Pasadena Water & Power seeks qualified contractors for the EV Charger Expansion Project at its Maintenance Yards, including construction and installation coordination of owner-furnished equipment.
Pasadena Water & Power (“PWP”) invites bids from qualified contractors to provide all labor, supervision, tools, equipment, materials, and incidentals necessary to construct the EV Charger Expansion Project at PWP Maintenance Yards in accordance with the Contract Documents.
The City has obtained the required construction permits. The Contractor shall perform all work in strict accordance with the approved design drawings and specifications included in this IFB.
Certain major equipment items will be furnished by the City under a separate procurement. The Contractor shall coordinate receipt, handling, installation, and commissioning of Owner-furnished equipment as defined in the Contract Documents.
Please use the See What Changed link to view all the changes made by this addendum.
The City has updated the answer to question #1.
Notice to Prospective Proposers
Part of the project is being funded by a U.S. Department of Housing and Urban Development Community Development Block Grant (CDBG). Therefore, the Contract is subject to certain federal requirements, including, but not limited to: Davis-Bacon Act prevailing wage regulations; The Build America, Buy America Act (BABA); and Section 3 requirements. See links below for details.
The complete set federal labor regulations and provisions conditions are located here: https://www.cityofpasadena.net/finance/wp-content/uploads/sites/27/HUD-Federal-Regulations-over-200k.pdf?v=1674593673378
The following forms must be summited with your response: https://www.cityofpasadena.net/finance/wp-content/uploads/sites/27/HUD-Federal-Forms-over-200k.pdf?v=1674593673378
Pasadena Water & Power (“PWP”) invites bids from qualified contractors to provide all labor, supervision, tools, equipment, materials, and incidentals necessary to construct the EV Charger Expansion Project at PWP Maintenance Yards in accordance with the Contract Documents.
The City has obtained the required construction permits. The Contractor shall perform all work in strict accordance with the approved design drawings and specifications included in this IFB.
Certain major equipment items will be furnished by the City under a separate procurement. The Contractor shall coordinate receipt, handling, installation, and commissioning of Owner-furnished equipment as defined in the Contract Documents.
We value your participation in this solicitation and want to ensure you have every opportunity to present your response in the manner instructed in this solicitation. It is important that you submit a complete response prior to 2:00 pm on Thursday, April 16, 2026 through this eProcurement portal. We strongly advise against waiting to within the last three days of the submittal deadline to begin working on your response. Starting early on your response increases time to:
Delaying your response may result in errors, or can cause you to miss the submission deadline. Either of which can negatively impact your submittal or cause your submittal to not be accepted.
See the "Timeline" in the Introduction section (#Instructions to Bidders). If there is a Mandatory pre-proposal meeting, bidders/proposers are required to attend at the time, date, and location included in the Timeline. If there is a Non-Mandatory pre-proposal meeting, bidders/proposers are not required to attend.
Each bidder/proposer will have the opportunity to clarify and ask questions regarding the Specifications. The Pre-Proposal Meeting will be held at the time, date, and location in the Timeline of this solicitation.
The quantities contained in the bid documents are approximate only and are for the sole purpose of comparing bids. The City may, in accordance with the specifications, order more or less equipment and/or materials as necessary at the City’s sole discretion. Payment will be made only for the amount of material actually provided, as determined by the City and accepted at the unit prices noted in the bid.
If this solicitation is issued by an Operating Company of the City of Pasadena including the Pasadena Center Operating Company; or Rose Bowl Operating Company; or Pasadena Community Access Corporation: In this solicitation, any reference to the City, shall actually refer to the PCOC, PRHB, or RBOC, or PCAC, e.g. "City" shall refer to the Operating Company, "City Council" to its Board of Directors, and "City Manager" to its Chief Executive Officer.
PWP invites bids from qualified contractors to provide all labor, supervision, tools, equipment, materials, and incidentals necessary to construct the EV Charger Expansion Project at PWP Maintenance Yards in accordance with the Contract Documents.
The City has obtained the primary construction permit for this project. The Contractor shall comply with all permit conditions and all applicable codes, regulations, and agency requirements.
The Contractor is responsible for securing and paying for all temporary permits, temporary utilities, jobsite facilities, storage permits, traffic control permits, and any permits required for construction operations, means, and methods, unless expressly identified as City-furnished.
The Contractor shall perform all work in strict accordance with the approved design drawings and specifications included in this IFB.
Certain major equipment items will be furnished by the City under a separate procurement. The Contractor shall coordinate receipt, handling, installation, and commissioning of Owner-furnished equipment as defined in the Contract Documents.
The work includes, but is not limited to, site preparation, civil construction, foundations, trenching, conduit installation, wiring, equipment setting, terminations, testing, restoration, and all related work necessary to deliver a complete and operational EV charging installation in accordance with the design documents.
The Contractor shall furnish all materials and equipment required for construction except for items expressly identified as Owner-furnished equipment. Any material or equipment not specifically listed as Owner-furnished shall be deemed Contractor-furnished.
Construction and Demolition Waste Management Ordinance - In addition to complying with all applicable federal, state and local laws and regulations, the Contractor shall take note of the specific requirements of the Construction and Demolition Waste Management Ordinance, Pasadena Municipal Code Chapter 8.62. The Contractor shall comply with all provisions of the Ordinance, as a material part of the work under this Contract in order to divert a minimum of 75% of the construction and demolition debris resulting from the work. The Waste Management Plan required by the Ordinance shall be submitted no later than fifteen (15) calendar days after the Contract award.
Pasadena has partnered with Green Halo Systems to receive and keep track of the construction and demolition waste management documents.
The Contractor shall not commence work until (1) the invoice payment has been made for both the Performance Security Deposit equal to 3% of the project value not to exceed $30,000, and the non-refundable Administrative Review Fee based on the City's General Fee Schedule available online at: www.cityofpasadena.net/finance/general-fund/fees-tax-schedules; and (2) the Waste Management Plan has been submitted through Green Halo and approved by the City's waste management compliance official.
The Contractor shall be required to certify compliance with the Construction and Demolition Waste Management Ordinance and provide required documentation during and at the end of the contract term. The refund of the Performance Security Deposit is subject to this compliance.
The cost to comply with the City's Construction and Demolition Waste Management Ordinance shall be included in the unit or lump sum prices for the applicable items of work listed in the Bidder's Proposal and no additional compensation will be allowed.
Failure to comply with any provisions of the Construction and Demolition Waste Management Ordinance, Pasadena Municipal Code Chapter 8.62 may result in forfeiture of the Performance Security Deposit.
Instructions
The contractor awarded the project will receive an invoice to pay the C&D administrative fee and C&D performance security deposit and an email with instructions to activate an account with Green Halo, complete the C&D plan and submit the weigh tickets of the receipt for the project.
To receive the Administrative Fee and C&D Performance Security Deposit Invoice and instructions to complete the C&D requirements in Green Halo, send an email to canddrecycling@cityofpasdena.netwith the following information.
• Project name
• Contract Number
• Email account of the person that will be assigned as the account holder in the Green Halo
For additional information visit the Construction and Demolition Debris Recycling webpage
The work described in this solicitation may be funded, in whole or in part, by the Federal Emergency Management Agency (FEMA).
All bidders are advised that this project is subject to the applicable terms, conditions, and requirements associated with FEMA-funded projects. These terms and conditions are included as an attachment to this solicitation and are hereby incorporated by reference. By submitting a bid, the bidder agrees to comply with all such FEMA-related requirements.
The prevailing wage rate provisions of Section 1770-1777 of the Labor Code and Section 7-2, entitled "Labor", of the Standard Specifications shall apply to this project. However, if there is a difference between the Pasadena Living Wage and Prevailing Wage rates for similar classifications of labor, the contractor and his subcontractors shall pay no less than the highest wage rate.
In responding to this request, all professional firms or contractors agree to comply with prevailing wage requirements, the Department of Industrial Relations, as further described below:
Contractor is aware of the requirements of California Labor Code Section 1720, et seq., and 1770, et seq., as well as California Code of Regulations, Title 8, Section 1600, et seq., (“Prevailing Wage Laws”), which require the payment of prevailing wage rates, that Contractor and all subcontractors must be registered and pay the registration fee with the Department of Industrial Relations (DIR), Contractor shall be subject to compliance monitoring and enforcement by the DIR, and the performance of other requirements on “Public Works” and “Maintenance” projects. If the services are being performed as part of an applicable “Public Works” or “Maintenance” project, as defined by the Prevailing Wage Laws, and if the total compensation is $1,000 or more, Contractor agrees to fully comply with such Prevailing Wage Laws.
The City retains all rights, title and interest in data and information input, uploaded, transmitted, or otherwise provided by or on behalf of the City into the vendor provided solution (“Organizational Data”). All Organizational Data shall remain the sole and exclusive property of the City. Vendor has no rights to use Organizational Data for any purpose other than to deliver the services contracted, unless otherwise authorized in writing by the City. Upon termination of any agreement between the City and vendor, the Organizational Data will be provided to the City, including uploaded documents and attachments, in an industry standard format such as csv, json or xml, or other agreed upon format at that time.
It is the bidders/proposers responsibility to examine the location of the proposed work, to fully acquaint themselves with the Specifications or Scope and the nature of the work to be done. The vendor shall have no claim against the City based upon ignorance of the nature and requirements of the project, misapprehension of site conditions, or misunderstanding of the specifications or contract provisions.
Screen Shots:
Instructions for the new eProcurement System: The following link will help you Get Started (https://opengov.my.site.com/support/s/article/c7a5affa-e073-4d5a-8d87-b6eadcf343a9) and will include vendor guides for using the system. Below are additional screen shots for support.
All Video Guides: OpenGov Procurement Vendor Training
This project requires adherence to the Section 3 labor compliance. Prospective bidder must include with their bid a Section 3 Economic Opportunity Plan on how to meet or exceed require Section 3 benchmarks. Failure to do may result in the forfeit of 5% of the project total cost.
Section 3 Benchmarks
- 25% of total labor hours worked by Section 3 workers; and
- 5% of total labor hours worked by Targeted Section 3 workers
A Section 3 Worker is defined as any worker who currently fits, or when hired within the past five years (not before
11/30/20) fit, at least one of the following categories, as documented:
Section 3 Targeted Worker is defined as:
Section 3 Business Concern is defined as a business that meets one of the following criteria within the last six months:
Bid security in the amount of five percent (5%) of the total bid price in the form of a surety bond, meeting City requirements, must accompany all bids. If the Bidder to whom the contract is awarded shall for fifteen (15) calendar days after such award fail or neglect to enter into the contract and file the required bonds, the City may deposit in its treasury said bid security and, under no circumstances, shall it be returned to the defaulting Bidder.
Electronic Bid bond is required. Bidders must submit all required information for the city to verify the bond with their bid . The bond must meet the following requirements and characteristics: A bid security in the amount of five percent (5%) of the total bid price in the form of a redeemable or callable electronic surety bond, meeting City requirements, must accompany all bids.
Bid Bond Instruction:
Use the following when trying to setup a bid bond for the City of Pasadena: The Project ID of the solicitation on which you are bidding. Your Contractor Vendor ID which is your Federal Tax ID or it’s equivalent. Both fields are required for validation. If you are having trouble finding these ID’s, please contact Surety2000 at 1-800-660-3263 or email help@surety2000.com
If a vendor ID has not been assigned, vendor can use their company EIN in the Contractor Vendor ID field in Surety2000.com.
Return of bid securities.
The city shall retain the bid security of the successful bidder until after execution of the contract and approval of the bonds or other security furnished by the bidder for the faithful performance of the contract or purchase order. Once a contract is fully executed, a notification will be sent to all bidders from the eProcurement system, at which time bidders can release their bond for this solicitation.
Except as otherwise provided under 41 CFR Part 60, to the extent this Agreement meets the definition of a "federally assisted construction contract" as set forth in 41 CFR Part 60-1 3 Locality agrees at all times during the term of this Agreement to comply with and abide by the following: (i) the equal opportunity clause (" Equal Opportunity Clause") in 41 CFR 60-1.4(b) in accordance with Executive Order 11246, as amended by Executive Order 11375 and that the Equal Opportunity Clause is a part of this Agreement and incorporated herein by this reference; and (ii) the regulations implementing the Equal Opportunity Clause at 41 CFR Part 60 and that such implementing regulations are a part of this Agreement and incorporated herein by this reference.
Bids will be received via the City's eProcurement Portal (https://procurement.opengov.com/portal/pasadena). A bid received after the time set for the bid opening shall not be considered. Bidders are required to submit (upload) all items listed in the Submittals/Checklist. Bids will be received prior to 2:00 pm on Thursday, April 16, 2026 and will be opened online at that time.
Copies of the Specifications and all required forms may be obtained for this solicitation online: https://procurement.opengov.com/portal/pasadena/projects/237062
Addenda shall be acknowledged via the City's eProcurement Portal. Refer to the Specifications for complete details and bidding requirements. The Specification and this Notice shall be considered a part of any contract made pursuant thereunder.
The vendor provided solution must keep all data and information within the United States, including when information is stored as part of a backup, unless otherwise authorized in writing by the City.
Policy - The City of Pasadena is committed to a policy of Equal Employment:
Compliance – To the extent permitted by law, Contractor expressly agrees to establish compliance with the Equal Employment Opportunity Practices Provisions of Chapter 4.08 of the Pasadena Municipal Code, and the Rules and Regulations adopted pursuant to said ordinance.
The successful bidder or proposer may be required to submit documentation during the term of the contract to evidence on going compliance with the City’s Equal Opportunity Practices Provisions. Such documentation may include, but not be limited to certified payroll records and Current Permanent Workforce Utilization reports.
Required Forms – Each bidder or proposer must submit a completed Form AA-1. Failure to submit this form will result in automatic disqualification with no exceptions unless bidder or proposer has an approved Form on file with the City.
Questions regarding Chapter 4.08 of the Pasadena Municipal Code and regulations adopted pursuant thereto should be directed to the Department of Finance, Purchasing Division 626.744.6755.
Attention is directed to Chapter 12.24 of the PMC, Excavations, and the Board of Directors (City Council) Policy Statement in Motion 25405 dated September 5, 1967. In general, all streets shall be free and clear of excavations and other construction during the period of November 15th through January 3rd for business districts, and December 15th through January 3rd for other areas. Accordingly, the Contractor will be required to shut down construction operations which would impede traffic movement during this period unless otherwise directed by the Engineer in emergency situations. Any existing excavations shall be backfilled, compacted, and temporarily repaved before the shutdown date. Bidders should reflect any costs of such shutdown in the various items of the Bidder's Proposal, and no additional payment will be allowed therefor. No time will be charged against the contract time for operations which are shut down in accordance with this section. A map showing the appropriate shutdown period for all locations in the City is available at the public counter of the City's Permit Center at 175 Garfield Avenue, Pasadena, 91101.
