    AI Summary

    The U.S. Army Corps of Engineers is seeking a contractor for the installation of bushings and testing of a spare Generator Step-Up transformer at the John Day Lock and Dam. This project is critical for ensuring operational readiness and involves various tasks including installation, oil processing, and electrical testing. The estimated contract value is between $300,000 and $400,000.

    Contract details

    Solicitation No.
    PANNWD-25-P-0000-002980
    Notice Type
    Presolicitation
    Set-Aside
    Total Small Business Set-Aside (FAR 19.5)
    Posted Date
    October 24, 2025
    Response Deadline
    November 7, 2025
    NAICS Code
    811310AI guide
    PSC / Class Code
    J061
    Issuing Office
    W071 ENDIST PORTLAND
    Primary Contact
    Joseph B. Jarvis
    State
    OR
    ZIP Code
    97204-3495
    AI Product/Service
    service

    Description

    SYNOPSIS

    The U.S. Army Corps of Engineers (USACE) Portland District is soliciting a contract for The John Day Lock and Dam Spare GSU Bushing Install and Transformer Testing in Goldendale, Washington. The proposed project will be a sole-source, firm-fixed price (FFP) contract.

    Background: The existing spare Generator Step-Up (GSU) transformer has been stored at its current location on the intake deck of the John Day Lock & Dam since 1978 and is not currently operational. The spare GSU transformer does not have bushings, low-voltage bushing housing, radiators, fans, temperature indicators, and the control cabinet is missing some devices.

    Currently, John Day Dam does not have an operational spare transformer should one of the in-service units fail which poses significant risk to the regions power needs. This testing contract is critical to understanding if the current ‘spare’ unit can be upgraded and availability for emergency service restored or if an entirely new transformer needs to be purchased. If a new transformer is required, the lead-time on that supply is 3-5 years.

    The existing spare GSU transformer has been stored at its current location between GSU Transformer Banks T3 and T4 on the intake deck (elevation 281) since 1978.
    Serial#            7000893
    Rating            164MVA/218MVA
    Oil Capacity   15539 Gal

    The spare GSU transformer does not have the following components installed:
    • High-voltage (HV) bushing
    • HV neutral bushing
    • Low-voltage (LV) bushings
    • LV bushing housings
    • Radiators
    • Fans
    • Temperature indicators

    John Day Operating Project presently has a spare 500kV shell-form single phase Westinghouse (now owned by Hitachi) GSU
    transformer located between GSU transformer banks T3 and T4 on the intake deck (EL. 281). The Project maintains a spare GSU
    transformer onsite in the event of an existing transformer experiences failure. As part of the solicitation, the spare transformer will be
    installed with Government furnished bushings and tested. In addition, the spare transformer will be furnished and installed with
    bottom terminals for the Government-furnished high-voltage (HV) and low-voltage (LV) bushings and other ancillary materials. The
    requested Hitachi bottom terminals for the HV, HV neutral, and LV bushings would be a direct replacement for the existing Hitachi
    (previously, Westinghouse) bottom terminals on the spare GSU transformer at John Day Operating Project. The GSU system and its
    drawings are proprietary to Hitachi. With the proprietary nature of the system, the installation of the materials and the associated
    electrical testing must be performed by an authorized Hitachi Representative.

    Purpose: The US Army Corps of Engineers – Portland District has a requirement to solicit non-personal services to include the install of government furnished bushings on a spare 500kV shell-form single-phase Westinghouse generator step-up (GSU) transformer and related electrical testing. This requirement also includes furnishing and installing bottom terminals for the government-furnished highvoltage and low-voltage bushings as well as other ancillary materials described herein. All work must be in accordance with the details provided in this Performance of Work Statement (PWS) and comply with all local, state, and federal regulations.

    Task 1 – Provide Mounting Hardware for the Bushings, CLIN 0001

    Provide mounting hardware for one (1) HV bushing, one (1) HV neutral bushing and four (4) LV bushings in accordance with
    requirements listed in section 8.1.1. Submit product data prior to procuring materials. Deliver the mounting hardware to John Day
    Lock and Dam prior to the start of Task 5 onsite work. Payment will be made for the procurement and delivery of the mounting hardware to John Day Dam. Amount will be measured by job and based on COR inspection and confirmation of delivered materials.

    Task 2 – Provide Gaskets for the Bushings, CLIN 0002

    Provide gaskets for one (1) HV bushing and four (4) LV bushings in accordance with requirements listed in sections 8.1.2 and 8.1.3. Submit product data prior to procuring materials. Deliver the bushing gaskets to John Day Lock and Dam prior to the start of Task 5 onsite work. Payment will be made for the procurement and delivery of the bushing gaskets to John Day Dam. Amount will be measured by job and based on COR inspection and confirmation of delivered materials.

