SLED Opportunity · IDAHO · ADA COUNTY HIGHWAY DISTRICT

    FY26 Large Patch Pavement Repair Program

    Issued by Ada County Highway District
    localInvitation To BidAda County Highway DistrictSol. 248429
    Closed
    STATUS
    Closed
    due Apr 22, 2026
    PUBLISHED
    Apr 7, 2026
    Posting date
    JURISDICTION
    Ada County
    local
    NAICS CODE
    237310
    AI-classified industry

    AI Summary

    Ada County Highway District seeks bids for the FY26 Large Patch Pavement Repair Program involving asphalt removal, base preparation, paving, and restriping at six locations, including pedestrian ramp improvements at one site. Bids are due by April 22, 2026, with detailed contract and submission requirements.

    Opportunity details

    Solicitation No.
    248429
    Type / RFx
    Invitation To Bid
    Status
    open
    Level
    local
    Published Date
    April 7, 2026
    Due Date
    April 22, 2026
    NAICS Code
    237310AI guide
    State
    Idaho
    Agency
    Ada County Highway District

    Description

    This project will replace deteriorated asphalt at six locations in Ada County. Work at each site includes asphalt removal, base preparation, paving, and restriping. One location will also include pedestrian ramp improvements.

    See Special Provisions SP 11554 – Construction Staging and Traffic Control Plan and Supplemental General Notes for date requirements, construction allowances, and important information for each segment.

    Background

    NOTE: Bid Opening Zoom Meeting Link:

    Join Zoom Meeting:

    BID ZOOM MEETING LINK

    Meeting ID: 853 4920 0922

    Passcode: 028768

    Project Details

    • Reference ID: CT226-22
    • Department: Safety Engineering
    • Department Head: Matt Degen (Safety Engineering Manager)

    Important Dates

    • Questions Due: 2026-04-17T18:00:00.000Z
    • Answers Posted By: 2026-04-20T22:00:00.000Z

    Evaluation Criteria

    • FORMAT

      The Contract Documents are divided into parts, divisions, and sections in keeping with Industry practice in order to separate categories of subject matter for convenient reference thereto. Generally, there has been no attempt to divide the specification sections into work performed by the various building trades, work by separate subcontractors, or work required for separate facilities in the project.

    • Special Provisions

      Please refer to the "Attachments" section for Special Provisions and other pertinent supporting documents.

    • 1. DEFINITIONS

      “Addenda” or “Addendum” shall mean a change made by the Owner in the bidding or contract documents prior to execution of the contract.

      “Bar Scheduling Chart” shall mean a construction schedule which contains a bar for each construction activity as set forth in the specifications and indicates the number of days to be actually worked reflecting activity start and end dates. 

      “Calendar Days” shall mean any day shown on the calendar, beginning and ending at midnight.

      “Contract Documents” shall mean the documents that establish the rights and obligations of the parties and include the Instructions to Bidders, Contract Agreement, Contract Certification, Addendum, Written Amendment (which pertain to Contract Documents), Bid Schedule, Notice to Proceed, Labor/Material Payment Bonds, Performance Bond, General Conditions Plans & Specifications, together with all Change Orders, Field Directives (also known as “AVOs”) and Resident Engineer’s written interpretations and clarifications issued on or after the effective date of the agreement. Shop Drawings and the reports and drawings of subsurface and physical conditions are not Contract Documents.

      “Contract Price” shall mean the monies payable by the Owner to the Contractor for completion of the Work in accordance with the Contract Documents.

      “Contract Time” shall mean the number of days or the dates stated in the Contract Agreement to complete the Work so that it is ready for final payment as evidenced by Resident Engineer’s written certification of Final Acceptance.

      “Contract Agreement” shall mean the written instrument, which evidences the contract between Owner and Contractor covering the Work.

      “Contractor” shall mean the individual, firm, corporation, or joint venture undertaking the execution of the Work under the terms of the Contract Documents.