No contractor or subcontractor may be awarded a contract for public work on a public works project unless registered with the Department of Industrial Relations pursuant to Labor Code section 1725.5.
This project is subject to compliance monitoring and enforcement by the Department of Industrial Relations.
The Contractor’s scope of work is defined by and shall conform to the design drawings, technical specifications, panel schedules, and attachments included in this IFB. These documents are incorporated by reference and shall govern over narrative descriptions. The Contractor is responsible for reviewing all Contract Documents prior to bidding.
Normal Business Hours are Monday through Thursday every other Friday 8:00 a.m. until 4:30 p.m. unless specifically requested by the contract administrator, no deliveries shall take place on Saturday, Sunday, or holidays recognized by the City of Pasadena.
See the schedule for closed Fridays: https://www.cityofpasadena.net/planning/scheduled-city-closure-9-80-plan/.
SHIPPING, STORAGE, AND HANDLING
The Vendor shall assume all responsibility for the safe delivery of THE MATERIALS shipped to its destination. The materials shall be protectively packaged for shipment to mitigate the risks to handling such as impacts, atmospheric conditions such as excessive heat and moisture control, and any other shipping risks.
By submitting a response, each vendor expressly agrees to and accepts the following conditions:
The City will procure certain major electrical equipment under a separate equipment contract. Owner-furnished equipment is limited to the items specifically identified in the Owner-Furnished Equipment Schedule included in the IFB.
The City is issuing a clarified Owner-Furnished Equipment Schedule for this project.
Bidders shall rely on the revised Owner-Furnished Equipment Schedule attached to this Addendum for the complete list of Owner-Furnished Equipment.
Revised Owner-Furnished Equipment Schedule
DC Fast Charging (“DCFC”) Equipment
Level 2 EV Charging Equipment
Electrical Switchgear, Transformers, and Communications Equipment
SWBD-C, SWBD-D, and SWBD-E
XFMR-C, XFMR-D, and XFMR-E
COMMUNICATIONS
Associated DCFC components shall be considered Owner-Furnished only to the extent they are included in the manufacturer’s supplied equipment package or are expressly identified in the Owner-Furnished Equipment Schedule. All other materials, equipment, appurtenances, incidentals, and work necessary to provide a complete and fully operational installation, and not expressly identified as Owner-Furnished Equipment, shall be Contractor-Furnished and Installed. This includes, but is not limited to, conduits, raceways, site wiring, terminations, grounding, foundations, supports, and all other balance-of-system work. The IFB states that certain major equipment items will be furnished by the City under separate procurement and that the Contractor shall coordinate receipt, handling, installation, and commissioning of Owner-furnished equipment.
The Contractor shall:
All other materials, accessories, hardware, fittings, and components required for installation shall be Contractor-furnished, even if not explicitly shown or enumerated.
Owner-Furnished Equipment Care
The Contractor assumes responsibility for custody, protection, and proper installation of Owner-furnished equipment upon delivery to the site. Damage resulting from improper handling, storage, or installation shall be corrected at the Contractor’s expense.
The vendor provided solution must protect and secure all data and information input to the system, including documents and attachments. Information must be protected by AES 128-bit or greater encryption. Information must be encrypted in transit between the solution and the user’s web browser. The solution must encrypt all data stored at rest, including on disk, within databases and when information is maintained external to the solution, such as part of a backup or a data export, unless otherwise authorized in writing by the City.
Bids will be evaluated based on the lowest Grand Total Price submitted in the Bidders' Proposal. The contract award will be made from among responsive and responsible bidders. In case of a discrepancy between the unit prices and item total, the unit price shall govern. In the event of a discrepancy between the item totals and the grand total price the item totals shall prevail. The prices will be subject to adjustment by the City on that basis in the event of discrepancy and bid awarded.
a. All transactions regarding this contract shall be done in compliance with the Davis-Bacon Act (40 U.S.C. 3141- 3144, and 3146-3148) and the requirements of 29C.F.R. pt. 5 as may be applicable. The contractor shall comply with 40 U.S.C. 3141-3144, and 3146-3148 and the requirements of 29 C.F.R. pt. 5 as applicable. b. Contractors are required to pay wages to laborers and mechanics at a rate not less than the prevailing wages specified in a wage determination made by the Secretary of Labor. c. Additionally, contractors are required to pay wages not less than once a week.
Technical support for an eProcurement system plays a vital role in ensuring smooth operations. You can call or email technical support using the information below.
In addition to complying with all applicable federal, state and local laws and regulations, the Contractor shall take note of the specific requirements of the Stormwater Management and Discharge Control, Pasadena Municipal Code Chapter 8.70. The Contractor shall comply with all provisions of the Stormwater Management and Discharge Control Ordinance, also known as NPDES Requirements, as a material part of the work under this Contract.
This form is only applied for formal solicitations $75,000 or more. The City requires that each bidder or proposer executes and submits to the City with the Bid/Proposal, the attached Declaration of Non Collusion in the section named "Submittals/Checklist."
See the Timeline in the section named "Instructions to Bidders." If there is a Mandatory pre-bid meeting, bidders are required to attend at the time, date, and location included in the Timeline (#Instructions to Bidders) of this solicitation. If there is a Non-Mandatory pre-bid meeting, bidders not required to attend.
Each prospective bidder will have the opportunity to clarify and ask questions regarding these Specifications. The Pre-bid Meeting will be held at the time, date, and location in the Timeline of this solicitation.
No contractor or subcontractor may be listed on a bid proposal for a public works project unless registered with the Department of Industrial Relations pursuant to Labor Code section 1725.5 [with limited exceptions from this requirement for bid purposes only under Labor Code section 1771.1(a)].
Bidder must bid on all materials and supplies listed in the Bidder’s Proposal (Market Basket). The City anticipates the order amount of the items listed in the Bidder’s Proposal. However, the City of Pasadena does not imply nor make any commitment to purchase a specific quantity. The City may increase or decrease the quantities based on the current requirements, and the contractor agrees to furnish more or less of the items stated in the Bidder’s Proposal. Additional varieties of the materials and supplies may be ordered as a result of this bid. Award of contract shall be based upon the grand total price contained in the Bidder’s Proposal.
The Market Basket in this solicitation is established to represent TBD of the total estimated value of the contract to be awarded. Prices for the remaining materials and supplies for this solicitation are represented by dollar value in the Grand Total, they will be a part of the market basket analysis when determining the low bidder.
MOST FAVORED CUSTOMER: Contractor agrees to treat the City as its most favored customer. Contractor represents that all of the prices, warranties, benefits and other terms being provided hereunder are equivalent to or better than the terms being offered by Contractor to its current customers. The City shall be entitled to any and all other services normally offered by the Contractor (and/or manufacturer through the Contractor) to its customers.
CATALOG PRICING: While the materials and supplies listed in this solicitation represent a majority of the materials and supplies needed, there is a small percentage of items that are unknown at this time. Therefore, bidders are required to, in addition to providing pricing for all materials and supplies, submit a catalog with all available supplies or materials for future purchasing consideration as a part of this overall contract with their bid. Catalog information must include per unit pricing.
In the event vendor receives a subpoena, court order, or other legal process requesting access to or disclosure of any Organizational Data, the vendor shall promptly notify the City in writing, unless legally prohibited from doing so, and shall cooperate with City in seeking a protective order or other appropriate remedy. Any disclosure of Organizational Data in response to legal process must be authorized in writing by the City, unless prohibited by law.
A sample of the contract the successful vendor will be required to enter into with the City is attached hereto and by this reference incorporated herein and made part of this solicitation.
The City has obtained the primary construction permit for this project. The Contractor shall comply with all conditions of the permit and all applicable agency requirements.
The Contractor is responsible for securing and paying for all temporary permits, temporary utilities, jobsite facilities, storage permits, traffic control permits, and any other permits required for construction operations or means and methods.
Failure to obtain required temporary permits shall not relieve the Contractor of responsibility for timely completion of the work.
In addition, the Contractor shall adhere to NPDES (National Pollution Discharge Elimination System) Best Management Practices to prevent deleterious materials or pollutants from entering the City or county storm drain systems, including, but not limited to implementing the Best Management Practices specified below, and the Contractor shall comply with all directions of the City in this regard during construction:
The following shall be implemented:
All federal financial assistance recipients must have a Unique Entity ID (UEI) number registered with the System for Award Management (SAM) database at SAM.gov. Prior to award, the successful Bidder must provide proof of SAM registration. This proof may be submitted with the Bid. Vendors seeking to register can register for free at the following link: https://sam.gov/content/entity-registration. The SAM registration process may take several business days to complete. Therefore, the city recommends that the Bidder begin the registration process if bidder has not done so already.
a. Standard. Recipient and subrecipient contracts must include a provision for compliance with the Copeland “Anti-Kickback” Act (40 U.S.C. 3145), as supplemented by Department of Labor regulations (29 CFR Part 3, “Contractors and Subcontractors on Public Building or Public Work Financed in Whole or in Part by Loans or Grants from the United States”). b. Applicability. This requirement applies to all contracts for construction or repair work above $2,000 in situations where the Davis-Bacon Act also applies. It DOES NOT apply to the FEMA Public Assistance Program. c. Requirements. If applicable, the non-federal entity must include a provision for compliance with the Copeland “Anti-Kickback” Act (40 U.S.C. § 3145), as supplemented by Department of Labor regulations at 29 C.F.R. Part 3 (Contractors and Subcontractors on Public Building or Public Work Financed in Whole or in Part by Loans or Grants from the United States). Each contractor or subrecipient must be prohibited from inducing, by any means, any person employed in the construction, completion, or repair of public work, to give up any part of the compensation to which he or she is otherwise entitled. The non-Federal entity must report all suspected or reported violations to FEMA. Additionally, in accordance with the regulation, each contractor and subcontractor must furnish each week a statement with respect to the wages paid each of its employees engaged in work covered by the Copeland Anti-Kickback Act and the Davis Bacon Act during the preceding weekly payroll period. The report shall be delivered by the contractor or subcontractor, within seven days after the regular payment date of the payroll period, to a representative of a Federal or State agency in charge at the site of the building or work.
Following award of the Contract, PWP will schedule a pre-construction meeting. The Contractor’s project manager, superintendent, and major subcontractors shall attend.
Bidders shall propose the number of Working Days required to achieve Substantial Completion of the project. The proposed duration shall be stated in the Bid Proposal and shall not exceed one hundred twenty (180) Working Days.
The accepted proposed duration will become the Contract Time and will be incorporated into the Contract.
Prior to commencing on-site work, the Contractor shall submit a detailed construction schedule for review and acceptance by the City. The schedule shall identify major activities, milestones, inspections, equipment installation, commissioning, and anticipated completion dates. City review of the schedule shall not relieve the Contractor of responsibility for completing the work within the Contract Time.
Time is of the essence. Failure to achieve Substantial Completion within the Contract Time shall subject the Contractor to liquidated damages as specified in the Contract Documents.
Bids will be evaluated based on the lowest Grand Total Price submitted in the Bidders' Proposal for each Group. Each Group will be evaluated and awarded independently based on the lowest Grand total Price for each Group. Bidders may bid on any combination of the Groups below. Bidders are required to bid on all line items listed within the specific Group they select. Failure to bid on all line items for a selected Group or Groups may result in rejection of the bid(s).
False, incomplete or unresponsive statements in connection with the bid may be sufficient cause for rejection of a bidder/proposer.
a. Contractor. The contractor shall comply with 18 U.S.C. § 874, 40 U.S.C. § 3145, and the requirements of 29 C.F.R. pt. 3 as may be applicable, which are incorporated by reference into this contract. b. Subcontracts. The contractor or subcontractor shall insert in any subcontracts the clause above and such other clauses as FEMA may by appropriate instructions require, and also a clause requiring the subcontractors to include these clauses in any lower tier subcontracts. The prime contractor shall be responsible for the compliance by any subcontractor or lower tier subcontractor with all of these contract clauses. c. Breach. A breach of the contract clauses above may be grounds for termination of the contract, and for debarment as a contractor and subcontractor as provided in 29 C.F.R. § 5.12.”
Any additional work identified during the course of the project that is deemed necessary, but outside the original Scope of Services, must be recorded as a Change Order and approved by the City in writing before work is started.
Build America, Buy America Act or BABA requires any “infrastructure project” exceeding a total project cost of $250,000 in Community Development Block Grant or HOME Investment Partnership Act apply a domestic content procurement preference, meaning that all iron, steel, manufactured products, and construction materials used in the infrastructure project must be produced in the United States, unless the awarding agency has issued a waiver of this requirement. Public infrastructure projects in the United States, which includes, at a minimum: the structures, facilities, and equipment for roads, highways, and bridges; public transportation; dams, ports, harbors, and other 6 maritime facilities; intercity passenger and freight railroads; freight and intermodal facilities; airports; water systems, including drinking water and wastewater systems; electrical transmission facilities and systems; utilities; broadband infrastructure; and buildings and real property; and structures, facilities, and equipment that generate, transport, and distribute energy including electric vehicle (EV) charging.
The vendor shall not permit the storage of City data and information on vendor mobile or removable devices (e.g. laptops, USB drives, removable drives, optical disks, etc.) except for limited purpose and duration, and only if authorized in writing by the City. Any such use also requires that vendor meets the data security requirements as noted above, ensuring that all storage on mobile or removable devices is appropriately encrypted and protected.
Parties interested in responding are required to submit electronically through the City of Pasadena's eProcurement Portal prior to 2:00 pm, Thursday, April 16, 2026. Please upload all required documents as instructed in the section named Submittals/Checklist sufficiently early electronically through the city's eProcurement Portal before the time and day listed in this solicitation. Responses must be received in the system prior to the deadline.
The Specification or Scope of Work included in this Notice shall be considered part of any contract made pursuant thereunder.
Bidders must possess and provide the following license(s) or certification(s) to be deemed qualified to perform the work specified:
Class A – General Engineering; OR B – General Building; OR C-10 Electrical Contractor
The Contractor shall furnish all labor, materials, equipment, and incidental items necessary to provide a complete and operational installation consistent with the Contract Documents.
Materials or work reasonably inferable from the drawings, specifications, and attachments as necessary for proper construction and operation shall be included in the bid, even if not specifically enumerated.
This requirement does not shift design responsibility to the Contractor but obligates the Contractor to provide all components required to construct the project as designed.
Electronic Bid bond is required. Bidders must provide all required information for the City to verify the bond with their bid. The bond must meet the following requirements and characteristics: Bid security in the amount of five-percent (5%) of the total bid price in the form of a redeemable or callable electronic surety bond, meeting City requirements, must accompany all bids.
