has completed this ICR check by stating the following:

       

      [Prime Consultant] confirms that the proposed Consultant project team has current Indirect Cost Rate documentation. [Prime Consultant] has confirmed with the following Consultants: [Subconsultant 1, Subconsultant 2, Subconsultant 3, etc.]. 

    • References, Related Experience and Examples of Work (required)

      Please download the below documents, complete, and upload.

      Provide client references with phone numbers and emails for the projects listed above. Include previous program references, including at least one non-City of Seattle project reference. Specify the client, location, consultant firm members and participating individuals and role on team (principal, project director, etc.), type of work, implementation results or status, examples of work, and other relevant information as needed. References will not be scored but will be used to verify qualifications, which may affect the rating of the respondent. The City reserves the right to contact other references in addition to those provided by the respondent.

    • Certification Regarding Lobbying (required)

      Please download the below documents, complete, and upload.

      49 Code of Federal Regulations (CFR) Part 20.110 requires a signed certificate to be included with your submittal. To be considered responsive, submittals must contain a signed copy of the attached Federal Lobbying Certification and, if applicable, the Disclosure of Lobbying Activities form.

    • Debarment Certification (required)

      Please download the below documents, complete, and upload.

      This Agreement is a covered transaction for purposes of 49 CFR Part 29. As such, the Consultant is required to verify that the Consultant, its principals, as defined in 49 CFR 29.995, or affiliates, as defined at 49 CFR 29.905, are excluded or disqualified as defined in 49 CFR 29.940 and 29.945. The Consultant is required to comply with 49 CFR 29, Subpart C and must include the requirement to comply with 49 CFR 29, Subpart C in any lower tier covered transaction it enters into. To be considered responsive, submittals must contain a completed and signed copy of the attached Federal Debarment Certification.

    • Pricing Proposal (required)
    • Pricing (required)
      • Choose Option 1 when you have set line items, for example:
        • This is a quote for goods or commodities.
        • This is a public works bid, with a pricing table that can be uploaded into OpenGov Procurement from an Excel spreadsheet.
        • Seeking services for hourly rate schedules.
      • Choose Option 2 when you need vendors to provide you with the line items. 
    • Will this solicitation be awarded based on Evaluation Criteria/Committee? (required)

    Key dates

    1. July 15, 2026Published
    2. August 12, 2026Responses Due

    AI classification tags

    Frequently asked questions

    SLED stands for State, Local, and Education. These are solicitations issued by state governments, counties, cities, school districts, utilities, and higher education institutions — as opposed to federal agencies.

    SamSearch Platform

    Stop searching. Start winning.

    AI-powered intelligence for the right opportunities, the right leads, and the right time.