      “CPM Schedule” shall mean a planning, scheduling and control technique whereby a construction project is completely planned and scheduled and an arrow diagram drawn to show the interconnected individual tasks involved in constructing the project. CPM Schedules permits determination of the relative significance of each project event, and establishes the optimum sequence and duration of the operations.

      “Final Acceptance” shall mean a written document executed by the Resident Engineer acknowledging that the Work has been completed and is acceptable and that all other obligations imposed on the Contractor by the Contract Documents have been fulfilled.

      “IDAHO STANDARDS FOR PUBLIC WORKS CONSTRUCTION (ISPWC) Specifications and Drawings”, shall mean those standards adopted by Ada County Highway District Commissioners for use on work performed within the Highway District rights-of-way. Any ACHD Supplemental Standard Specifications to the ISPWC manual shall also be considered part of the adopted standards. 

      The Contractor’s attention is specifically directed to the fact that the Ada County Highway District Commission has NOT adopted Section 100-General Conditions, of the ISPWC document; accordingly, bidders should disregard this section of the ISPWC manual for work performed for Ada County Highway District. 
      Copies of the ISPWC specifications and drawings manual are available from Local Highway Technical Assistance Council (LHTAC), 3330 Grace St., Boise, Id.  83703.  The ACHD Supplemental Standard Specifications are available from ACHD.

      “Managing Engineer” shall mean the Manager of the Engineering Department, Ada County Highway District. 

      “Owner” as hereinafter used in this agreement, shall mean Ada County Highway District, or its successors and assigns. 

      “Project Inspector” shall mean the agent of the Owner and the Resident Engineer present on the site of the Work on behalf of the Owner to provide more extensive observations of the Work.

      “Resident Engineer” as hereinafter used in this agreement, shall mean the Professional Engineer or his agent employed by the Owner who directly represents the Owner during the Work and has full authority to act on behalf of the Owner.

      “Subcontractor” as hereinafter used in this agreement, shall mean those persons or entities hired by the Contractor to perform a portion of the Work, and includes one who furnishes material and/or labor, but does not include one who merely furnishes material.

      “Work” shall mean the entire completed construction project required under the Contract Documents. This includes and is the result of performing or providing all necessary labor, services and documentation to produce such construction, and furnishing, installing and incorporating all materials and equipment into such construction as required by the Contract Documents.

    • GENERAL DESCRIPTION OF THE PROJECT

      A general description of the work to be done is contained in the Invitation to Bid (ITB). The scope is indicated on the accompanying drawings and specified in the applicable parts of these Contract Documents.

    • 2. SCOPE OF CONTRACT

      It is the intention of this agreement that Work shall be done in a workmanlike manner as called for in the Contract Documents to the satisfaction and final approval of the Owner.

    • DOCUMENT INTERPRETATION
      1. The Contract Documents governing the work proposed herein consist of the drawings and all material bound herewith. Said documents are intended to be compatible and to provide all details reasonably required for the execution of the proposed work.
      2. Anyone submitting a proposal shall have thoroughly examined all the Contract Documents. Should there be any doubt as to any meaning or intent of any Contract Document statement or provision, all questions or clarifications must be posted in the Q&A section of the solicitation located at the eProcurement Portal located at https://procurement.opengov.com/portal/achdidaho . All questions or clarifications must be submitted by noon on the Monday prior to the Bid Opening.
      3. Any interpretation that may alter or change the Contract Documents will be digitally published, in the form of Addenda, which will be furnished to officially listed Plan Holders via the eProcurement Portal . Bidders shall acknowledge receipt of Addenda as instructed.
    • 3. EXECUTION, CORRELATION AND INTENT OF DOCUMENTS

      The Contract Agreement shall be signed in triplicate by the Owner and Contractor.