Bid Bond Instruction:
Bidders must provide all required information for the City to verify the bond with their bid. The bond must meet the following requirements and characteristics: Bid security in the amount of five percent (5%) of the total bid price in the form of a redeemable or callable electronic surety bond, meeting City requirements, must accompany all bids. If the Bidder to whom the contract is awarded shall for fifteen (15) calendar days after such award fail or neglect to enter into the contract with the required insurance documentation, submit the Construction & Demolition Waste Management Plan, and file the required bonds, the City may deposit in its treasury said bid security and, under no circumstances, shall it be returned to the defaulting Bidder. Failure to return signed contract with all the attachments stated above may result in having the project awarded to the next lowest bidder.
Here is what bidders must provide to their bonding agent when trying to setup a bid bond for the City of Pasadena: The Project ID of the solicitation on which you are bidding. Your Contractor Vendor ID which is your Federal Tax ID or it’s equivalent. Both fields are required for validation. If you are having trouble finding these ID’s, please contact Surety2000 at 1-800-660-3263 or email help@surety2000.com
To the extent this Agreement is in excess of $100,000 and involves the employment of mechanics or laborers, Locality agrees at all times during the term of this Agreement to comply with and abide by the terms of the Contract Work Hours and Safety Standards Act, codified at 40 U.S.C. 3701 et seq., as supplemented by regulations at 29 CFR Part 5, and that such terms and regulations are a part of this Agreement and incorporated herein by this reference.
Upon termination of this agreement, or upon written request by the City, the vendor shall permanently delete all City data and information from its systems, including backups and any other repositories under vendor's control, within thirty (30) days, unless retention is required by law or authorized in writing by the City. Deletion must include all documents, attachments, and any derivative data, and shall be performed in accordance with recognized industry standards for secure data erasure. Upon completion of data deletion, the vendor shall provide the City with written certification confirming the destruction of all relevant data.
The City of Pasadena is committed to promoting the economic health and well being of its residents. To this end, contractor agrees to recruit Pasadena residents initially and to give them preference, if all other factors are equal, for any new positions that result from the performance of this contract and which are performed within the City.
The City reserves the right to change any part of these Instructions to Vendors and Specifications any time prior to the submittal deadline. Any changes shall be in the form of addenda and will become a part of the solicitation documents and of the contract. Addenda shall be made available to each vendor. A bidder's/proposer's failure to address the requirements of the addenda may result in the bid not being considered. If the City determines that a time extension is required for the solicitation, the addenda will give the new submission date.
Addenda shall be acknowledged via the City's eProcurement Portal.
The contract shall be awarded to the lowest responsive and responsible bidder. In determining whether a bidder is responsible and responsive, the following shall be considered:
Any Bidder or Proposer may withdraw their response via the City's eProcurement Portal prior to 2:00 pm on Thursday, April 16, 2026.
The regulation at 29 C.F.R. § 5.5(b) provides contract clause language concerning compliance with the Contract Work Hours and Safety Standards Act. (1) Overtime requirements. No contractor or subcontractor contracting for any part of the contract work which may require or involve the employment of laborers or mechanics shall require or permit any such laborer or mechanic in any workweek in which he or she is employed on such work to work in excess of forty hours in such workweek unless such laborer or mechanic receives compensation at a rate not less than one and one-half times the basic rate of pay for all hours worked in excess of forty hours in such workweek. (2) Violation; liability for unpaid wages; liquidated damages. In the event of any violation of the clause set forth in paragraph (b)(1) of this section the contractor and any subcontractor responsible therefor shall be liable for the unpaid wages. In addition, such contractor and subcontractor shall be liable to the United States (in the case of work done under contract for the District of Columbia or a territory, to such District or to such territory), for liquidated damages. Such liquidated damages shall be computed with respect to each individual laborer or mechanic, including watchmen and guards, employed in violation of the clause set forth in paragraph (b)(1) of this section, in the sum of $27 for each calendar day on which such individual was required or permitted to work in excess of the standard workweek of forty hours without payment of the overtime wages required by the clause set forth in paragraph (b)(1) of this section. (3) Withholding for unpaid wages and liquidated damages. The (write in the name of the Federal agency or the loan or grant recipient) shall upon its own action or upon written request of an authorized representative of the Department of Labor withhold or cause to be withheld, from any moneys payable on account of work performed by the contractor or subcontractor under any such contract or any other Federal contract with the same prime contractor, or any other federally-assisted contract subject to the Contract Work Hours and Safety Standards Act, which is held by the same prime contractor, such sums as may be determined to be necessary to satisfy any liabilities of such contractor or subcontractor for unpaid wages and liquidated damages as provided in the clause set forth in paragraph (b)(2) of this section. (4) Subcontracts. The contractor or subcontractor shall insert in any subcontracts the clauses set forth in paragraph (b)(1) through (4) of this section and also a clause requiring the subcontractors to include these clauses in any lower tier subcontracts. The prime contractor shall be responsible for compliance by any subcontractor or lower tier subcontractor with the clauses set forth in paragraphs (b)(1) through (4) of this section.
General
The Contractor shall be responsible for coordinating and performing commissioning of the EV charging equipment and associated electrical infrastructure in accordance with the Contract Documents.
Commissioning shall include inspection, verification, functional testing, and documentation necessary to demonstrate that the installed systems operate as intended.
Coordination with Owner-Furnished Equipment Vendors
For City-furnished EV chargers and major electrical equipment, the Contractor shall coordinate with the manufacturer or vendor for startup and commissioning activities.
The Contractor shall provide all labor, tools, temporary power, terminations, network connections, and site access necessary to support manufacturer startup and testing.
Minimum Commissioning Requirements
Commissioning shall include, at a minimum:
Documentation
The Contractor shall provide commissioning reports documenting all tests performed, results obtained, and any corrective actions taken. Commissioning documentation shall be submitted prior to Substantial Completion.
The vendor shall fully disclose any use of Artificial Intelligence (AI), Machine Learning (ML), or automated decision-making technologies within the proposed solution. This includes, but is not limited to, the specific functions where AI is used, the nature of the AI model (e.g., predictive, generative, or rule-based), and whether the AI is proprietary, third-party, or open-source. The vendor shall also disclose whether any AI models are shared across multiple customers or tenants. The City reserves the right to approve or reject the use of AI components based on risk, transparency, and alignment with City policies.
The City reserves the right to change any part of these Instructions and Specifications any time prior to the bid opening. Any changes shall be in the form of addenda and will become a part of the bid documents and of the contract. Addenda shall be made available to each Bidder or Proposer. A Bidder's or Proposer's failure to address the requirements of the addenda may result in the response not being considered. If the City determines that a time extension is required for the bid, the addenda will give the new submission date.
Addenda shall be acknowledged via the City'seProcurement Portal for the project named "MAINTENANCE YARDS EV CHARGER EXPANSION." Project ID: 2026-IFB-LM-0141. Bidders or Proposers can view a list of addenda released by the City by clicking on "Addenda & Notices." While drafting a response, there is a section for "Addenda Confirmation" where Bidders or Proposers must acknowledge each addenda released.
The deadline to submit questions related to this solicitation is Thursday, April 2, 2026, prior to 2:00 pm.
Questions regarding this solicitation should be submitted directly through the City's eProcurement Portal Q&A function. Do not contact any other City employee or official regarding this solicitation. Any questions submitted after the date and time specified may not be considered.
In connection with contracts related to the subject “Bidder’s Proposal,” and except as otherwise provided below, all work shall be done in accordance with the provisions of the 2018 edition of “STANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION” (commonly known as the “GREENBOOK”), Including Supplements, prepared and promulgated by Public Works Standards, Inc., a mutual benefit corporation. The Pasadena Department of Public Works has published a booklet titled, “SUPPLEMENTS AND MODIFICATIONS TO THE ‘GREENBOOK’ (STANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION)” dated September 2006, hereinafter referred to as the Pasadena Supplements. The provisions of these Specifications and the Pasadena Supplements shall apply and take precedence over the Greenbook, in that order of precedence. The Pasadena Supplements and the “Greenbook” are available online at: https://www.cityofpasadena.net/public-works/wp-content/uploads/sites/29/Pasadena-Recurring-Supplements-2023.pdf?v=1684796778799. All references in these Specifications to “Standard Specifications” shall mean the Pasadena Supplements and the Greenbook, taken together.
Section 9-3 of the “STANDARD SPECIFICATION FOR PUBLIC WORKS CONSTRUCTION” is hereby replaced with the following: Payment will be made when invoice has been submitted upon the completion this project.
The vendor shall not use any City data or information to train, fine-tune, or otherwise improve any AI or ML models, whether proprietary, third-party, or public, without the City’s express written consent. This includes a prohibition on using City data for training public or shared models. If AI models are used, the vendor must ensure City data is excluded from any datasets used for model development or refinement unless explicitly authorized in writing by the City.
1. The contractor agrees to comply with all applicable standards, orders or regulations issued pursuant to the Clean Air Act, as amended, 42 U.S.C. § 7401 et seq. 2. The contractor agrees to report each violation to the (name of applicant entering into the contract) and understands and agrees that the (name of the applicant entering into the contract) will, in turn, report each violation as required to assure notification to the Federal Emergency Management Agency, and the appropriate Environmental Protection Agency Regional Office. 3. The contractor agrees to include these requirements in each subcontract exceeding $150,000 financed in whole or in part with Federal assistance provided by FEMA.
Awarded bidder or proposer may be required to obtain and pay for any required business license under Title 5 of the Pasadena Municipal Code.
For further information contact Municipal Services Department at (626) 744-4166, Monday-Friday between 7:15 am and 5:15 pm. Additional Information regarding business license fees can be found here: https://www.cityofpasadena.net/finance/licenses/business-licenses/
The deadline to submit questions related to this solicitation is Thursday, April 2, 2026, prior to 2:00 pm.
Questions regarding this solicitation should be submitted directly through the City's eProcurement Portal Q&A function. Do not contact any City employee or official regarding this solicitation. Any questions submitted after the date and time specified may not be considered.
Release Dated: Wednesday, March 11, 2026
MIGUEL MÁRQUEZ
City Manager
All responses accepted by the City at the time of bid opening shall become the exclusive property of the City. Upon opening, all bids accepted by the City shall become a matter of public record and shall be regarded as public, with the exception of those elements of each bid which are identified by the bidder as business or trade secrets and plainly marked as "trade secret," "confidential," or "proprietary." Each element of a bid which a bidder desires not to be considered a public record must be clearly marked as set forth above, and any blanket statement (i.e., regarding entire pages, documents, or other non-specific designations) shall not be sufficient and shall not bind the City in any way whatsoever. If disclosure is required under the California Public Records Act or otherwise by law (despite the bidder's request for confidentiality), the City shall not in any way be liable or responsible for the disclosure of any such records or part thereof.
A sample of the contract the successful bidder will be required to enter into with the City is attached hereto and by this reference incorporated herein and made part of these specifications.
The vendor shall disclose whether the proposed solution includes Artificial Intelligence (AI), Machine Learning (ML), or automated decision-making technologies that are integral to its functionality. Where feasible, the vendor should provide mechanisms that allow the City to configure or limit the use of such features. The City recognizes that opting out of AI features may reduce functionality; however, vendors are expected to design solutions that support informed decision-making by clearly identifying which features rely on AI and whether such features are optional or required.
If you are already registered and need help logging in or retrieving your user information utilize the blue chat bubble visible on the lower right hand corner of the screen.
Click on the hyperlink for the City's eProcurement Portal to create your vendor profile.
Electronic Submission of Bids
All Proposers are required to submit their bid pricing electronically via the city's eProcurement Portal. The electronic system will close submission exactly at the date and time set forth in this solicitation or as changed by addenda. In addition, your bid must be submitted via the eProcurement Portal.
Proposers are responsible for submitting and having their bid accepted before the closing time set forth in this solicitation or as changed by addenda. NOTE: It is the Proposer's sole responsibility to ensure their bid and document(s) are uploaded, transmitted, and arrive in time electronically. The City will have no responsibility for bids that do not arrive in a timely manner, no matter what the reason.
Upon closing of the Bid, Bid Results will be available on the City's eProcurement Portal.
In the case of a discrepancy between the electronic bid schedule (pricing) and any uploaded Bid schedule document or pricing, the electronic bid schedule will be the accepted bid.
Steps to Submit Your Electronic Proposal:
To submit an offer to the City, vendor must begin by clicking on the green DRAFT PROPOSAL button.
https://procurement.opengov.com/portal/pasadena/projects/237062
1. Acknowledge all Addenda
2. Accept City of Pasadena Terms and Conditions Message
3. Answer all required vendor questions.
4. Upload all required forms. Proposer may save their work and return.
5. Review your work and submit proposal when ready.
6. You will receive a confirmation email from OpenGov upon receipt of your bid/proposal.
7. Proposer may withdraw their bid at any time prior to 2:00 pm on Thursday, April 16, 2026.
Note: If an addenda is issued after a response has been submitted, Proposer or bidder must return to take steps below. Failure to do both steps will result in an invalidated offer.
1- Acknowledge the new addenda; and
2- Resubmit your bid through the City's eProcurement Portal.
Substantial Completion is the stage in the progress of the work when the project is sufficiently complete, in accordance with the Contract Documents, so that the EV charging system and associated infrastructure are fully installed, operational, tested, and available for intended use by the City.
Substantial Completion shall include, at a minimum:
Minor corrective work or punch list items that do not materially affect safety or operation may remain outstanding.
Substantial Completion shall be determined solely by the City and documented in writing. The date of Substantial Completion establishes the end of the Contract Time for purposes of liquidated damages.
SUBSTITUTION FOR PATENTED AND SPECIFIED ARTICLES
Wherever these Specifications specify any material or process by patent or proprietary name, or by name of manufacturer, such specification is only for the purpose of describing the material or process desired and shall be deemed to be followed by the words and/or approved equivalent. Any bidder may offer in the proposal any material or process that is equivalent in every respect to the material or process specified. This statement of alternate unit shall clearly describe the material or process for which the substitution is proposed and shall provide technical data establishing equivalency.
Equivalents to Specifications
The material, equipment or service offered by the bidder will meet all requirements of the specifications in this Notice Inviting Bids. Questions requesting approval of equals must be submitted before the deadline for questions to the City contacts listed in the Bid Invitation. Bidder must provide all information (no pricing) with their bid in order for the City to determine if the product offered is an equal to the manufacturer specified and/or meets the technical specifications. This includes details for each item to which a proposed equal will be taken, proposed make and model specifications, and any other information on the material specified herein regarding approved equals requested. Bidder must state brand name and/or manufacturer of each item proposed and include detailed specifications. All guarantees and/or warranties must also be stated. Parts and materials must be latest model or current date and meet specifications or be equal to the specifications.
During the question and answer period, the City reserves the right to determine whether equivalents meet the bid specifications of the City, and are equal to the manufacturer specified or the stated technical specifications. The decision of the City regarding equality shall be final.
Equals can be submitted for approval during the Question and Answer period through this eProcurement Portal: https://procurement.opengov.com/portal/pasadena/projects/237062.
