City of Orange, Texas seeks contractor for removal and replacement of a 600KW police department generator and ATS, including installation of new feeder and backup power provision during replacement. Project includes labor, materials, testing, and compliance with safety and restoration requirements.
SCOPE OF WORK
City of Orange, Texas
HMGP Contract No. Dr-4485
FEMA Project No. 0488
Police Department Generator
GENERAL
This contract provides for removal and replacement of the existing Police Department 600KW generator and ATS and all necessary appurtenances for the City of Orange, Texas.
SPECIFIC
This contract shall include all necessary labor, materials, equipment, tools, inspection, testing, and superintendence required for the proposed project as shown in the contract plans and specifications. This contract includes, but is not limited to the following:
1. 600 KW Generator. Furnish all labor materials and equipment to remove and replace the existing generator with a new 600KW diesel generator including disconnections and reconnections, testing and start up by the generator manufacturer and all necessary appurtenances, all in strict accordance with plans and specifications. Refer to Electrical Scope of Work.
2. Automatic Transfer Switch (ATS). Furnish all labor, materials and equipment to remove the existing ATS with a new ATS compatible to the new Generator including disconnections and reconnections, programming, testing and start up by the ATS manufacturer and all necessary appurtenances, all in strict accordance with plans and specifications. Refer to Electrical Scope of Work.
3. New Feeder. Furnish all labor, materials and equipment to install a new feeder, auxiliary power and controls between the new ATS and new Generator, including conduits and conductors, connections, testing, and all necessary appurtenances, all in strict accordance with plans and specifications. Refer to Electrical Scope of Work.
4. Backup Power. The contractor shall provide a backup generator of at least 600KW during the replacement of the existing generator and ATS. Refer to Electrical Scope of Work.
CONDITIONS ALONG THE ROUTES
The Contractor's attention is called to various physical conditions along the routes as follows.
1. The Contractor shall notify City personnel at least 72 hours before construction begins. The Contractor shall take precautions to avoid damage to foundations, existing equipment, and appurtenances. The Contractor shall observe all applicable OSHA and owner requirements while working near the electrical equipment.
2. Underground utilities exist near or within the project area. During construction the Contractor shall take the necessary precautions to avoid damaging the existing utilities within the limits of the project site.
SPECIAL REQUIREMENTS
1. The Contractor shall contact Mr. James Lawrence at 409-238-9108 prior to starting any work within the project site.
2. The Contractor shall restore all project locations to their original condition or better prior to the project completion.
3. Contractor to provide backup power during the replacement of the existing generator and ATS.
## Details **Bid/Project ID:** Bid No. 2026-04 **Type of Work:** Police Department Generator **Pre-Bid Location:** the City of Orange Neighborhood Facility Meeting Room, 303 N. 8th Street, Orange, Texas. **Pre-Bid Notes:** NON-MANDATORY **Bid Location:** the City of Orange, will be received at the office of the City Secretary, City Hall, 812 N. 16th Street Orange, Texas 77630. **Engineer/Publisher:** Schaumburg & Polk, Inc. (Beaumont) **Engineer Address:** 8865 College Street, Suite 100, Beaumont, Texas, 77707SLED stands for State, Local, and Education. These are solicitations issued by state governments, counties, cities, school districts, utilities, and higher education institutions — as opposed to federal agencies.