    Task 3 – Provide Bottom Terminal, Bottom Shield, Drawings and Associated Mounting Hardware for the HV Bushing, CLIN 0003

    Provide the bottom terminal, bottom shield and associated mounting hardware for the HV bushing in accordance with requirements listed in section 8.1.4. Submit product data prior to procuring materials. Deliver the bottom terminal, bottom shield and associated mounting hardware to John Day Lock and Dam prior to the start of Task 5 onsite work. Payment will be made for the procurement and delivery of the bottom terminal, bottom shield and associated mounting hardware for the HV bushing. Amount will be measured by job and based on COR inspection and confirmation of delivered materials.

    Task 4 – Provide Bottom Terminals, Drawings and Associated Mounting Hardware for Four (4) LV Bushings, CLIN 0004

    Provide the bottom terminals and associated mounting hardware for four (4) LV bushings in accordance with requirements listed in section 8.1.5. Submit product data prior to procuring materials. Deliver the bottom terminals and associated mounting hardware to John Day Lock and Dam prior to the start of onsite work. Payment will be made for the procurement of the bottom terminals and associated mounting hardware for the four (4) LV bushings. Amount will be measured by unit price and based on COR inspection and confirmation of delivered materials.

    Task 5 – Drain Oil, Install Bushings, Perform Oil-filling, and Processing, and Perform Electrical Testing of the Spare Transformer, CLIN 0005

    Provide all pre-work submittals as listed in Section 8 for government review and approval prior to the start of any onsite work. Provide all labor, equipment, materials, including mobilization and demobilization, required to drain the oil, install government furnished bushings, perform oil-filling, oil processing, oil analysis, and perform electrical testing on the spare transformer in accordance with the requirements of “Clause 5, Liquid-immersed power transformers rated 10 MVA and above or with high-voltage windings 69 kV and above” of IEEE C57.93 at John Day Lock and Dam. Payment will be made for completion of the work and
    submittal of the Final Spare GSU Report. Amount will be measured by job and based on Government inspection of the completion of requirements in PWS Sections 8 and 9.

    Contract Period of Performance: The estimated Period of Performance for this contract is approximately FY26

    Estimated Contract Value: The estimated cost of the project is approximatley $300,000.00 - $400,000.00.

    Set Asides and Codes: 100% Small Business Set-Aside. The North American Industrial Classification Code (NAICS) for this requirement would be 811310 - Commercial and Industrial Machinery and Equipment (except Automotive and Electronic) Repair and Maintenance. The related size standard is $11M. The Product Service Code (PSC) is J061 - MAINT/REPAIR/REBUILD OF EQUIPMENT- ELECTRIC WIRE AND POWER DISTRIBUTION EQUIPMENT

    Selection Process: Sole-Source acqusition

    Anticipated Solicitation Release Date: The government anticipates releasing the solicitation in November 2025. The closing date for proposals will be approximately 30 days later (TBD). Actual dates and times will be identified in the solicitation. Responses to this synopsis are not required. Additional details may be found in the solicitation when it is posted.

    System for Award Management (SAM): Offerors must register in the SAM at https://www.sam.gov/portal/public/SAM/ prior to submission of proposals and prior to receiving an award.

    Point of Contact: The USACE-NWP points of contact for this action are Joseph Jarvis at joseph.b.jarvis@usace.army.mil and Cory Pfenning at cory.r.pfenning@usace.army.mil. Email is the only method for receiving responses to this pre-solicitation notice.

    Point of Contact for small business questions or assistance is the Portland District Deputy for Small Business, Maura Timmerman at (402) 370-0095 or maura.j.timmermann@usace.army.mil.

    THIS PRE-SOLICITATION NOTICE IS FOR THE PURPOSE OF INFORMING INDUSTRY THAT THIS SOLICITATION WILL BE POSTED ON SAM ON OR ABOUT 31 OCTOBER 2025. THIS NOTICE IS NOT A REQUEST FOR PROPOSALS AND PROPOSALS RECEIVED AS A RESULT OF THIS PRE-SOLICITATION NOTICE WILL NOT BE ACCEPTED OR EVALUATED.

    THE GOVERNMENT RESERVES THE RIGHT TO CANCEL THIS SOLICITATION EITHER BEFORE OR AFTER THE CLOSING DATE. NO REIMBURSEMENT WILL BE MADE FOR ANY COSTS ASSOCIATED WITH PROVIDING INFORMATION IN RESPONSE TO THIS PRESOLICITATION NOTICE OR ANY FOLLOW-UP INFORMATION REQUEST.

    Key dates

    1. October 24, 2025Posted Date
    2. November 7, 2025Proposals / Responses Due

    AI search tags

    Frequently asked questions

    JDA SPARE GSU BUSHING INSTALL AND TRANSFORMER TESTING is a federal acquisition solicitation issued by DEPT OF DEFENSE. Review the full description, attachments, and submission requirements on SamSearch before the response deadline.

    SamSearch Platform

    Stop searching. Start winning.

    AI-powered intelligence for the right opportunities, the right leads, and the right time.