SLED Opportunity · FLORIDA · COUNTY OF LEVY
AI Summary
Levy County, Florida seeks proposals for purchase and installation of backup generators for an emergency shelter in a school building. Vendor or electrical engineer to determine generator configuration. RFP due by March 30, 2026.
The County is soliciting sealed proposals from qualified professional firms for purchase and installation of backup generator(s) for an emergency shelter located within a school building. The configuration of the generator(s) is to be determined by the vendor and/or an electrical engineer during the bid process. The generator(s) shall be installed with all accessories necessary for its operation.
Levy County is a local government entity governed by a Board of County Commissioners (the “Board” or “BOCC”) and administered by a County Manager. The County is approximately 1,413 square miles in size and has a population of approximately 46,000 (that includes 7 municipalities). The unincorporated area is largely rural with approximately 92.8% of the County’s Future Land Use being comprised of Natural Resources and Conservation (18%), Forestry/Rural Residential (42.4%) and Agricultural/Rural Residential (32.4%).
| Event | Date | Location |
|---|---|---|
| Proposal Opening | 2026-03-30T15:00:00.000Z | Levy County Government Center, 318 Mongo Street, Room C, Bronson, FL 32621 |
| County Commission Meeting - Authorize staff to negotiate with top firm(s) in ranked order & authorize Chair to sign the Contract | 2026-04-07T13:00:00.000Z | Levy County Government Center Auditorium, 310 School Street, Bronson, FL 32621 |
| Professional Services Committee Meeting to review and rank proposals | 2026-03-30T17:00:00.000Z | Levy County Government Center, 318 Mongo Street, Room C, Bronson, FL 32621 |
Please use the See What Changed link to view all the changes made by this addendum.
Proposer shall provide a written narrative explaining their intended approach and a proposed timeline for the completion of the Services with clear deadlines and specific action items identified for each phase of the project, including alternatives for providing effective stakeholder engagement and public participation and underrepresented members of our community.
Proposer shall describe basis for billing for the Services, such as a fixed fee for each Task or hourly rates with a not to exceed amount per Task. Please include time/cost for travel to public meetings. For Budget purposes, it is critical to the County to have a maximum cost for these Services.
Upload your proposal here.
Do not include any pricing information in your proposal.
Please download the below documents, complete, and upload.
Please download the below documents, complete, and upload.
Please download the below documents, complete, and upload.
Please download the below documents, complete, and upload.
Please download the below documents, complete, and upload.
Please download the below documents, complete, and upload.
By clicking "Please confirm", the proposal proposer, certifies that it is not:
Pursuant to section 287.135(5), Florida Statutes, the County may disqualify the proposal proper immediately or immediately terminate any agreement entered into for cause if the proposal proposer is found to have submitted a false certification as to the above or if the Contractor is placed on the Scrutinized Companies that Boycott Israel List, is engaged in a boycott of Israel, has been placed on the Scrutinized Companies with Activities in Sudan List or the Scrutinized Companies with Activities in the Iran Petroleum Energy Sector List, or has been engaged in business operations in Cuba or Syria, during the term of the Agreement. If the County determines that the proposal proposer has submitted a false certification, the County will provide written notice to the proposal proposer. Unless the proposal proposer demonstrates in writing, within 90 calendar days of receipt of the notice, that the County’s determination of false certification was made in error, the County shall bring a civil action against the proposal proposer. If the County’s determination is upheld, a civil penalty shall apply, and the proposal proposer will be ineligible to propose on any Agreement with a Florida agency or local governmental entity for three years after the date of County’s determination of false certification by proposal proposer.
As the person authorized to sign this statement, I certify that this firm complies fully with the above requirements.
Please download the below documents, complete, and upload.
Upload your SunBiz Registration here.
What are you purchasing? Select an option below.
Select one of the options below.
Will you contract be a:
Q (Cost Estimate): Is there a cost estimate or budget associated with this project?
A: Funding for this project has been established in the amount of $1,500,000.
Q (Pre-Proposal Meeting): Is it possible to schedule a site visit for 1pm on 3/17?
A: Unfortunately, we are not able to accommodate a site visit for any other time than 10am on 3/17.
Q (Optional brand): Will you accept Winco Generators and ASKO transfer switch
A: The specific equipment configuration and manufacturer will be determined by the proposing firm based on their recommended solution. The County currently utilizes Ring Power as its service provider; however, it is the responsibility of the proposing firm to confirm that the proposed generator and associated equipment can be serviced and supported by Ring Power or to identify an alternative qualified service provider capable of maintaining the system.
Q (Current loads): Is it possible to have the utility company supply the peak KW loads for the past year? This will aid in sizing the generator accurately.
A: Per discussions between County staff and Central Florida Electric, the peak load for the BMHS campus has been recorded at approximately 515 kW. Accordingly, any generator proposed for this project shall be sized to adequately meet or exceed this demand to ensure reliable operation under peak load conditions.
Q (Timeline): What if the project isn't finished by 12-31-26, and is completed 45 days after the deadline, will the contractor still be paid in full?
A: Funding is available only through December 31, 2026.
Q (Pre-bid meeting questions):
A: How is down time handled? What type of fence is required around the generator? Who will issue permits? Timeline? Downtime associated with the installation and operation of the generator shall be coordinated in advance with the school to minimize disruption to campus activities. The awarded vendor shall be responsible for the installation of a security fence enclosing the generator. All required permits for this project will be issued by the County. All work associated with this project must be fully completed no later than December 31, 2026.