Closed Solicitation · DEPARTMENT OF TRANSPORTATION

    AZ FS 289(1) AZ NFSR 289 BRIDGE REPLACEMENT

    Sol. 6982AF25B000019SolicitationLAKEWOOD, CO
    Closed
    STATUS
    Closed
    closed Nov 19, 2025
    POSTED
    Oct 20, 2025
    Publication date
    NAICS CODE
    237310
    Primary industry classification
    PSC CODE
    Y1LB
    Product & service classification

    AI Summary

    The AZ NFSR 289 Bridge Replacement project involves reconstructing a portion of FR 289 and replacing the existing Tonto Creek Bridge. The project aims to enhance safety and access to recreational sites. The estimated cost ranges from $2,000,000 to $5,000,000, with an anticipated completion date in October 2026. Interested bidders should prepare for a comprehensive scope of work including roadway excavation and bridge construction.

    Contract details

    Solicitation No.
    6982AF25B000019
    Notice Type
    Solicitation
    Posted Date
    October 20, 2025
    Response Deadline
    November 19, 2025
    NAICS Code
    237310AI guide
    PSC / Class Code
    Y1LB
    Primary Contact
    Stephanie Navarro
    State
    CO
    ZIP Code
    80228
    AI Product/Service
    both

    Description

    PROJECT NUMBER: AZ FS 289(1)

    PROJECT NAME: AZ NFSR 289 BRIDGE REPLACEMENT

    PROJECT DESCRIPTION:  The project is located in the Tonto National Forest approximately 18 miles East of Payson, AZ. The existing Tonto Creek Bridge (no. 031204000003356) was built in 1956 and is a single lane, concrete slab bridge. NFSR 289 is a two-lane roadway that accesses several residential homes, a fish hatchery, and a summer camp along with many recreational sites and trailheads. The purpose of this project is to replace the existing Tonto Creek Bridge, expand the Horton Springs Parking Lot and improve pedestrian and vehicular safety and access to the recreation sites around the Tonto Creek Bridge on NFSR 289.

    SCOPE OF THE WORK:  The scope of the project includes reconstructing a portion of FR 289, removing the existing bridge and constructing a new single-span bridge over Tonto Creek including new sidewalk and reconstruction of the Horton Springs Parking Lot.  This project includes removal of the existing two-span bridge, including removal of the existing pier.  The project also includes channel grading in Tonto Creek.  The new roadway and bridge will be constructed East of the existing alignment (upstream of the existing bridge) to minimize impacts to public traffic.

    PRINCIPAL WORK ITEMS:

    • 20304-2000 Removal of Bridge:  1 LPSM
    • 20401-0000 Roadway Excavation: 3,100 CUYD
    • 20401-0000 Roadway Excavation (Channel Excavation): 500 CUYD
    • 20441-0000 Waste: 2,300 SQFT
    • 30202-2000 Roadway Aggregate, Method 2: 750 TON
    • 40301-0100 Asphalt Concrete Pavement, Type 1: 535 TON
    • 50101-2600 Minor Concrete Pavement, Plain, 6-Inch Depth, 180 SQYD
    • 55201-0200 Structural Concrete, Class A (AE): 252 CUYD
    • 55302-1100 Precast, Prestressed Concrete Box Beam, Type B2-48: 448 LNFT
    • 55401-1000 Reinforcing Steel: 14,200 LB
    • 55401-2000 Reinforcing Steel, Epoxy-Coated: 18,500 LB
    • 55601-0900 Bridge Railing, Steel:  162 LNFT
    • 62801-000 Temporary Stream Diversion:  LPSM

    ANTICIPATED SCHEDULE: 

    Advertisement – October 2025

    Award – December 2025

    NTP – January 2026

    Contract Completion – October 2026

    Due to weather, no onsite work is anticipated between January and April 2026

    ESTIMATED COST RANGE:  Total estimated cost between $2,000,000 and $5,000,000.

    Key dates

    1. October 20, 2025Posted Date
    2. November 19, 2025Proposals / Responses Due

    AI search tags

    Frequently asked questions

    AZ FS 289(1) AZ NFSR 289 BRIDGE REPLACEMENT is a federal acquisition solicitation issued by DEPARTMENT OF TRANSPORTATION. Review the full description, attachments, and submission requirements on SamSearch before the response deadline.