Closed Solicitation · DEPT OF DEFENSE

    EM-DTOS BLDG ROOF REPLACEMENT PROJECT

    Sol. W912P526QA005Sources SoughtSet-aside: Total Small Business Set-Aside (FAR 19.5)NASHVILLE, TN
    Closed
    STATUS
    Closed
    closed Nov 21, 2025
    POSTED
    Nov 17, 2025
    Publication date
    NAICS CODE
    238160
    Primary industry classification
    PSC CODE
    Z2GZ
    Product & service classification

    AI Summary

    The U.S. Army Corps of Engineers is seeking information for a roof replacement project at the EM-DTOS Building in Old Hickory, TN. This is a market research effort to identify capable contractors for a firm fixed-price construction contract. Interested parties should respond by November 21, 2025, with relevant qualifications and experience in roofing projects.

    Contract details

    Solicitation No.
    W912P526QA005
    Notice Type
    Sources Sought
    Set-Aside
    Total Small Business Set-Aside (FAR 19.5)
    Posted Date
    November 17, 2025
    Response Deadline
    November 21, 2025
    NAICS Code
    238160AI guide
    PSC / Class Code
    Z2GZ
    Issuing Office
    W072 ENDIST NASHVILLE
    Primary Contact
    Kenyanna Jennings
    State
    TN
    ZIP Code
    37203-1070
    AI Product/Service
    service

    Description

    REQUEST FOR INFORMATION

    The Government is issuing this Request for Information to determine a competitive basis for this procurement described. This is NOT a solicitation. No reimbursement will be made for any costs associated with providing information in response to this survey.

    This survey is for market research purposes only. Only contractor capable of providing this type of construction should respond to this Request for Information.

    Requirement

    The U.S. Army Corps of Engineers (USACE), Nashville District, anticipates a requirement for a firm fixed-price construction contract for Roof Replacement Project for EM-DTOS Building in Old Hickory, TN. The anticipated NAICS code is 238160 Roofing Contractor, Size Standard $19.0 M. The estimated magnitude of this project is between $25,000 and $100,000.

    Description of Work: The metal roof and all materials shall be capable of performing within the parameters for which it was designed and intended function, in accordance with the operating and performance requirements specified herein in accordance with the manufacturer’s warranty requirements. The new metal roof and materials shall be of standard, commercial, design; prototypes and demos will not be accepted. The installment of the new metal roof and materials shall be completed so that when the roofing is installed and assembled for any purpose and/or function for which it is designed and/or constructed by the manufacturer.

    1. The Contractor shall remove existing 350 square feet of damaged roofing on the southern corner of the DTOS building.
    2. Replacement of the 350 square feet of damaged paneling and insulation removed from the southern corner of the DTOS building.
    3. Conduct an inspection of the entire 5,000 square foot building for any unknown damages that need to be addressed.
    4. Replace the gutter and downspout system for the entire building.
    5. Replacement of the two ventilation fans on the roof of the building and reestablish connection with the wall fan ventilation fans of the building.
    6. Increase insulation value to R-15.
    7. Installation of new roofing materials: The specific type of metal roofing material will depend on the DTOS building’s design and the customer’s and COR’s preferences.
    8. De-energize of any electrical utilities must be requested for approval to the COR no later than 14 days in advance.
    9. Clean-up and disposal: All debris and waste materials from the roof replacement will be properly cleaned up and disposed of daily. Contractors will perform a thorough hands-on daily cleanup and magnet sweep at the end of each day to pick up and dispose of all debris such as nails, screws, etc. In addition, the contractor shall also use a blower to blow the roof surface, decks, and areas around the DTOS building clean of such debris and the end of each day prior to departing from the site.
    10. Final inspection: A final inspection will be conducted to ensure that the new roof meets all safety and quality standards. Contractor shall inform COR within 3 business days prior to final inspection to provide enough time for all required key personnel to attend.

    Survey

    The Government is issuing this notice to determine a competitive basis. This is not a solicitation and the items listed herein are subject to change or eliminated from the requirement. This survey is for market research purposes only. Only contractor capable of providing this type of work should respond to this Request for Information. Your response to this survey is request by 2:00 PM Central Time, November 21, 2025. Please sent by email to Kenyanna Jennings at Kenyanna.L.Jennings@usace.army.mil and Alison Abernathy at Alison.T.Abernathy@usace.army.mil.

    1. Name of your firm:
    2. CAGE:
    3. Point of Contact, Phone Number and Email Address:
    4. Are you a Small Business classified under the above NAICS code? If so, do you fall into a sub-category (e.g.HubZone, 8(a), SDVOSB, WOSB, etc.)?
    5. For this requirement, what percentage of this work would you subcontract (reference FAR 52.219-14, Limitations of Subcontracting, Class Deviation 2019-O0003)?
    6. Do you plan to subcontract to only small businesses?
    7. If the answer to question 3 is “yes”, are these small businesses with a sub-category (e.g.HubZone, 8(a), SDVOSB, WOSB, etc.)?
    8. If this requirement is advertised, do you anticipate submitting a quote?
    9. Lis one (1) contract completed or substantially completed (75%) within the last 10 years valued between $25,000 and $100,000 that demonstrates the contractor’s experience, as a prime contractor or subcontractor, of similar scope as this requirement (Roofing):
    • Project Name:
    • Contract Number (if applicable):
    • Year Completed:
    • Prime Contractor or Sub-Contractor: Type and percentage of work self-performed (based on contract value):
    • Dollar Amount:
    • General Description of Project:

         10. Please provide any additional information you feel is necessary:

    Key dates

    1. November 17, 2025Posted Date
    2. November 21, 2025Proposals / Responses Due

    AI search tags

    Frequently asked questions

    EM-DTOS BLDG ROOF REPLACEMENT PROJECT is a federal acquisition solicitation issued by DEPT OF DEFENSE. Review the full description, attachments, and submission requirements on SamSearch before the response deadline.

    SamSearch Platform

    Stop searching. Start winning.

    AI-powered intelligence for the right opportunities, the right leads, and the right time.