Active SLED Opportunity · NEW JERSEY · ATLANTIC COUNTY UTILITIES AUTHORITY, NJ
AI Summary
Atlantic County Utilities Authority seeks proposals for underwater inspection and condition reporting of its Ocean Outfall pipe. The project requires compliance with ASCE standards and includes video documentation. Evaluation focuses on cost, technical competence, and past performance. Proposals due by May 1, 2026.
The Atlantic County Utilities Authority (ACUA) is requesting proposals to perform an underwater inspection and report of the ACUA’s Ocean Outfall force main to verify the condition of the exposed piping. A report, along with video documentation, shall depict any evidence of flow restriction, leaks, degradation of pipe weighting, compromise in the cathodic protection system or corrosion of exposed steel structures. The inspection shall be conducted in accordance with standards of the American Society of Civil Engineers Waterfront Facilities Inspection and Assessment Manual No. 130. Percent cleaning shall be as required for a level II, routine inspection.
The Atlantic County Utilities Authority (ACUA) owns and operates a Solid Waste complex in Egg Harbor Township, Atlantic County, NJ, known as the Howard F. Haneman Environmental Park, and a Wastewater Treatment Facility in Atlantic City, Atlantic County, NJ, known as City Island Treatment Plant.
The Solid Waste facility is home to an active landfill, a recycling center, composting site, and ancillary facilities. Also on site is the ACUA’s primary administration building, constructed in 1992, which features a closed-loop geothermal HVAC system. The site is home to a 5.4 MW landfill methane gas to electricity project which provides 100% of the power needs of the Park. The ACUA’s solid waste complex is located at 6700 Delilah Road, in Egg Harbor Township, New Jersey. The site consists of approximately 360 acres with approximately 102 acres representing the landfill footprint.
The Wastewater Treatment Facility has been in operation since 1978 and services 14 communities in Atlantic County. It is home to the Jersey-Atlantic Wind Farm, a 7.5 MW wind farm that is privately owned and from which the ACUA purchases approximately 12 million kWh per year of electricity. In addition, the facility also houses a 500 kW solar PV system.
The ACUA is responsible to the residents of Atlantic County to be financially prudent and environmentally responsible.
| Event | Date | Location |
|---|---|---|
| Start of Work | 2026-07-01T04:00:00.000Z | https://teams.microsoft.com/l/meetup-join/19%3ameeting_MGZmNjMxZDctNmIzOS00N2VkLWEyZjQtMzRkYWI0OGU3MmU1%40thread.v2/0?context=%7b%22Tid%22%3a%2250c8182d-cb6f-484e-8470-596e9da7fa16%22%2c%22Oid%22%3a%22b676c5f8-7665-4a31-8926-b57be1371a4e%22%7d |
Once you start your proposal you will be asked to complete a DocuSign form containing the following:
This document MUST be signed via DOCUSIGN. Printing, signing and attaching a photocopy will not be accepted.
Please download the below documents, complete, and upload.
Please include your New Jersey Business Registration Certificate
Any documents that are required to be submitted with this RFP can be uploaded and attached here.
Please include a current copy with your submission.
When answered yes, the RFP will include language regarding date, time and place of Site Visit.
Q (No subject): Are existing inspection reports available for review?
A: Yes, potential Proposers may stop by the ACUA's office, at 6700 Delilah Road, Egg Harbor Township, NJ 08234, to review the last inspection report (June 2023). At the front desk, please ask for John Conover.
Q (No subject): On page 5 of the RFP, under “Inspection Report and Video,” ACUA requires documentation of inspection in video footage. Does the ACUA require audio in these recordings?
A: Yes.
Q (No subject): On page 5 of the RFP, under “Team Leader Requirements,” the ACUA requests “the Team leader shall be at the site for the duration of the field inspection and shall personally direct the inspection team to assure each component is properly inspected and documented.” Is the Team Leader required to be present in the video/audio coverage? Which personnel are required to be present?
A: As stated, the Team Leader shall be at the site for the duration of the field inspection and shall personally direct the inspection team. The Team Leader is not required to be present in the video/audio coverage. Team personnel assignments will be at the discretion of the proposer, assuming they comply with any requirements set forth in the RFP.
SLED stands for State, Local, and Education. These are solicitations issued by state governments, counties, cities, school districts, utilities, and higher education institutions — as opposed to federal agencies.