The Bidder to whom a contract is awarded shall file the bonds specified by Section 2-4, "Contract Bonds," of the Standard Specifications before execution of the contract. The term "Contract Price" shall be deemed to mean the total contract "not to exceed" amount consisting of the base bid stated in the Bidder's Proposal plus such additional amounts provided for adjustments to the estimated quantities contained in the Bidder's Proposal and for extra work covered by approved change orders, if any. See Section P-2-4 of the Pasadena Supplements.
Invoice Submission Portal
The invoice submission process is activated when an invoice is submitted through the Vendor Invoice Portal. Invoices submitted are automatically sent to the department being invoiced for review. Once the city department verifies its accuracy, the department will submit the invoice to Accounts Payable for payment processing. One final review and approval by the department who was invoiced is needed in order for a check to be issued. Checks are issued on Tuesday and Thursday.
How to submit invoices to the City of Pasadena?
Create an account: Visit the City’s Invoice Submission website: https://invoice.cityofpasadena.net/ and select “Create Account”
Refer to the "Invoice Submission Portal - Vendor User Guide" for detailed instructions.
1. The contractor agrees to comply with all applicable standards, orders, or regulations issued pursuant to the Federal Water Pollution Control Act, as amended, 33 U.S.C. 1251 etseq. 2. The contractor agrees to report each violation to the (name of the applicant entering into the contract) and understands and agrees that the (name of the applicant entering into the contract) will, in turn, report each violation as required to assure notification to the Federal Emergency Management Agency, and the appropriate Environmental Protection Agency Regional Office. 3. The contractor agrees to include these requirements in each subcontract exceeding $150,000 financed in whole or in part with Federal assistance provided by FEMA.
The City of Pasadena is committed to promoting the economic health and well-being of its residents. To this end, Contractor agrees to recruit Pasadena residents initially and to give them preference, if all other factors are equal, for any new positions which result from the performance of this Contract and which are performed within the City. The Contractor will be required to make good-faith effort to hire Pasadena residents for all new hires, including subcontractor new hires. A good-faith effort will include requests to unions or community organizations designated by City to provide a list of qualified Pasadena residents. If qualified candidates available, Contractor will conduct interviews with assistance of City and union/community organizations. Residents are individuals who are, and have been one year prior to the effective date of the contract, residents of the City of Pasadena. Submission to the City of documentation of requests and interviews will constitute proof of a good-faith effort. Interviews of Pasadena residents, if conducted, shall be completed and documentation submitted to the City prior to commencement of Contract work.
Bidders shall not be allowed to take advantage of any errors or omissions in the Instructions to Bidders or Specifications. Full instructions will be given if such error or omission is discovered and timely called to the attention of the City.
(1) This contract is a covered transaction for purposes of 2 C.F.R. pt. 180 and 2 C.F.R. pt. 3000. As such, the contractor is required to verify that none of the contractor’s principals (defined at 2 C.F.R. § 180.995) or its affiliates (defined at 2 C.F.R. § 180.905) are excluded (defined at 2 C.F.R. § 180.940) or disqualified (defined at 2 C.F.R. § 180.935). (2) The contractor must comply with 2 C.F.R. pt. 180, subpart C and2 C.F.R. pt. 3000, subpart C, and must include a requirement to comply with these regulations in any lower tier covered transaction it enters into. (3) This certification is a material representation of fact relied upon by (insert name of recipient/subrecipient/applicant). If it is later determined that the contractor did not comply with 2 C.F.R. pt. 180, subpart C and 2 C.F.R. pt. 3000, subpart C, in addition to remedies available to (insert name of recipient/subrecipient/applicant), the Federal Government may pursue available remedies, including but not limited to suspension and/or debarment. (4) The bidder or proposer agrees to comply with the requirements of2 C.F.R. pt. 180, subpart C and 2 C.F.R. pt. 3000, subpart C while this offer is valid and throughout the period of any contract that may arise from this offer. The bidder or proposer further agrees to include a provision requiring such compliance in its lower tier covered transactions.
By submitting a bid or proposal, each bidder or proposer expressly agrees to and accepts the following conditions:
Materials and equipment furnished shall be new, complete, ready-for-use and of the latest model, shall not have been used in demonstration or other services and have all the usual equipment as shown by manufacturer’s current specifications and catalogs unless otherwise specified.
Click here to register onto the City's eProcurement Portal hosted by OpenGov.
If you are already registered and need help logging in or retrieving your user information simply click on the blue chat bubble on the lower right hand corner of your screen or contact OpenGov at procurement-support@opengov.com for help at any time.
Customer Service
For assistance with e-bidding or uploading documents: Contact OpenGov via the blue chat bubble on the lower right hand corner of your screen or email at procurement-support@opengov.com.
Monday through Friday 5 am - 5 pm PST, except statutory holidays-- response time is typically less than ten minutes.
The Contractor warrants that all work performed under this Contract shall be free from defects in workmanship and Contractor-furnished materials for a period of one (1) year from the date of final acceptance by Pasadena Water & Power.
During the warranty period, the Contractor shall promptly repair or replace, at no cost to the City, any defective work, including all labor, materials, equipment, and incidental costs necessary to restore the work to proper operating condition.
Manufacturer warranties for Owner-furnished equipment shall be assigned to the City; however, the Contractor remains responsible for workmanship, installation, and integration of such equipment.
The construction warranty is in addition to and does not limit any other rights or remedies available to the City under the Contract or applicable law.
Final Acceptance shall occur only after successful completion of commissioning, correction of all punch list items, and submission of required closeout documentation.
This form is only required for the purchases of technology. The City of Pasadena Department of Information Technology (DoIT) is tasked with reviewing all IT solutions proposed for use by the City. DoIT uses this questionnaire to assess various business, security, and/or operational impacts of bidder or proposer proposed technology solutions, SaaS offerings, software or hardware that will reside on the City’s servers and/or network, that will integrate to the City’s existing applications, servers and/or network, or that may have an impact on the City’s ability to conduct business. This questionnaire is also used to identify and distinguish at an early stage in the evaluation process the potential roles and responsibilities of the City and the proposer.
If selected, proposers are required to complete the Pasadena Department of Information Technology Technical Questionnaire. The questionnaire is included in the section named "Submittal/Checklist." When completing the questionnaire, please note:
This section is only required for the lease/purchase of Printers/Copiers/Scanners.
All devices or associated storage media which is replaced or removed must be sanitized in accordance with the "clear", "purge" or "destroy" categories of sanitization as defined in the NIST SP 800-88 publication "Guidelines for Media Sanitization". Sanitization of media must be certified by the Contractor and signed documentation detailing the device(s), media and category of sanitization must be provided to the Department of Information Technology (DoIT). Documentation of bulk or blanket sanitization is not acceptable.
All equipment must be configured such that the hard drive or associated storage media is encrypted or such encryption can be enabled by DoIT at will. All equipment must be configured to permit hard drive or associated storage media to be removed by a DoIT technician if necessary.
Temporary removal of equipment, such as for maintenance or repair, is subject to data sanitization requirements as stated above.
All device hard drives or associated storage media shall be left in DoIT’s possession at the end of the any lease, rental, or other time-limited usage agreement, if specified by the City.
All administrative accounts on equipment must be configured with non-default password, complex passwords, and the account names and passwords provided to DoIT.
Contractor must provide configuration printouts in hard copy form of all settings for any TCP/IP functions, including but not limited to network configurations, static routes, SMTP, SNMP, scan-to-file, etc., and storage media encryption configurations. Printouts must be delivered to DoIT when equipment configuration is complete and “ready for operation”.
Local Business is defined in the Pasadena Municipal Code section:
4.08.020, O: "Local business" means a business with a fixed place of business located in the city.
To receive any preferences offered to a Pasadena business in this solicitation, a Pasadena business must be located within the City Boundary by the release date of this solicitation.
Byrd Anti-Lobbying Amendment, 31 U.S.C. § 1352 (as amended) Contractors who apply or bid for an award of $100,000 or more shall file the required certification. Each tier certifies to the tier above that it will not and has not used Federal appropriated funds to pay any person or organization for influencing or attempting to influence an officer or employee of any agency, a Member of Congress, officer or employee of Congress, or an employee of a Member of Congress in connection with obtaining any Federal contract, grant, or any other award covered by 31 U.S.C. § 1352. Each tier shall also disclose any lobbying with non-Federal funds that takes place in connection with obtaining any Federal award. Such disclosures are forwarded from tier to tier up to the recipient who in turn will forward the certification(s) to the awarding agency.
The City reserves the right to inspect all work. Concealed work installed without inspection approval may be required to be uncovered at the Contractor’s expense.
Contractor shall provide factory warranties on all materials furnished against defects in materials and/or workmanship. The factory warranty shall become effective on the date of delivery and acceptance by the City. Should any defect in materials or workmanship appear during the warranty period, the Contractor shall repair or replace the same at no cost to the City.
Each bidder shall include in the price bid any patent fees, royalties and charges on any patented article or process to be furnished or used in the prosecution of the Work.
If a bid bond is required, below are instructions for utilizing Surety2000 to submit an electronic bid bond.
Video Trainings:
Bid Bond Instruction:
Bidders must provide all required information for the City to verify the bond with their bid. The bond must meet the following requirements and characteristics: Bid security in the amount of five percent (5%) of the total bid price in the form of a redeemable or callable electronic surety bond, meeting City requirements, must accompany all bids. If the Bidder to whom the contract is awarded shall for fifteen (15) calendar days after such award fail or neglect to enter into the contract with the required insurance documentation, submit the Construction & Demolition Waste Management Plan, and file the required bonds, the City may deposit in its treasury said bid security and, under no circumstances, shall it be returned to the defaulting Bidder. Failure to return signed contract with all the attachments stated above may result in having the project awarded to the next lowest bidder.
Here is what bidders must provide to their bonding agent when trying to setup a bid bond for the City of Pasadena: The Project ID of the solicitation on which you are bidding. Your Contractor Vendor ID which is your Federal Tax ID or it’s equivalent. Both fields are required for validation. If you are having trouble finding these ID’s, please contact Surety2000 at 1-800-660-3263 or email help@surety2000.com
In the performance of this contract, the Contractor shall make maximum use of products containing recovered materials that are EPA-designated items unless the product cannot be acquired— 1. Competitively within a timeframe providing for compliance with the contract performance schedule; 2. Meeting contract performance requirements; or 3. At a reasonable price. ii. Information about this requirement, along with the list of EPA designated items, is available at EPA’s Comprehensive Procurement Guidelines web site, https://www.epa.gov/smm/comprehensiveprocurement-guideline-cpg-program. iii. The Contractor also agrees to comply with all other applicable requirements of Section 6002 of the Solid Waste Disposal Act.”
The Contractor shall protect existing facilities and restore all disturbed areas to equal or better condition. Damage to City property shall be repaired at the Contractor’s expense.
Any materials not conforming to requirements of this Specification shall be considered defective. All such materials, whether in place or not, shall be immediately removed from the site of the work. Any defective materials installed shall be removed and replaced by the City and all costs of removal and replacement shall be deducted from any amounts due or to become due to the Contractor. No rejected materials, the defects of which have been subsequently corrected, shall be used.
Price bid shall include all federal, state, local and other taxes.
Final payment shall not be made until the Contractor provides as-built drawings, warranty documents, equipment manuals, and all required closeout materials.
If applicable, contractors must sign and submit to the non-federal entity the following certification. APPENDIX A, 44 C.F.R. PART 18 – CERTIFICATION REGARDING LOBBYING Certification for Contracts, Grants, Loans, and Cooperative Agreements The undersigned certifies, to the best of his or her knowledge and belief, that: 1. No Federal appropriated funds have been paid or will be paid, by or on behalf of the undersigned, to any person for influencing or attempting to influence an officer or employee of an agency, a Member of Congress, an officer or employee of Congress, or an employee of a Member of Congress in connection with the awarding of any Federal contract, the making of any Federal grant, the making of any Federal loan, the entering into of any cooperative agreement, and the extension, continuation, renewal, amendment, or modification of any Federal contract, grant, loan, or cooperative agreement. 2. If any funds other than Federal appropriated funds have been paid or will be paid to any person for influencing or attempting to influence an officer or employee of any agency, a Member of Congress, an officer or employee of Congress, or an employee of a Member of Congress in connection with this Federal contract, grant, loan, or cooperative agreement, the undersigned shall complete and submit Standard Form-LLL, “Disclosure Form to Report Lobbying,” in accordance with its instructions. 3. The undersigned shall require that the language of this certification be included in the award documents for all subawards at all tiers (including subcontracts, subgrants, and contracts under grants, loans, and cooperative agreements) and that all subrecipients shall certify and disclose accordingly. This certification is a material representation of fact upon which reliance was placed when this transaction was made or entered into. Submission of this certification is a prerequisite for making or entering into this transaction imposed by section 1352, title 31, U.S. Code. Any person who fails to file the required certification shall be subject to a civil penalty of not less than $10,000 and not more than $100,000 for each such failure. The Contractor, certifies or affirms the truthfulness and accuracy of each statement of its certification and disclosure, if any. In addition, the Contractor understands and agrees that the provisions of 31 U.S.C.Chap. 38, Administrative Remedies for False Claims and Statements, apply to this certification and disclosure, if any. _________________________________________ Signature of Contractor’s Authorized Official Name ________________________________ Title of Contractor’s Authorized Official _______________________ Date FEDERAL CONTRACT PROVISIONS
For the purpose of determining the lowest bidder on a contract for materials and supplies only, 1.75% of that portion of the bid subject to sales or use tax shall be deducted from any bid where it is determined that if such bidder were awarded the contract, the City would receive a refund of the 1.75% sales and use tax pursuant to the Uniform Sales and Use Tax Ordinance of the City of Pasadena.
Deficient parts will be rejected and the Contractor will be required to make the necessary adjustments or replacements. It shall be the Contractor’s responsibility to pick up any rejected parts, make the necessary corrections, and deliver materials at no additional cost to the City.
If this purchase includes a service, and the contract total is at $25,000 or more, it is then subject to the City of Pasadena's Living Wage Ordinance, Pasadena Municipal Code Chapter 4.11. The ordinance requires that contractors providing labor or services to the City under contracts in excess of $25,000 pay no less than the City’s Living Wage to all employees who spend any of their time providing labor or delivering services to the City.
The selected contractor will be required to evidence compliance with the Living Wage Ordinance by submitting payroll records as requested by the City. Each record shall include the full name of each employee performing labor or providing services under the contract; job classification; rate of pay and benefit rate.
Failure to comply with the provisions of the Pasadena Living Wage Ordinance is grounds for termination of the contract and a basis for penalties as stated in Pasadena Municipal Code Chapter 4.11. Questions concerning the Pasadena Living Wage Ordinance should be directed to:
Finance Department
Purchasing Division
626-744-6755 - phone
626-744-6757 – fax
Please visit https://ww5.cityofpasadena.net/finance/doing-business-with-the-city/ for the current calendar year Pasadena Living Wage rate.
