The AZ NFSR 289 Bridge Replacement project involves reconstructing a portion of FR 289 and replacing the existing Tonto Creek Bridge. The project aims to enhance safety and access to recreational sites. The estimated cost ranges from $2,000,000 to $5,000,000, with an anticipated completion date in October 2026. Interested bidders should prepare for a comprehensive scope of work including roadway excavation and bridge construction.
PROJECT NUMBER: AZ FS 289(1)
PROJECT NAME: AZ NFSR 289 BRIDGE REPLACEMENT
PROJECT DESCRIPTION: The project is located in the Tonto National Forest approximately 18 miles East of Payson, AZ. The existing Tonto Creek Bridge (no. 031204000003356) was built in 1956 and is a single lane, concrete slab bridge. NFSR 289 is a two-lane roadway that accesses several residential homes, a fish hatchery, and a summer camp along with many recreational sites and trailheads. The purpose of this project is to replace the existing Tonto Creek Bridge, expand the Horton Springs Parking Lot and improve pedestrian and vehicular safety and access to the recreation sites around the Tonto Creek Bridge on NFSR 289.
SCOPE OF THE WORK: The scope of the project includes reconstructing a portion of FR 289, removing the existing bridge and constructing a new single-span bridge over Tonto Creek including new sidewalk and reconstruction of the Horton Springs Parking Lot. This project includes removal of the existing two-span bridge, including removal of the existing pier. The project also includes channel grading in Tonto Creek. The new roadway and bridge will be constructed East of the existing alignment (upstream of the existing bridge) to minimize impacts to public traffic.
PRINCIPAL WORK ITEMS:
ANTICIPATED SCHEDULE:
Advertisement – October 2025
Award – December 2025
NTP – January 2026
Contract Completion – October 2026
Due to weather, no onsite work is anticipated between January and April 2026
ESTIMATED COST RANGE: Total estimated cost between $2,000,000 and $5,000,000.