      The Contract Documents are complimentary and what is called for by one shall be binding as if called for by all. In case of conflict between plans and the specifications detailing the items being represented by such plans, the specifications shall govern. In case of a discrepancy in any of the plans, drawings, specifications, or other contract documents, such discrepancy shall be promptly submitted in writing to the Resident Engineer for clarification, resolution, or determination. Any work done by the Contractor prior to the Resident Engineer’s clarification, resolution or determination shall be done at his sole risk and expense.

      In resolving inconsistencies among two or more sections of the Contract Documents precedence shall be given in the following order:

      • Change Orders
      • Special Provisions
      • Plans
      • Supplemental Specifications
      • General Conditions
      • Standard Specifications

      Figures and dimensions on drawings shall take precedence over scale dimensions and detailed drawings shall take precedence over general drawings.

      The apparent silence of the specifications and plans as to any detail or a description concerning any point shall be regarded as meaning that only the best general practice is to prevail and that only approved material and workmanship of first quality should be used.

      Failure to execute the contract and file the executed contract and Contract Certification with Owner by the date and time specified by Owner in the “Notice of Intent to Award Letter,” may be just cause for the refusal to award and forfeiture of the Contractor’s Bid Security to Owner as liquidated damages.

    • BIDDER'S UNDERSTANDING
      1. Each Bidder must inform their self of the conditions relating to the execution of the work, and it is assumed that the Bidder will adequately inspect the site and become thoroughly familiar with all site conditions and the Contract Documents. Failure to do so will not relieve the successful Bidder of their obligation to enter into a contract and complete the contemplated work in strict accordance with the Contract Documents. It shall be the Bidder's obligation to verify complete satisfaction to all information concerning all site conditions.
      2. Ada County Highway District (ACHD) will make available for inspection by prospective Bidders, upon request and prior to the final inquiry deadline, during regular business hours, any information that it may have as to the subsurface conditions and surface topography at the work site. Investigations, if any, conducted by ACHD of subsurface conditions were made for the purpose of study and design and the ACHD does not assume any responsibility whatever with respect to the sufficiency of borings or of the logs of test borings or of other investigations that have been made or of the interpretations made therefrom; and there is no warranty or guarantee, either expressed or implied, that the conditions indicated by such investigations are representative of those existing through-out such area, or any part thereof.
      3. Logs of test borings or topographic maps showing a record of the data obtained by ACHD investigations of surface and subsurface conditions that are made available or bound herewith shall not be considered a part of the contract documents; said logs represent only the opinion of the Engineer as to the character of the materials encountered by the Engineer in their investigations and is provided only for the convenience of the Bidders.
      4. Information derived from inspection of logs of test borings, or topographic maps, or from drawings showing location of utilities and structures will not in any way relieve the Bidder from any risk or the responsibility to properly examine the site and make such additional investigations as necessary or from properly fulfilling all the terms of the Contract Documents.
      5. Each Bidder shall inform their self of, and the Bidder awarded a contract shall comply with, all Federal, State, and local laws, statutes and ordinances relative to the execution of the work. This requirement includes, but is not limited to, applicable regulations concerning minimum wage rates; non-discrimination in the employment of labor; protection of public and employee safety and health; environmental protection; the protection of natural resources; fire protection; burning and non-burning requirements; permits, fees and similar requirements.
      6. The submission of a Bid will constitute an incontrovertible representation by the Bidder that the Bidder has been given adequate opportunity to get acquainted with the scope of the Work, the conditions imposed upon execution of the Work and to the Bidder’s satisfaction, has resolved any questions regarding any perceived conflicts, ambiguities, errors, and discrepancies contained within the Contract Documents.
      7. ACHD has prepared and upon request will provide prospective Bidders with electronic versions of the Contract Documents and Proposal Documents for Submittal including the Design Plan Sets and Specifications for the proposed project in PDF format. The original digital copy of the electronic design data is retained on file at the ACHD. The electronic data is provided for Bidder convenience and information and will not become part of the Contract. No guarantee or warranty is made by ACHD that the electronic design data provided to the Bidder is compatible with any of the systems that are used by the Bidder, is complete, is representative of the actual conditions at the sight of work, or accurately reflects the quantities and character of the actual work required. The furnishing of electronic design data does not relieve the Bidder from risks or of duty to make examination and investigations of the site of work or of other responsibilities as outlined in the Contract Documents including, but not limited to, the General Conditions.
    • 4. SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK

      The Contractor acknowledges that it has taken steps reasonably necessary to ascertain the nature and location of the Work, and that it has investigated and satisfied itself as to the general and local conditions which can affect the Work or its cost, including but not limited to (1) conditions bearing upon transportation, disposal, handling and storage of materials; (2) the availability of labor, water, electric power, and roads; (3) uncertainties of weather, river stages or similar physical conditions at the site; (4) the conformation and conditions of the ground; (5) the nature of businesses that may be affected by the Work, including the impacts of driveway closures or restriction, restricted travel through the project, and/or the hours of construction activity; and (6) the character of equipment and facilities needed preliminary to and during work performance. The Contractor also acknowledges that it has satisfied itself as to the character, quality, and quantity of surface and subsurface materials or obstacles to be encountered insofar as this information is reasonably ascertainable from an inspection of the site, including all exploratory work done by Owner, as well as from the drawings and specifications made as part of the contract. Any failure of the Contractor to take the actions described and acknowledged in the paragraph will not relieve the Contractor from responsibility for estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expense to the Owner.

      Owner assumes no responsibility for any conclusions or interpretations made by Contractor based on the information made available by the Owner. Nor does Owner assume responsibility for any understanding reached or representation made concerning conditions, which can affect the Work by any of its officers or agents before the execution of the Contract, unless that understanding or representation is expressly stated in this Contract. 

      The Contractor’s attention is especially directed to the Contract Documents and such other materials included as part of the contract requirements in order to verify for himself, to his complete satisfaction, all information concerning site conditions and the work to be done. 

    • 5. PLANS & SPECIFICATIONS

      The Owner shall be responsible for the adequacy and sufficiency of its plans and specifications. The Owner, through the Resident Engineer, shall furnish plans, which represent the requirements of the Work to be performed under the contract. If the Contractor observes that the Plans & Specifications are incorrect or contrary to law, it shall immediately notify the Resident Engineer, in writing, and any necessary changes shall be adjusted as provided in a contract changes paragraph.

      Contractor will be furnished free of charge up to 10 copies of the construction Plans and Specifications depending upon the size and complexity of the project. Additional sets over the 10 copies will be furnished to the Contractor upon request, at the cost of reproduction, postage and handling.

      All models, drawings, or copies thereof furnished by the Owner are property of the Owner, and shall not be reused in other work, and upon request shall be returned to the Owner at the completion of the work and prior to final payment. 

    • DRAWINGS

      The number of drawings consists of Nineteen (19) Plan Sheets.

    • 6. VERBAL AGREEMENTS

      No verbal agreements or conversations with any officers, agents, or employees of the Owner, either before or after execution of this contract, shall affect or modify any of the terms or obligations contained in any of the documents comprising the Contract Documents.