The following access to records requirements apply to this contract: (1) The Contractor agrees to provide (insert name ofstate agency or local or Indian tribal government), (insert name of recipient), the FEMA Administrator, the Comptroller General of the United States, or any of their authorized representatives access to any books, documents, papers, and records of the Contractor which are directly pertinent to this contract for the purposes of making audits, examinations, excerpts, and transcriptions. (2) The Contractor agrees to permit any of the foregoing parties to reproduce by any means whatsoever or to copy excerpts and transcriptions as reasonably needed. (3) The Contractor agrees to provide the FEMA Administrator or his authorized representatives access to construction or other work sites pertaining to the work being completed under the contract. (4) In compliance with the Disaster Recovery Act of 2018, the (write in name of the non-federal entity) and the Contractor acknowledge and agree that no language in this contract is intended to prohibit audits or internal reviews by the FEMA Administrator or the Comptroller General of the United States.
If a vendor is providing labor for any subsequent contract resulting from this solicitation, they must comply with the City of Pasadena Minimum Wage as set forth in Chapter 5.02 of the Pasadena Municipal Code. Vendors are encouraged to review the City’s minimum wage information guide at (https://bit.ly/3o3SHMh). The minimum wage ordinance may be found at Pasadena Municipal Code.
This procedure specifies the process to be utilized by the City of Pasadena in resolving protests regarding this solicitation. In order for a protest to be considered by the City of Pasadena, it must be submitted in accordance with the procedures outlined in the FORMAL SOLICITATION PROTEST PROCEDURE found at the following link: (https://ww5.cityofpasadena.net/finance/doing-business-with-the-city/). A protest submitted that is not in accordance with this procedure, may be returned to the submitting party without any further action by the City of Pasadena.
There is a separate packet of forms as part of these specifications that a bidder must complete to establish compliance with a number of special City of Pasadena requirements, including, but not limited to, Equal Employment and Affidavit of Non Collusion. These forms and their instructions should be considered an integral part of the specifications and failure to complete them shall be grounds, in the sole discretion of the City, for rejection of any bidder.
4.08.130 Lowest and best bidder.
In determining the lowest and best bidder, the following shall be considered, in addition to price:
A. The quality of the material offered;
B. The ability, capacity and skill of the bidder to perform the contract or provide the material or services;
C. Whether the bidder can perform the contract or provide the service promptly, or within the time specified, without delay or interference;
D. The sufficiency of the bidder's financial resources and the effect thereof on his ability to perform the contract or provide the material or services;
E. The character, integrity, reputation, judgment, experience and efficiency of the bidder;
F. The quality and timeliness of the bidder's performance on previous orders or contracts for the city;
G. Litigation by the bidder on previous orders or contracts with the city;
H. The ability of the bidder to provide future maintenance and service where such maintenance and service is essential;
I. Certification by bidder of compliance with the Equal Employment Opportunity—Non-discrimination requirements.
J. Certification by bidder of compliance with the Pasadena living wage ordinance, where applicable.
(Ord. 6899, § 2, 2002; Ord. 6763, § 2, 1998; Ord. 5068, § 3.08, 1972)
As detailed in the Section Titled #Public Works Claims Procedure new Public Contract Code Section 9204, effective January 1, 2017, specifies new procedural requirements for claims submitted by a contractor on any public works project.
Bidders or Proposers shall not be allowed to take advantage of any errors or omissions in the Instructions to Bidders/General Instructions or Specifications/Scope of Work. Full instructions will be given if such error or omission is discovered and timely called to the attention of the City.
“The contractor shall not use the DHS seal(s), logos, crests, or reproductions of flags or likenesses of DHS agency officials without specific FEMA pre-approval.”
“This is an acknowledgement that FEMA financial assistance will be used to fund all or a portion of the contract. The contractor will comply with all applicable Federal law, regulations, executive orders, FEMA policies, procedures, and directives.”
The material, equipment or service offered by the bidder will meet all requirements of the specifications in this Notice Inviting Bids. Questions requesting approval of equals must be submitted before the deadline for questions to the City contacts listed in the Bid Invitation. Bidder must provide all information (no pricing) in order for the City to determine if the product offered is an equal to the manufacturer specified and/or meets the technical specifications. This includes details for each item to which a proposed equal will be taken, proposed make and model specifications, and any other information on the material specified herein regarding approved equals requested. Bidder must state brand name and/or manufacturer of each item proposed and include detailed specifications. All guarantees and/or warranties must also be stated. Parts and materials must be latest model or current date and meet specifications or be equal to the specifications.
During the question and answer period for this solicitation (MAINTENANCE YARDS EV CHARGER EXPANSION; 2026-IFB-LM-0141), the City reserves the right to determine whether equivalents meet the bid specifications of the City, and are equal to the manufacturer specified or the stated technical specifications. The decision of the City regarding equality shall be final.
The Prime Contractor shall be solely responsible for the payment of all subcontractors, suppliers, laborers, and any other persons or entities employed in connection with the performance of this Contract.
The City shall have no obligation to pay, or to ensure the payment of, any subcontractors, suppliers, or workers directly. The Prime Contractor shall ensure timely and full payment in accordance with all applicable laws, including but not limited to California Public Contract Code §§ 10262 and 10262.5 and Labor Code § 218.7.
Failure to comply with this requirement may result in the withholding of payments, imposition of penalties, and/or other remedies available under the Contract and applicable law.
The Prime Contractor shall also include in all subcontracts a provision requiring subcontractors to pay their lower-tier subcontractors and suppliers in a timely manner consistent with this section.
Each bidder or proposer shall include in the price bid any patent fees, royalties and charges on any patented article or process to be furnished or used in the prosecution of the Work.
Prior to contract award, the lowest responsive and responsible bidder must provide an active registration with "Sam.Gov." Vendors seeking to register can register for free at the following link: https://sam.gov/content/entity-registration
“The Federal Government is not a party to this contract and is not subject to any obligations or liabilities to the non-Federal entity, contractor, or any other party pertaining to any matter resulting from the contract.”
Price bid or Price Proposals shall include all federal, state, local and other taxes.
This procedure specifies the process to be utilized by the City of Pasadena in resolving protests regarding this solicitation. In order for a protest to be considered by the City of Pasadena, it must be submitted in accordance with the procedures outlined in the FORMAL SOLICITATION PROTEST PROCEDURE found at the following link: (https://ww5.cityofpasadena.net/finance/doing-business-with-the-city/). A protest submitted that is not in accordance with this procedure, may be returned to the submitting party without any further action by the City of Pasadena.
Proof of insurance is not required to be submitted with your bid/proposal, but will be required prior to the City's award of the contract. Refer to the Insurance requirements in the "Insurance Requirements" section of this document.
“The Contractor acknowledges that 31 U.S.C. Chap. 38 (Administrative Remedies for False Claims and Statements) applies to the Contractor’s actions pertaining to this contract.”
The Bidder to whom a contract is awarded shall file the bonds specified by Section 2-4, "Contract Bonds," of the Standard Specifications before execution of the contract. The term "Contract Price" shall be deemed to mean the total contract "not to exceed" amount consisting of the base bid stated in the Bidder's Proposal plus such additional amounts provided for adjustments to the estimated quantities contained in the Bidder's Proposal and for extra work covered by approved change orders, if any. See Section P-2-4 of the Pasadena Supplements.
Performance Bonds Required: 50%
FEMA recipients and subrecipients and their contractors and subcontractors are required per 2 C.F.R. Part 200, Appendix II to include a contract provision in all FEMA-funded contracts and subcontracts, including any purchase orders. 1. On or after Aug. 13, 2020, for all new, extended, or renewed contracts using FEMA funds, especially for covered telecommunications equipment or services: a. FEMA recipients and subrecipients are required to include a provision in their contracts explaining the prohibitions under section 889 of the NDAA and as clarified in this policy. b. This also applies to subcontracts under any new, extended, or renewed contract. (a) Definitions. As used in this clause, the terms backhaul; covered foreign country; covered telecommunications equipment or services; interconnection arrangements; roaming; substantial or essential component; and telecommunications equipment or services have the meaning as defined in FEMA Policy, #405-143-1 Prohibitions on Expending FEMA Award Funds for Covered Telecommunications Equipment or Services As used in this clause. The link to the policy is listed here: Prohibitions on Expending FEMA Award Funds for Covered Telecommunications Equipment or Services (Interim) FEMA Policy #405-143-1 (b) Prohibitions. (1) Section 889(b) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019, Pub. L. No. 115-232, and 2 C.F.R. § 200.216 prohibit the head of an executive agency on or after Aug.13, 2020, from obligating or expending grant, cooperative agreement, loan, or loan guarantee funds on certain telecommunications products or from certain entities for national security reasons. (2) Unless an exception in paragraph (c) of this clause applies, the contractor and its subcontractors may not use grant, cooperative agreement, loan, or loan guarantee funds from the Federal Emergency Management Agency to: (i) Procure or obtain any equipment, system, or service that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology of any system; (ii) Enter into, extend, or renew a contract to procure or obtain any equipment, system, or service that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology of any system; (iii) Enter into, extend, or renew contracts with entities that use covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system; or (iv) Provide, as part of its performance of this contract, subcontract, or other contractual instrument, any equipment, system, or service that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system. (c) Exceptions. (1) This clause does not prohibit contractors from providing— a. A service that connects to the facilities of a third-party, such as backhaul, roaming, or interconnection arrangements; or b. Telecommunications equipment that cannot route or redirect user data traffic or permit visibility into any user data or packets that such equipment transmits or otherwise handles. (2) By necessary implication and regulation, the prohibitions also do not apply to: a. Covered telecommunications equipment or services that: i. Are not used as a substantial or essential component of any system; and ii. Are not used as critical technology of any system. b. Other telecommunications equipment or services that are not considered covered telecommunications equipment or services. (d) Reporting requirement. (1) In the event the contractor identifies covered telecommunications equipment or services used as a substantial or essential component of any system, or as critical technology as part of any system, during contract performance, or the contractor is notified of such by a subcontractor at any tier or by any other source, the contractor shall report the information in paragraph (d)(2) of this clause to the recipient or subrecipient, unless elsewhere in this contract are established procedures for reporting the information. (2) The Contractor shall report the following information pursuant to paragraph (d)(1) of this clause: (i) Within one business day from the date of such identification or notification: The contract number; the order number(s), if applicable; supplier name; supplier unique entity identifier (if known); supplier Commercial and Government Entity (CAGE) code (if known); brand; model number (original equipment manufacturer number, manufacturer part number, or wholesaler number); item description; and any readily available information about mitigation actions undertaken or recommended. (ii) Within 10 business days of submitting the information in paragraph (d)(2)(i) of this clause: Any further available information about mitigation actions undertaken or recommended. In addition, the contractor shall describe the efforts it undertook to prevent use or submission of covered telecommunications equipment or services, and any additional efforts that will be incorporated to prevent future use or submission of covered telecommunications equipment or services. (e) Subcontracts. The Contractor shall insert the substance of this clause, including this paragraph (e), in all subcontracts and other contractual instruments.
The winning proposal/bid may be required to submit a completed and signed IRS Form W-9. Failure to submit this form may result in the response being deemed non-responsive.
The Bidder to whom a contract is awarded shall file the bonds specified by Section 2-4, "Contract Bonds," of the Standard Specifications before execution of the contract. The term "Contract Price" shall be deemed to mean the total contract "not to exceed" amount consisting of the base bid stated in the Bidder's Proposal plus such additional amounts provided for adjustments to the estimated quantities contained in the Bidder's Proposal and for extra work covered by approved change orders, if any. See Section P-2-4 of the Pasadena Supplements.
Labor & Materials Bonds Required: 50%
Proof of insurance is not required to be submitted with your bid, but will be required prior to the City's award of the contract. A copy of the City standard is included in the attachments.
(a) As appropriate and to the extent consistent with law, the non-Federal entity should, to the greatest extent practicable under a Federal award, provide a preference for the purchase, acquisition, or use of goods, products, or materials produced in the United States (including but not limited to iron, aluminum, steel, cement, and other manufactured products). The requirements of this section must be included in all subawards including all contracts and purchase orders for work or products under this award. (b) For purposes of this section: (1) “Produced in the United States” means, for iron and steel products, that all manufacturing processes, from the initial melting stage through the application of coatings, occurred in the United States. (2) “Manufactured products” means items and construction materials composed in whole or in part of non-ferrous metals such as aluminum; plastics and polymer-based products such as polyvinyl chloride pipe; aggregates such as concrete; glass, including optical fiber; and lumber.
Bidders acknowledge that they shall provide the goods and/or services without monetary limitations on liability. If Bidders take exception to this requirement, Bidders shall expressly state any exceptions, including the proposed limits of liability, (a) in detail; (b) as a separate line item; and (c) not part of any form documents submitted. Bidders acknowledge that any exceptions may result in a finding of non-responsiveness.
The initial term of the contract resulting from these Specifications shall be for one year from the date of execution by the City. No optional extension periods will be included with this contract.
This section is only applied when buying paper products.
Beginning January 1, 2022, SB 1383 requires jurisdictions (cities, counties, cities and counties, or special districts that provide solid waste collection services) to purchase recycled-content paper products that are recyclable.
SB 1383 builds upon existing laws that require jurisdictions to purchase products that contain minimum recycled content, and adds additional requirements on product recyclability and recordkeeping.
All vendors providing Paper Products and Printing and Writing Paper shall:
ONLY REQUIRED FOR FUNDING AGREEMENTS a. Standard. If the FEMA award meets the definition of “funding agreement” under 37C.F.R. § 401.2(a) and the non-Federal entity wishes to enter into a contract with a small business firm or nonprofit organization regarding the substitution of parties, assignment or performance of experimental, developmental, or research work under that “funding agreement,” the non Federal entity must comply with the requirements of 37 C.F.R. Part 401 (Rights to Inventions Made by Nonprofit Organizations and Small Business Firms Under Government Grants, Contracts and Cooperative Agreements), and any implementing regulations issued by FEMA. See 2 C.F.R. Part 200, Appendix II(F). b. Applicability. This requirement applies to “funding agreements,” but it DOES NOT apply to the Public Assistance, Hazard Mitigation Grant Program, Fire Management Assistance Grant Program, Crisis Counseling Assistance and Training Grant Program, Disaster Case Management Grant Program, and Federal Assistance to Individuals and Households – Other Needs Assistance Grant Program, as FEMA awards under these programs do not meet the definition of “funding agreement.” c. Funding Agreements Definition. The regulation at 37 C.F.R. § 401.2(a) defines “funding agreement” as any contract, grant, or cooperative agreement entered into between any Federal agency, other than the Tennessee Valley Authority, and any contractor for the performance of experimental, developmental, or research work funded in whole or in part by the Federal government. This term also includes any assignment, substitution of parties, or subcontract of any type entered into for the performance of experimental, developmental, or research work under a funding agreement as defined in the first sentence of this paragraph.
