Active Solicitation · DEPT OF DEFENSE
AI Summary
The Department of Defense is seeking contractors for a construction project to upgrade the Uninterrupted Power Supply system at the 183d Wing in Springfield, IL. The project involves removing an existing UPS and installing a new scalable system. A site visit is planned, and the estimated project cost is between $25,000 and $250,000, following Simplified Acquisition Procedures.
Estimated Solicitation posting - Last week of July
Estimated Site Visit - First week of August (usually a Tuesday or Thursday, 1pm).
A Draft Statement of Work (SOW) is attached to this notice for planning and market research purposes only. Do not submit formal quotes at this time.
1. PROJECT DESCRIPTION
The 183d Wing (183WG) at the Abraham Lincoln Capital Airport, Air National Guard Base, Springfield, IL, has a requirement for a firm-fixed-price construction contract to upgrade the Uninterrupted Power Supply (UPS) system in Building 8.
The contractor shall provide all personnel, equipment, supplies, transportation, tools, materials, supervision, and non-personal services necessary to remove the existing 10 kW UPS system and install a new scalable 20 kW UPS system.
Key scope items include:
Period of Performance: 120 days or less after issuance of Notice to Proceed (NTP).
2. BRAND NAME OR EQUAL
This requirement will be solicited as "Brand Name or Equal" for a system similar to the Vertiv Liebert Model APM2 with modular and scalable architecture. The forthcoming solicitation will explicitly list the salient characteristics that any proposed "equal" equipment must meet to be considered acceptable.
3. MAGNITUDE OF CONSTRUCTION
In accordance with FAR 36.204, the estimated magnitude of this construction project is between $25,000 and $250,000. This acquisition will be conducted using Simplified Acquisition Procedures under FAR Part 13.
4. SITE VISIT / PRE-PROPOSAL CONFERENCE
A formal site visit will be held. The exact date, time, and registration instructions for the site visit will be provided in the official solicitation when it is posted. Contractors are highly encouraged to attend to observe site conditions, conduit routing paths, and space constraints.
5. DISCLAIMER
THIS IS A PRE-SOLICITATION NOTICE ONLY. This is not a Request for Quote (RFQ) or Request for Proposal (RFP). No solicitation document is currently available. All interested parties should monitor SAM.gov for the official solicitation, which will contain the full Statement of Work, applicable FAR/DFARS clauses, Davis-Bacon Wage Determinations, and instructions for quote submission. Do not submit quotes or proposals in response to this notice.