Active SLED Opportunity · FLORIDA · CITY OF CLEARWATER
AI Summary
Invitation to Bid for replacement of grating at NE WRF Influent Building in Clearwater, FL. Scope includes demolition and installation of grating over influent channels. Construction time is 365 days. Pre-proposal meeting via Zoom on 2026-08-06. Questions due by 2026-08-12.
The scope of work for the replacement of the grating at the influent building through the splitter box includes in general the following:
1. Demolition of the existing grating over the channels in the influent headworks building and through to the splitter box;
2. Installation of new grating over the channels in the influent headworks
The Contractor shall furnish all labor, materials, equipment, tools, services and incidentals to complete all work required by Contract Documents.
The Contractor shall perform all work complete, in place and ready for continuous service, and shall include repairs, testing, permits, clean up, replacements and restoration required as a result of damages caused during construction.
All materials, equipment, skills, tools and labor which is reasonably and properly inferable and necessary for the proper completion of the work in a substantial manner and in compliance with the requirements stated or implied by the Contract Documents shall be furnished and installed by the Contractor without additional compensation, whether specifically indicated in the Contract Documents or not.
The Contractor shall comply with all local, State, Federal, and other codes that are applicable to the proposed construction work.
Construction Time 365 days
| Event | Date | Location |
|---|---|---|
| Bid Opening Location | 100 S Myrtle Ave. Rm 314 Clearwater, FL 33756 |
Project Name: NE WRF Influent Building Floor Repair
Project Number: 25-0004-UT
Scope of Work:
The scope of work for the replacement of the grating at the influent building through the splitter box includes in general the following:
1. Demolition of the existing grating over the channels in the influent headworks building and through to the splitter box;
2. Installation of new grating over the channels in the influent headworks
The Contractor shall furnish all labor, materials, equipment, tools, services and incidentals to complete all work required by Contract Documents.
The Contractor shall perform all work complete, in place and ready for continuous service, and shall include repairs, testing, permits, clean up, replacements and restoration required as a result of damages caused during construction.
All materials, equipment, skills, tools and labor which is reasonably and properly inferable and necessary for the proper completion of the work in a substantial manner and in compliance with the requirements stated or implied by the Contract Documents shall be furnished and installed by the Contractor without additional compensation, whether specifically indicated in the Contract Documents or not.
The Contractor shall comply with all local, State, Federal, and other codes that are applicable to the proposed construction work.
Construction Time 365 days
4.1 Technical Specifications
Reference Attachment A-NE WRF Bld_IFB Specifications
Section IV - Technical Specifications can be found on the City's website at: https://www.myclearwater.com/Business-Development/Doing-Business-with-the-City/Engineering-Construction-Bid-Information/Contract-Specifications
Section V - Contract Documents can be found on the City's website at: https://www.myclearwater.com/Business-Development/Doing-Business-with-the-City/Engineering-Construction-Bid-Information/Contract-Specifications
Are you a Certified Small Business or a Certified Minority, Woman or Disadvantaged Business Enterprise?
Pick one of the following
List the Agency that provided your certification.
Provide a copy of your certification
By submitting this response, the Vendor hereby certifies that:
PER FLORIDA STATUTE 448.095, CONTRACTORS AND SUBCONTRACTORS MUST REGISTER WITH AND USE THE E-VERIFY SYSTEM TO VERIFY THE WORK AUTHORIZATION STATUS OF ALL NEWLY HIRED EMPLOYEES.
The affiant, by virtue of confirming below, certifies that:
Please download the below documents, complete, notarize, and upload.
Please download the below documents, complete, and upload.
Please download the below documents, complete, and upload.
Upload your current W-9 form. (available at https://www.irs.gov/pub/irs-pdf/fw9.pdf)
SLED stands for State, Local, and Education. These are solicitations issued by state governments, counties, cities, school districts, utilities, and higher education institutions — as opposed to federal agencies.
SamSearch Platform