Provide experience with governmental agencies for two projects/contracts of similar scope and size. Complete and submit the attached Relevant Experience Form with your bid to demonstrate experience with projects of similar scope and size to that which is to be performed.
The Contractor shall provide written notification to the City when the Contractor deems the work complete and ready for final inspection. Upon the receipt of this notice, the City will make a final inspection and notify the Contractor within five (5) working days that the work is approved or that additional work is needed before approval. The work will neither be final nor accepted until the City notifies the contractor in writing that the entire work is completed to the specifications. No deviations from the Specifications will be accepted unless previously approved in writing by the City. Within ten (10) days after the work is accepted, the City will record a Notice of Completion. The Contractor shall be responsible for risk of loss or damage to the work until the date of the written notice of acceptance from the City. The period of any guarantee or warranty provided under these Specifications, shall commence on the date the work is accepted.
This section of the FEDERAL REGISTER contains regulatory documents having general applicability and legal effect, most of which are keyed to and codified in the Code of Federal Regulations, which is published under 50 titles pursuant to 44 U.S.C. 1510. The Code of Federal Regulations is sold by the Superintendent of Documents. DEPARTMENT OF AGRICULTURE Rural Utilities Service 7 CFR Part 1787 RIN 0572–AC42 ‘‘Buy American’’ Requirement. Details for this requirement can be found at the following link: https://www.govinfo.gov/content/pkg/FR-2018-11-27/pdf/2018-25815.pdf
The CONTRACTOR shall begin work within fifteen (15) calendar days after date of the Notice to Proceed and shall diligently prosecute the work to completion in every detail, within 180 Working Days after the date in the Notice to Proceed with Work, exclusive of maintenance periods if any.
A working day consists of the following: Mon-Fri, 8:00 am to 4:00 pm
Except the following observed City Holidays:
The Contractor is required to confirm dates with the City prior to start of construction.
REQUIRED FOR ALL FEDERALLY FUNDED AGREEMENTS. City of Pasadena and contractors may be subject to the equal opportunity requirements implementing Executive Order 11246, “Equal Employment Opportunity,” as amended by Executive Order 11375, “Amending Executive Order 11246 Relating to Equal Employment Opportunity,” and as supplemented by regulations at 41 CFR part 60, “Office of Federal Contract Compliance Programs, Equal Employment Opportunity, Department of Labor”, as well as 2 C.F.R. §200.321, “Contracting with small and minority businesses, women’s business enterprises, and labor surplus area firms.” Contractors shall be required to complete the applicable Equal Employment Opportunity forms and SBE/MBE/WBE/LSA forms included in the project specifications. Contractor shall also sign and submit a certification that declares all necessary affirmative steps were taken to assure that small and minority businesses, women’s business enterprises, and labor surplus area firms were used when possible, as outlined by 2 C.F.R. §200.321.
The provisions of this Contract relating to payment for products or services shall become effective when funds assigned for the purpose of compensating the Contractor as herein provided are actually available to for disbursement. The City shall be the sole judge and authority in determining the availability of funds under this Contract. If any action is taken by the City, any state agency, Federal department or any other agency to suspend, decrease, or terminate its fiscal obligations under, or in connection with, this Contract, the City may amend, suspend, decrease, or terminate its obligations under, or in connection with, this Contract. In the event of termination, The City shall be liable for payment only for products provided or services rendered prior to the effective date of the termination, provided that such products or services were provided or performed in accordance with the provisions of this Contract.
Failure of the contractor to meet the delivery date will result in damages being sustained by the City of Pasadena. Such damages are, and will continue to be, impracticable and extremely difficult to determine. For each consecutive calendar day in excess of the delivery date the Contractor shall pay the City of Pasadena, or have withheld from monies due it, the sum of $1,500 per day.
Execution of the Contract shall constitute agreement by the City of Pasadena and the Contractor that this represents the minimum value of the costs and actual damage caused by the failure of Contractor to meet the deliver date. Such sum is liquidated damages and shall not be construed as a penalty, and may be deducted from payments due Contractor if such delays occur.
If any person contemplating submitting a proposal of the items or services listed herein is in doubt as to the true meaning of any part of this RFP, he/she may submit a question through the City's eProcurement Portal Q&A section for an interpretation or correction thereof.
Any interpretation or correction of City specifications will be made only by addendum, duly issued by the City representative(s) identified in this solicitation, above. Addenda (if any) shall be made available on the City's eProcurement system, and sent to each vendor included on the "Followers" list in the City's eProcurement system. A vendor's failure to address the requirements of any and all addenda may result in the response (proposal or bid, or alike) not being considered. If the City determines that a time extension is required for the proposal, the City will issue an addendum that will give the new submission date. The vendor is responsible to register on the City's eProcurement Portal and follow the project named MAINTENANCE YARDS EV CHARGER EXPANSION in order to be included in the "Followers" list in the City's eProcurement system to insure they receive all documents including addendums which are available as a download.
The City reserves the right to change any part of these Instructions to PROPOSERS and Specifications any time prior to Deadline for Submissions. Any changes shall be in the form of addenda and will become a part of the Proposal documents and of the contract.
REQUIRED FOR ALL FEDERALLY FUNDED AGREEMENTS. Contractors shall comply with the CPA requirements as implemented by 46 CFR 381 in order to ensure a fair and reasonable participation by privately owned United States-flag commercial vessels in transporting cargoes which are subject to the Cargo Preference Act of 1954 and which are generated by U.S. Government Grant, Guaranty, Loan and/or Advance of Funds Programs Use of United States-flag vessels: The contractor agrees – To utilize privately owned United States-flag commercial vessels to ship at least 50 percent of the gross tonnage (computed separately for dry bulk carriers, dry cargo liners, and tankers) involved, whenever shipping any equipment, material, or commodities pursuant to this contract, to the extent such vessels are available at fair and reasonable rates for United States-flag commercial vessels. To furnish within 20 days following the date of loading for shipments originating within the United States or within 30 working days following the date of loading for shipments originating outside the United States, a legible copy of a rated, ‘on-board’ commercial ocean bill-of-lading in English for each shipment of cargo described in paragraph (b) (1) of this section to both the Contracting Officer (through the prime contractor in the case of subcontractor bills-of-lading) and to the Division of National Cargo, Office of Market Development, Maritime Administration, Washington, DC 20590. To insert the substance of the provisions of this clause in all subcontracts issued pursuant to this contract.”
REQUIRED FOR FEDERALLY FUNDED AGREEMENTS IN EXCESS OF $100,000 AND INVOLVES THE EMPLOYMENT OF MECHANICS OR LABORERS. The Contractor shall comply with 40 U.S.C. §§ 3702 and 3704, as supplemented by Department of Labor regulations at 29 C.F.R. Part 5. See 2 C.F.R. Part 200, Appendix II(E). Under 40 U.S.C. § 3702, each contractor must be required to compute the wages of every mechanic and laborer on the basis of a standard work week of 40 hours. Work in excess of the standard workweek is permissible provided that the worker is compensated at a rate of not less than one and a half times the basic rate of pay for all hours worked in excess of 40 hours in the work week. Further, no laborer or mechanic must be required to work in surroundings or under working conditions which are unsanitary, hazardous, or dangerous. Overtime requirements. No contractor or subcontractor contracting for any part of the contract work which may require or involve the employment of laborers or mechanics shall require or permit any such laborer or mechanic in any workweek in which he or she is employed on such work to work in excess of forty hours in such workweek unless such laborer or mechanic receives compensation at a rate not less than one and one-half times the basic rate of pay for all hours worked in excess of forty hours in such workweek. Violation; liability for unpaid wages; liquidated damages. In the event of any violation of the clause set forth in paragraph (b)(1) of this section the contractor and any subcontractor responsible therefor shall be liable for the unpaid wages. In addition, such contractor and subcontractor shall be liable to the United States (in the case of work done under contract for the District of Columbia or a territory, to such District or to such territory), for liquidated damages. Such liquidated damages shall be computed with respect to each individual laborer or mechanic, including watchmen and guards, employed in violation of the clause set forth in paragraph (b)(1) of this section, in the sum of $27 for each calendar day on which such individual was required or permitted to work in excess of the standard workweek of forty hours without payment of the overtime wages required by the clause set forth in paragraph (b)(1) of this section. Withholding for unpaid wages and liquidated damages. The (write in the name of the Federal agency or the loan or grant recipient) shall upon its own action or upon written request of an authorized representative of the Department of Labor withhold or cause to be withheld, from any moneys payable on account of work performed by the contractor or subcontractor under any such contract or any other Federal contract with the same prime contractor, or any other federally-assisted contract subject to the Contract Work Hours and Safety Standards Act, which is held by the same prime contractor, such sums as may be determined to be necessary to satisfy any liabilities of such contractor or subcontractor for unpaid wages and liquidated damages as provided in the clause set forth in paragraph (b)(2) of this section. Subcontracts. The contractor or subcontractor shall insert in any subcontracts the clauses set forth in paragraph (b)(1) through (4) of this section and also a clause requiring the subcontractors to include these clauses in any lower tier subcontracts. The prime contractor shall be responsible for compliance by any subcontractor or lower tier subcontractor with the clauses set forth in paragraphs (b)(1) through (4) of this section. Records. The contractor or subcontractor shall maintain payrolls and basic payroll records during the course of the work and shall preserve them for a period of three years from the completion of the contract for all laborers and mechanics, including guards and watchmen, working on the contract. Such records shall contain the name and address of each such employee, social security number, correct classifications, hourly rates of wages paid, daily and weekly number of hours worked, deductions made, and actual wages paid. Access to Records. Records to be maintained under this provision shall be made available by the contractor or subcontractor for inspection, copying, or transcription by authorized representatives of the Department of Homeland Security, the Federal Emergency Management Agency, and the Department of Labor, and the contractor or subcontractor will permit such representatives to interview employees during working hours on the job.”
The Contractor shall, at its own expense provide a storage location for his materials and equipment. The contractor must request and coordinate with Public Works Department for an approved location.
The Contractor shall, at its own expense, preserve and protect from injury all improvements existing at the site, such as equipment, trees, parkways, flowers, shrubbery, lawns, fences, curbs, gutters, sidewalks, walls, manholes and all other improvements of whatever nature. If any such improvements are injured, damaged, or destroyed by the Contractor, or its employees, subcontractors or agents, they shall promptly be restored by the Contractor, at the Contractor’s expense, to the condition existing before such injury, damage, or destruction. The Contractor shall protect and maintain in uninterrupted service any existing sub-surface utilities and shall promptly repair any damages to such utilities at his own expense. Existing utilities of record in the area affected by this contract may be shown in the drawings, however, if any pipe or conduit is encountered, the contractor shall determine their usage and arrange with the proper utility concerned for its removal or protection. The Contractor shall be held responsible for all damage to work installed by him or others that is caused by his work or by anyone employed by him. The Contractor shall utilize “UNDERGROUND SERVICE ALERT’ (USA) of Southern California (1-800-422-4133) to obtain marking of underground pipeline and utility locations. The contractor shall notify “USA” at least two working days in advance of beginning any excavation and/ or jacking operations. Utilities that are not subscribers or members of “USA” shall be notified separately and independently. To avoid unnecessary marking of utilities in the street and sidewalk areas, the Contractor shall specifically indicate those areas where underground utility information is needed using a temporary water based marking chalk (“AERVOE” brand or approved equal) with a visible life not to exceed three (3) weeks. Such markings shall be limited to only those areas where the Contractor’s operation could damage buried utilities. Unnecessary markings resulting from Contractor’s failure to identify only critical locations shall be removed by the Contractor at his expense. If the Contractor fails to properly and completely remove all unnecessary markings, the City will remove and bill the Contractor for all direct and indirect removal costs.
An NFE is required by 2 C.F.R. § 200.315 to provide certain licenses with respect to copyright and data to the federal awarding agency. 2 C.F.R. § 200.315(b) provides to the federal awarding agency “a royalty-free, nonexclusive and irrevocable right to reproduce, publish, or otherwise use [any work that is subject to copyright] for federal purposes, and to authorize others to do so.” 2 C.F.R. § 200.315(d) provides to the federal government the rights to “obtain, reproduce, publish, or otherwise use” data produced under a federal award and to authorize others to do the same. Applicability When an NFE enters into a contract requiring a contractor or subcontractor to produce copyrightable subject matter and/or data for the NFE under the award, the NFE should include appropriate copyright and data licenses to meet its obligations under 2 C.F.R. § 200.315(b) and (d), respectively. Work that is subject to copyright, or copyrightable subject matter, includes any written reports or literary works, software and/or source code, music, choreography, pictures or images, graphics, sculptures, videos, motion pictures or other audiovisual works, sound and/or video recordings, and architectural works. Suggested Language The following provides a sample contract clause: “License and Delivery of Works Subject to Copyright and Data Rights” The Contractor grants to the (insert name of the non-federal entity), a paid-up, royalty-free, nonexclusive, irrevocable, worldwide license in data first produced in the performance of this contract to reproduce, publish, or otherwise use, including prepare derivative works, distribute copies to the public, and perform publicly and display publicly such data. For data required by the contract but not first produced in the performance of this contract, the Contractor will identify such data and grant to the (insert name of the non-federal entity) or acquires on its behalf a license of the same scope as for data first produced in the performance of this contract. Data, as used herein, shall include any work subject to copyright under 17 U.S.C. § 102, for example, any written reports or literary works, software and/or source code, music, choreography, pictures or images, graphics, sculptures, videos, motion pictures or other audiovisual works, sound and/or video recordings, and architectural works. Upon or before the completion of this contract, the Contractor will deliver to the (insert name of the non-federal entity) data first produced in the performance of this contract and data required by the contract but not first produced in the performance of this contract in formats acceptable by the (insert name of the non-federal entity).”
The Contractor shall bear all risk of loss or damage to the work until its final completion and acceptance by the City. In this connection, the Contractor shall be responsible for proper storage and handling of all materials, including those materials furnished by the City, and for the care of all work until such final completion and acceptance. The Contractor shall, at its own expense, promptly replace material damaged or lost during this period, and shall repair any portion of the work damaged during this period. If the Contractor neglects or refuses to do so, the City may do so at the Contractor’s expense. However, the Contractor shall not be responsible for damage exceeding five percent of the Contract amount from Acts of God as defined in California Government Code Section 4151, such as earthquakes in excess of magnitude 3.5 on the Richter Scale, provided such damaged work was done according to the Specifications. Contractor shall not sell, assign, mortgage, hypothecate or remove equipment or materials which have been installed or delivered, and which may be necessary for the completion of the work, without written consent of the General Manager.
SAM REGISTRATION
Prior to bid submittal date, the lowest responsive and responsible bidder must be verified to not be on the government-wide exclusions list for suspension or debarment.
Vendors seeking to register can register for free at the following link: https://sam.gov/content/entity-registration
All federal financial assistance recipients must have a Unique Entity ID (UEI) number.
As of April 4, 2022, DUNS Numbers will no longer be used by federal agencies. As part of a governmentwide initiative, the Office of Management and Budget (OMB), directed all federal agencies to complete their transition to the Unique Entity ID created in SAM.gov. This transition allows the government to streamline the entity identification and validation process, making it easier for entities to do business with the federal government for your company does not have a UEI, you can obtain one by visiting https://sam.gov/content/entity-registration.
The SAM registration process may take several business days to complete. Therefore, the City recommends that the Bidder begin the registration process if bidder has not done so already.
This proof must be submitted with the Bid. If you fail to submit this information with the Bid, the Bid may be deemed non-responsive.
The Contractor shall transfer to the City the manufacturer's warranty or guarantee for each item delivered or installed under the Contract. Where applicable, the City shall be named as owner-beneficiary in any such warranty or guarantee. The Contractor shall ensure that each warranty or guarantee is in full force and effect from the date the City commences operation and use of the item. All such manufacturer's warranties or guarantees shall be in addition to the Contractor's warranty under this Contract. In addition to the above and any special guarantees required by the Detailed Specifications, the Contractor shall warrant that its work is fit for the City's particular purpose as indicated in the Specifications, fulfills all requirements of these Specifications, and is free from defects in materials, equipment, workmanship or installation. For a period of one two (2) years following the City's acceptance of the Work as provided in herein in this Specification, the Contractor shall repair or replace at its own expense any portion of the Work, including any material or equipment incorporated into the Work, that is defective or otherwise fails to conform to the above warranty or special guarantees. The City will notify Contractor of any such defect or nonconformity. Such notice will be given in writing, if possible, or by the means most practical under the circumstances. If the Contractor fails to correct the defect or other non-conformity within ten (10) days after receiving such notice, or in case of emergency demanding immediate action, then the City may make the necessary replacements or repairs and charge the Contractor the total cost of all labor, materials, equipment, administration and overhead required. If final payment has not been made, the City may withhold an amount for these costs; if the amount withheld is not sufficient, the City may recover any balance from the Contractor. The Contractor's performance bond shall remain in effect for a period of two (2) years after the date of acceptance of the work to cover the Contractor's warranties and guarantees as set forth above. The warranty period for each work order begins on the day when the retention is approved to be released.
Below is a Summary and an Executive Summary: Click Here for the Complete Document: https://public-inspection.federalregister.gov/2023-17724.pdf
SUMMARY:
The Office of Management and Budget is revising the OMB Guidance for Grants and Agreements. The revisions are limited in scope to support implementation of the Build America, Buy America Act provisions of the Infrastructure Investment and Jobs Act and to clarify existing provisions related to domestic preferences. These revisions provide further guidance on implementing the statutory requirements and improve Federal financial assistance management and transparency.
SUPPLEMENTARY INFORMATION:
Executive Summary
The Office of Management and Budget (OMB) is revising its guidance in title 2 of the Code of Federal Regulations (2 CFR) to add a new part 184 and revise 2 CFR 200.322. The revisions implement the requirement for the Director of OMB to issue guidance to the head of each Federal agency to assist in the implementation of the requirements of the Build America, Buy America Act (BABA), Public Law 117-58, 135 Stat. 429, 70901-70927, Nov. 15, 2021. As required by BABA, the new part 184 of 2 CFR provides clear and consistent guidance to Federal agencies about how to apply the domestic content procurement preference (Buy This document is scheduled to be published in the Federal Register on 08/23/2023 and available online at federalregister.gov/d/2023-17724, and on govinfo.gov America or BABA preference) as set forth in BABA to Federal awards for infrastructure projects. See BABA 70915. For example, the new part 184 includes definitions for key terms, including iron or steel products, manufactured products, construction materials, and materials identified in section 70917(c) (section 70917(c) materials) of BABA. These definitions provide a common system for Federal agencies to distinguish between the product categories established under the statutory text in BABA. The new part also offers standards that define “all manufacturing processes” in the case of construction materials. The new part 184 also includes guidance for determining the cost of components of manufactured products. The part 184 text uses a modified version of the “cost of components” test found in the Federal Acquisition Regulation (FAR) at 48 CFR 25.003, which is used for Federal procurement. Using this approach for determining the cost of components of manufactured products in the context of Federal financial assistance aims to provide a consistent approach for industry, with only minor modifications which are explained in this document. The new part 184 also includes guidance on proposing and issuing Buy America waivers. For example, based on the statutory text of BABA, it restates the circumstances under which a waiver may be justified. The new part also includes guidance on the type of process that a Federal agency should implement to allow recipients to request waivers, including the process a Federal agency should follow in issuing proposed and final waivers. The revised provision in 2 CFR part 200 specifies that Federal agencies providing Federal financial assistance for infrastructure projects must implement the Buy America preferences set forth in 2 CFR part 184, as required under section 70914(a) BABA, as of the effective date of the guidance, unless specified otherwise.
Click Here for the Complete Document: https://public-inspection.federalregister.gov/2023-17724.pdf
The Contractor shall provide adequate safety measures and devices to prevent accidents, injury, or loss of life to the public and to workers, inspectors, and any persons whose duties bring them on the work. The Contractor shall comply with all orders and requirements of the California Division of Industrial Safety. The Contractor shall immediately install or provide any safeguarding or safety measures which the Division or the General Manager shall require. Without limiting the foregoing, in accordance with generally accepted construction practices the Contractor will be solely and completely responsible for conditions of the job site, including safety of all persons and property during performance of the work. This requirement will apply continuously and not be limited to normal working hours. Construction review of the Contractor’s performance by the City, its agents or employees, does not include review of the adequacy of Contractor’s safety measures at or near the construction site. Such construction review shall not relieve the Contractor of its obligations under this paragraph. The Contractor must comply with safety requirements issued by CAL/OSHA confined spaces, Article 108, #5157, #5158, #5159 and Pasadena Water and Power Department Safety Handbook Section I & II of Underground Distribution, when entering underground manholes. These requirements include, but not limited to: entry permits, air monitoring and ventilation, safety and rescue provisions. The Contractor and all his personnel must wear approved hard hats, clothing and equipment required on the jobsite. The Contractor shall employ workers who are qualified, experienced and well trained to work safely around or near energized electrical equipment. It is also a requirement of this contract that the contractor must provide his own electrical personnel who is qualified to monitor and supervise his workers while working inside the energized vault. Sanitation The Contractor shall provide all appropriate sanitary conveniences and shall remove the conveniences at the completion of the work.
For Compliance with Federal Acquisition Regulations (FAR) Clauses and Deviations
General Requirements
All bidders or proposers must adhere to the following Federal Acquisition Regulation (FAR) clauses, including specified deviations. Bidder/Proposers should ensure their representations and certifications are completed and up to date in SAM.gov before submitting their proposal.
Required Representations and Certifications
Contract Terms and Conditions
Subcontracting Requirements
- FAR 52.244-6 – Subcontracts for Commercial Products and Commercial Services
- If the Bidder/Proposer intends to subcontract any portion of the work:
- Subcontractors must comply with all applicable FAR clauses.
- The prime contractor is responsible for ensuring subcontractor compliance with federal laws.
- The Government reserves the right to review and approve subcontractors for compliance.
The Contractor shall keep the site free from accumulation of waste materials, rubbish and debris at all times. Upon completion of the work, the Contractor shall remove from the site all tools, equipment, temporary structures, unused materials, concrete forms, scaffolding, rubbish and other materials belonging to the Contractor or used under its direction during construction, and shall leave the site broom clean, unless the General Manager specifies otherwise. In the event the Contractor fails to clean up as required by these Specifications, the City may perform such cleanup work at the Contractor’s expense; the Contractor and its sureties shall be liable for such expense.
The Contractor shall be responsible for providing quality control measures to assure that all work is done in accordance with the Contract documents and any product manufacturer’s recommendations.
If, in the opinion of a City Inspector or Representative, the Contractor is not providing quality control, further repair work may be suspended in part or in whole. Repair work shall only be allowed to commence once the Contractor has demonstrated satisfactory improvement in quality control procedures and repair results.
This procurement is funded by: City of Pasadena. Vendors must submit all required document with their proposal.
By submitting this bid the Bidder hereby certifies under penalty of perjury of the laws of the State of California that all representations made in the documents that comprise the proposal for MAINTENANCE YARDS EV CHARGER EXPANSION due on Thursday, April 16, 2026 are true and correct to the best of my knowledge at the time of the proposal’s submission.
By confirming, the bidder acknowledges the following:
Subsequent to the closing of this solicitation, but prior to contract award, the recommended vendor will be required to provide the following documents within 10 calendar days of being notified, otherwise the submitted proposal may be deemed non-responsive.
Please confirm that you will provide the following per these instructions.
All Insurance Required by this Solicitation (If Required)
Bidder agrees that their bid shall remain open and shall not be withdrawn for a period of not less than one hundred and eighty (180) calendar days from the date of opening bids, or until rejected by the City, whichever occurs first.
By submitting a response, Bidder agrees to commence work within fifteen (15) calendar days from the date of issuance of a Notice to Proceed and proposes and agrees to have all work completed within NO VALUE Working Days after contract time commences.
If your submittal does not include all of the below items, it may be deemed non-responsive.
Please download the below documents, complete, and upload.
This form is only required for the purchases of technology at $5,000 or more. If selected, proposers will be required to complete the Pasadena Department of Information Technology Technical Questionnaire. The questionnaire is included in the #Attachments. When completing the questionnaire, please note:
In order to comply with the section named “Data Security for Printers/Copiers/Scanners,” My company will:
Please download the below documents, complete, and upload.
While the materials and supplies listed in this solicitation represent a majority of the materials and supplies needed, there is a small percentage of items that are unknown at this time. Therefore, bidders are required to, in addition to providing pricing for all materials and supplies, submit a catalog (PDF) with all available supplies or materials for future purchasing consideration as a part of this overall contract with their bid. Catalog information must include per unit pricing.
Please enter your Bid Bond information from Surety2000 below.
Electronic Bid bond is required. Bidders must submit all required information for the city to verify the bond with their bid. The bond must meet the following requirements and characteristics: A bid security in the amount of five percent (5%) of the total bid price in the form of a redeemable or callable electronic surety bond, meeting City requirements, must accompany all bids.
Please enter your Bond IDand your Vendor ID from Surety2000for this Solicitation (Project ID: 2026-IFB-LM-0141).
Bid Bond Instruction:
Here is what you should provide your bonding agent when trying to setup a bid bond for the City of Pasadena: The Project ID of the solicitation on which you are bidding. Your Contractor Vendor ID which is your Federal Tax ID or it’s equivalent. Both fields are required for validation. If you are having trouble finding these ID’s, please contact Surety2000 at 1-800-660-3263 or email help@surety2000.com
Please upload a copy of your: Class A – General Engineering; OR B – General Building; OR C-10 Electrical Contractor
Please enter your license number with the CSLB for: Class A – General Engineering; OR B – General Building; OR C-10 Electrical Contractor
Solely for the purpose of verification. Please enter your Public Works Contractor Registration Number. This will be verified against the state database for the Department of Industrial Relations Registration.
In 2014, the California legislature enacted several laws impacting public works contracting. Senate Bill 854 (SB 854) creates changes in the way DIR monitors prevailing wage requirements. All contractors and subcontractors must register with the DIR and meet DIR requirements before bidding on public works contracts in California. No contractor or subcontractor may be awarded a contract for public work or public works project unless registered with the DIR.
Public Work Contractors/Subcontractors can register with the DIR at
Please upload a copy of all required DIR registrations for the prime and all subcontractors.
In 2014, the California legislature enacted several laws impacting public works contracting. Senate Bill 854 (SB 854) creates changes in the way DIR monitors prevailing wage requirements. All contractors and subcontractors must register with the DIR and meet DIR requirements before bidding on public works contracts in California. No contractor or subcontractor may be awarded a contract for public work or public works project unless registered with the DIR.
Public Work Contractors/Subcontractors can register with the DIR at www.dir.ca.gov/Public-Works/.
Please download the below documents, complete, and upload.
Please download the below documents, complete, and upload.
Please download the below documents, complete, and upload.
In addition to the items listed above, the following list is provided for the convenience of both you and the City and to help eliminate errors and omissions which may render your bid unacceptable. The following forms are required to be submitted with your bid: https://www.cityofpasadena.net/finance/wp-content/uploads/sites/27/HUD-Federal-Forms-under-200k.pdf?v=1674593673378
HUD Federal Forms (under $200k)
In addition to the items listed above, the following list is provided for the convenience of both you and the City and to help eliminate errors and omissions which may render your bid unacceptable. The following forms are required to be submitted with your bid: https://www.cityofpasadena.net/finance/wp-content/uploads/sites/27/HUD-Federal-Forms-over-200k.pdf?v=1674593673378
HUD Federal Forms (Over $200k)
All bidders must provide a copy of their Active SAM Registration with their bid.
Select a general funding source
For Example: "Homeland Security"
This amount is the dollar value of the award from HUD. Contact Housing if you have questions.
Below is a list of potential attachments that may or may not apply to your procurement. Please review the attachments in the section named "Attachments" to ensure they are relevant and appropriate.
Do not erase the text below. Enter the number after the text that reads "FEDERAL-AID PROJECT NUMBER:"
"Public Work" as defined by the State of California: Construction, alteration, demolition, installation, or repair work done under contract and paid in whole or in part out of public funds. It can include preconstruction and post-construction activities related to a public works project. For additional information on SB 854 please refer to the following link: www.dir.ca.gov/public-works/PublicWorksSB854FAQ.html
Goods/Equipment, Services, SAAS, Printers, Copiers/Scanners)
If any of the following items apply, please contact HR (Jaime Arellano, jarellano@cityofpasadena.net; (626) 744-7301) for approval before you proceed. DO NOT SUBMIT BEYOND THIS POINT UNTIL YOU HAVE OBTAINED APPROVAL FROM HUMAN RESOURCES.
A section will be inserted into the solicitation to indicate a specific amount of Working Days within which the project must be completed. This is typical on projects with a start- and end-date.
Please enter a number only to represent the number of calendar days within which the contractor must complete the work.
Indicate the Liquidated Damages amount in dollars for this contract. For each consecutive calendar day in excess of the delivery date the Contractor shall pay the City of Pasadena, or have withheld from monies due it, the sum of [$ Dollars] per day.
Please enter the specific License or Certification required to be eligible to compete on this solicitation. For example, "C33 - Painting and Decorating, OR Class A – General Engineering with Asbestos Certification, OR class B – General Building with Asbestos Certification".
If the "Experience is Required" option is selected, a form will be added to capture the experience you require.
A Market Basket of Goods are the materials and supplies currently in your Bidder's Proposal and represents a pricing method used in solicitations where vendors must provide prices for a representative list of the most commonly purchased materials and supplies. The current list —called the Market Basket—reflects the City’s anticipated purchasing. The materials in the Market Basket represent a defined percentage of the contract’s estimated value and consist of the top items the City purchases. While bidders must price all items in the Market Basket, they must also provide catalog pricing for all other available materials or supplies to cover items not specifically listed.
An electronic Bid Bond, or Bid security is submitted by all bidders in the amount of five percent (5%) of the total bid price in the form of cash, cashier's check, money order or surety bond, meeting City requirements, must accompany all bids.
4.08.140 - Bonds or security required when: All such contracts or purchase orders shall require adequate security for the faithful performance of the contract in a form approved by the city attorney. In addition to a faithful performance bond or other security, contractors who furnish both labor and material shall furnish a contractor's bond satisfactory to the city in an amount not less than 50 percent of the value of the contract. The director of finance may waive the requirement of a faithful performance bond when in his opinion such waiver will not be detrimental to the city.
4.08.140 - Bonds or security required when: All such contracts or purchase orders shall require adequate security for the faithful performance of the contract in a form approved by the city attorney. In addition to a faithful performance bond or other security, contractors who furnish both labor and material shall furnish a contractor's bond satisfactory to the city in an amount not less than 50 percent of the value of the contract. The director of finance may waive the requirement of a faithful performance bond when in his opinion such waiver will not be detrimental to the city.
General definitions and parameters of each approach.
For Example: "Homeland Security"
4.08.140 - Bonds or security required when: All such contracts or purchase orders shall require adequate security for the faithful performance of the contract in a form approved by the city attorney. In addition to a faithful performance bond or other security, contractors who furnish both labor and material shall furnish a contractor's bond satisfactory to the city in an amount not less than 50 percent of the value of the contract. The director of finance may waive the requirement of a faithful performance bond when in his opinion such waiver will not be detrimental to the city.
4.08.140 - Bonds or security required when: All such contracts or purchase orders shall require adequate security for the faithful performance of the contract in a form approved by the city attorney. In addition to a faithful performance bond or other security, contractors who furnish both labor and material shall furnish a contractor's bond satisfactory to the city in an amount not less than 50 percent of the value of the contract. The director of finance may waive the requirement of a faithful performance bond when in his opinion such waiver will not be detrimental to the city.
Q (Clarification — Owner-Furnished vs. Contractor-Furnished DCFC Equipment): Section 9.3 states owner-furnished equipment is limited to items in the Owner- Furnished Equipment Schedule. Section 9.1 states any equipment not specifically listed as owner-furnished shall be deemed contractor-furnished. However, Sheet E0.0 directs the Contractor to "Furnish and Install" all EV charging equipment including the DCFC system, and Attachment O provides Kempower specs without clearly designating furnishing responsibility. Please clarify: Is the following DCFC equipment Owner-Furnished or Contractor-Furnished? 1. Kempower Power Unit C503 V4 (600kW) 2. Kempower Satellite V2 Dual Port (Qty 2) 3. Associated DCFC components (power/comm cables between units, mounting hardware, network equipment) This clarification is needed to ensure an accurate bid, as the furnishing responsibility for this equipment represents a significant cost impact.
A: The City confirms that the following DC fast charging equipment is Owner-Furnished Equipment: KEMPOWER 600KW C503 D6 V4 DCFC Power Cabinet KEMPOWER Dual-Port Satellite V2 Dispensers (Qty. 2) (NACS & CCS) with 23-foot cables Associated DCFC components shall be considered Owner-Furnished only to the extent they are included in the manufacturer’s supplied equipment package or are expressly identified in the Owner-Furnished Equipment Schedule. All other materials, equipment, appurtenances, incidentals, and work necessary to provide a complete and fully operational installation, and not expressly identified as Owner-Furnished Equipment, shall be Contractor-Furnished and Installed. This includes, but is not limited to, conduits, raceways, site wiring, terminations, grounding, foundations, supports, and all other balance-of-system work. The Contractor shall be responsible for coordinating with the City and equipment supplier regarding receipt, handling, storage, installation, startup support, testing, and commissioning of Owner-Furnished Equipment. For purposes of bidding, the reference on Sheet E0.0 to “Furnish and Install” shall be interpreted to require the Contractor to furnish all materials and perform all work not expressly identified as Owner-Furnished Equipment, and to provide complete installation of the DCFC system.
Q (Technical Specifications — Confirmation of Contract Documents): The bid documents include the Competitive Bid Package, Approved Stamped Plans (Attachment N — Sheets E0.0 through S1.0), the PWP Transformer Vault Drawing (Attachment P), and EV Charger Equipment Data (Attachment O). However, we do not find a standalone technical specification manual (e.g., Division 26 — Electrical, Division 31 — Earthwork, Division 33 — Utilities, etc.) included with the bid documents. 1. Are the drawings and bid package the complete set of contract documents for this project, or is there a separate technical specification manual that should accompany the plans? 2. If no separate specifications exist, please confirm that the drawing notes, general notes on Sheet E0.0, and the bid package conditions are the sole basis for defining materials, installation methods, testing requirements, and acceptable manufacturers. Impact: Without clarification, bidders may interpret material, installation, and testing standards inconsistently, which could result in non-comparable bids and potential scope gaps during construction.
A: The bid documents issued with this IFB including the referenced attachments, are the contract documents currently being provided for bidding purposes. Based on the documents issued, bidders shall rely on the bid package, approved drawings, attached equipment information, and all issued attachments and addenda in preparing their bids. No separate standalone technical specification manual has been included in the materials issued with this IFB. Accordingly, bidders shall base their bids on the Contract Documents provided, including the design drawings, notes, panel schedules, technical information included in the attachments, and the requirements set forth in the bid package. The Contract Documents are intended to be read together. However, separate manufacturer-specific startup or commissioning procedures were not included in the bid documents issued with this IFB. Bidders shall therefore base their bids on the Contract Documents provided and shall include all work necessary for complete installation, startup support, testing, and commissioning consistent with the Contract Documents. In the event manufacturer-specific startup or commissioning procedures are applicable to furnished equipment, the Contractor shall coordinate with the City and equipment vendor following award. To the extent bidders identify conflicts, omissions, or ambiguities in the issued documents, such matters should be raised through the Q&A process prior to bid submission.
Q (Electronic Bid Docs): Will electronic signatures be acceptable on the bid documents or is it necessary to print sign and upload?
A: Electronic signatures are acceptable on bid documents submitted through the City’s eProcurement Portal, so long as the documents are signed by an authorized representative and otherwise comply with all solicitation requirements. Bidders remain responsible for submitting complete and properly executed forms by the bid deadline.
Q (No subject): Is submission of the bid bond through Surety2000 required, or will a standard bid bond be accepted?
A: Submission of the bid bond as an electronic bid bond is required.
Q (No subject): Are there BABA requirements associated with this work?
A: Yes
Q (Pre-Proposal Meeting / Site Visit): Please confirm whether a pre-proposal meeting or job walk will be conducted for this project. If no formal pre-proposal meeting is scheduled, please confirm: - Whether site access can be arranged for bidders prior to bid submission - The process and contact for coordinating a site visit
A: At this time, no pre-bid meeting or formal job walk is scheduled for this project. Based on the information provided in the solicitation, together with publicly available overhead satellite imagery and related online resources, the City believes bidders have sufficient information to assess the site and project conditions for purposes of preparing a bid. Because the project site is not open to the public, the City will not arrange individual site visits prior to bid submission. If the City determines that a site visit is necessary, or if it receives sufficient interest from prospective bidders to warrant one, the City reserves the right to issue an addendum scheduling a pre-bid meeting or job walk for all prospective bidders.
Q (Clarification of Required Licenses): Form AA-1 "Licenses and Certifications" requests a City of Pasadena Business License. Please confirm whether bidders are required to possess an active Pasadena Business License at the time of bid submission, or if the license may be obtained after award.
A: Bidders are not required to possess a City of Pasadena Business License at the time of bid submission unless expressly stated elsewhere in the solicitation. The successful bidder shall obtain the required City of Pasadena Business License before contract execution and prior to performance of the work.
Q (Prequalifications): Are there any contractor/subcontractor prequalification's needed to bid on this project.
A: No separate contractor or subcontractor prequalification is required for this project. However, bidders shall comply with the solicitation’s experience requirement set forth in Section 7.19, Relevant Experience. As stated in that section, bidders must provide experience with governmental agencies for two projects/contracts of similar scope and size and must complete and submit the Relevant Experience Form with the bid.
Q (No subject): Drawing 245_W_Mountain_EV.dwg has a single line drawing that shows #1 AL EPR cable, a New 27KV, SF6 3-Way Switch and RFI #462 25KV. Is this the contractors responsibility or will this be provided and installed by PWP?
A: #1 AL EPR cable, 8-750 kcmil AL 600V cables, 27KV SF6 3-Way Switch, 25KV RFI #462, and 3-833KVA transformers will be provided and installed by PWP.
Q (No subject): Drawing 245_W_Mountain_EV.dwg, Note 4, requires contractor to "Grout all around conduits that penetrate slab box to form water tight seal". Will the contractor be required to access the existing PWP vault to grout penetrations?
A: Access to the existing PWP vault will be required by qualified contractor to gout around conduit knockouts with the supervision of PWP field personnel.
Q (Site Visit Request): Contractor is requesting a site visit for the following reasons. A. The overhead satellite imagery does not clearly identify the exact location of the existing PWP vault that requires connection. B. The existing EV chargers scheduled for removal will also require removal of associated cabling; however, the location of the power source is currently unknown. C. Due to the scope of work involving concrete and asphalt removal, patching, and restriping, the contractor requests verification of existing site conditions. D. The contractor requests confirmation of elevation conditions at the locations where the EV chargers will connect to the new cable tray. E. The contractor requests verification of existing site conditions to support construction logistics and planning.
A: A. Please reference PWP electric service drawing 245_W_MOUNTAIN_EV.dwg for exact location of existing PWP vault. B. The power source for existing EV chargers is in close proximity as shown on sheet E5.2 (south east island of Area F). C. Existing site conditions are visible via satellite imagery. D. The elevated platform has a height of approximately 4 ft. E. Existing site conditions are visible via satellite imagery.
Q (No subject): Given that this is a federally funded project subject to BABA requirements, the specified IXP chargers do not comply. Confirming that the City will accept alternate AC BABA compliant chargers?
A: The AC chargers for this project are Owner-Furnished Equipment. As clarified in Section 9, as revised by Addendum No. 1, bidders are not required to furnish or propose alternate AC chargers under this IFB. The City will separately procure the Owner-Furnished Equipment identified in the solicitation.
Q (No subject): Can the City specify which major equipment items will be furnished by the City under a separate procurement.
A: Yes. The major equipment items to be furnished by the City under separate procurement are identified as Owner-Furnished Equipment in Section 9, as revised by Addendum No. 1. Bidders shall rely on that revised section for the complete listing of equipment to be furnished by the City.
Q (No subject): Can the City provide an engineer estimate?
A: The City does not have an engineer’s estimate for this solicitation and therefore is not providing one.
Q (No subject): To ensure alignment across bidder's submissions, can the City provide clarity throughout the SOW identifying which items will be contractor-furnished versus owner-furnished?
A: Clarification regarding Owner-Furnished Equipment has been provided in Section 9, as revised by Addendum No. 1. Bidders shall refer to that section for the equipment and materials to be furnished by the City.
Q (No subject): Drawing 245_W_Mountain_EV.dwg references, under "Customer to Install" drawings V-859, V-252, V-860, V-258. Can the City provide these drawings?
A: Drawings will be provided.
Q (No subject): Are there union labor requirements under this SOW?
A: No separate union labor requirement is identified in the solicitation. However, contractors shall comply with all applicable requirements of the solicitation documents, including any applicable prevailing wage and labor compliance obligations.
Q (No subject): Will the parking lot remain unoccupied during construction where the new work is being installed and should the contractor plan to fence off for separation from the public? Or does the parking lot need to remain uninterrupted and plating required?
A: The parking lot is not accessible to the public. The lot will be required to remain uninterrupted for PWP staff during normal business hours.
Q (No subject): Will the street work on Glenn Ave require engineered traffic plans and city approval or is watch manual/greenbook standards acceptable?
A: Glenn Ave is a private street within the PWP Maintenance Yard and not accessible to the public. Traffic control plan will not be required.
Q (No subject): 1. Please provide expected award date or duration for NTP from the bid opening. 2. Please provide the contractual construction duration for this project from NTP. 3. Please provide dates owner furnished contractor installed equipment is expected on site and how it relates to the construction NTP/duration. Much of this equipment is expected to have long leadtimes and required to be installed & commissioned to complete this scope.
A: The City’s anticipated contract award date is approximately eight (8) weeks after the bid due date. Notice to Proceed will be issued following contract execution and satisfaction of applicable pre-construction requirements. The estimated contract duration is approximately eighteen (18) months. The anticipated construction period is six (6) months or less from Notice to Proceed. Owner-Furnished Equipment is anticipated to be available within approximately six (6) months after award. The Contractor shall coordinate its work accordingly, including sequencing, installation, and commissioning activities associated with such equipment.
Q (No subject): Per document “APPROVED_STAMPED_PLANS_311_W_MOUNTAIN_ST”, sheet E4.0, note KN#12 states: “Move storage containers as needed to provide sufficient working clearance.” Please confirm the city will move all their material and storage containers.
A: Contractor may be required to move certain large items such as storage containers as needed to provide sufficient working clearances for construction. The city will move all other materials such as transformers and cable reels if they interfere with construction.
Q (No subject): The site plan and section detail at 1/E5.1 do not show bollards at the new above ground gutter. Please confirm whether bollards or a wheel stop are required to protect the new cable tray and 80A EV chargers located at Zone A. If required, does the striping for parking stalls need to be extended at these locations into the drive aisle to accommodate vehicle parking?
A: There will not be bollards or wheel stops in zone A.
Q (245_(311)_W_MOUNTAIN_EV_1.30.26.pdf): The drawing states "Contractor to install" but the notes state "the owner shall be responsible to furnish and install the items listed below...". Please confirm if the contractor is responsible for procuring and/or installing the Precast vault, vault ventilation, branch circuit, primary conduit, pulling eye assembly, grounding, switchgear & meters.
A: The winning bidder shall be responsible to furnish and install all items outlined on the PWP service drawing 245_W_MOUNTAIN_EV.dwg except for service conductors, utility transformers, & metering equipment.
Q (Restoration): What are the limits for concrete restoration? Will the contractor be permitted to only restore the trench area, or are full panel replacements required? If full panel replacement is required, please provide panel dimensions.
A: Restoration for trenched areas only.
Q (RE:Precast Vaults): Project description on E0.0, Note 4 specifies (3) 3’x5’ precast vaults. Conduit plan on E4.0 shows (4) 3’x5’ precast vaults. Please clarify if there are (3) or (4) new 3’x5’ precast vaults.
A: There will be (4) new 3' x 5' pull boxes as shown on sheet E4.0 Conduit Plan