    • TYPE OF PROPOSAL
      1. Unit Price: When the proposal for the work is to be submitted on a unit price basis, unit price bids will be required for all items of work set forth in the proposal, except those designated to be paid for as a lump sum. IN CASE OF DISCREPANCY BETWEEN UNIT PRICES AND TOTALS, UNIT PRICES WILL PREVAIL.
        1. The estimate of quantities of work to be done is tabulated in the Contract Documents and, although stated with as much accuracy as reasonably possible, is approximate only and is established solely for the basis of calculation upon which the award of contract shall be made.
        2. Payment to the Contractor will be made on the measurement of work actually performed by the Contractor as specified in the Contract Documents. ACHD reserves the right to increase or decrease the amount of any class of work as may be deemed necessary, unless otherwise specified in the Contract Documents.
      2. Lump Sum: When the proposal for the work is to be submitted on a lump sum basis, a single lump sum price shall be submitted in the appropriate place in the Proposal Documents For Submittal. The total amount to be paid the Contractor shall be the amount of the lump sum.
    • PREPARATION OF PROPOSALS
      1. All bidders must submit their proposals as electronically sealed bids utilizing the eProcurement Portal located https://procurement.opengov.com/portal/achdidaho.
      2. All Contract Documents and Plans are available through the eProcurement Portal .
      3. All blanks on the Vendor Questionnaire and Bid Schedule(s) shall be completed, and the Authorized Signature Form electronically signed as provided. If the Bidder is a corporation, the legal name of the corporation shall be set forth, together with the signature of the officer or officers authorized to sign contracts, attested to by the Secretary of the Corporation, and affix corporate seal, on behalf of the corporation. If the Bidder is a partnership, the true name of the firm shall be set forth, together with the signature of the partner or partners authorized to sign contracts on behalf of the partnership. If the signature is by an agent other than an officer of a corporation or a member of a partnership, a notarized power-of-attorney must be on file with the ACHD prior to opening of proposals or submitted with the proposal.
      4. Bidders may modify their electronic Proposals at any time prior to the scheduled closing date and time for the receipt of bids.
      5. If any document uploaded and submitted to the eProcurement Portal contains omissions, erasures, or alterations, they shall be initialed by an authorized representative of the Bidder. In addition, the Proposal submitted shall not contain additions of any kind, prices uncalled for, or fail to conform to the conditions of the published Invitation to Bid.
      6. Late Bids are not allowed through the eProcurement Portal website. ACHD will not accept a late Bid or Proposal, in any format, regardless of cause or circumstance. Bidders are solely responsible to ensure timely submission of their Proposals to ACHD via the eProcurement Portal.
      7. All electronic Bids shall be accompanied by the Bid Security and other required documents. If a Cashier’s Check or Certified Check is utilized as the Bid Security, then the Check shall be hand-delivered to or sent to and received by ACHD within 48 hours of the Bid Opening date and time stated in the ITB. The shipping envelope for the Check Bid Security shall be plainly marked with the Project Name, Contract Number, Bid Opening date and time, and state “Bid Security Enclosed”.
      8. ACHD assumes no responsibility for failure of any computer or other equipment to deliver all or a portion of the bid or proposal at the time or to the location required by the solicitation.
      9. Following the Bid Opening, the Bid Results will be available at the eProcurement Portal.
      10. Neither OpenGov nor ACHD warrant that access to and use of the eProcurement Portal will be free from interruptions or free from errors, nor shall OpenGov or ACHD be responsible for any inadvertent disclosure of bid repository information or any unauthorized access to bid repository information by third persons.
      11. In the case of known loss of services by OpenGov within two (2) hours prior to the deadline for submission of bids, ACHD will delay the deadline for bid submissions to ensure the ability of potential Bidders to submit bids. If this occurs, instructions will be communicated to known Plan Holders.
    • 7. PRECONSTRUCTION CONFERENCE

      Contractor, upon award of the Work project and before construction commences, shall schedule a meeting with the Owner or his duly authorize representative. Contractor shall instruct his primary Subcontractors or their representatives to attend this meeting. Contractor shall bring to this meeting the schedule setting forth the preconstruction schedule as provided in subparagraph (c), a complete list of Subcontractors for all phases of the Work, a list of known material suppliers for all phases of the Work, as well as the designated safety employee as required in General Condition 15(c).  The location of this meeting shall be at Owner’s office. 

      Prior to the commencement of the Work, Contractor shall designate a competent Superintendent and will inform Owner in writing of the Superintendent’s name and, upon request Contractor shall provide the qualifications, experience and address of the Superintendent. Superintendent will be present at the Work site at all times while Work is actually in progress and will have complete authority to represent and act for Contractor. Superintendent shall supervise and direct the Work and shall not physically participate in the actual performance, assemblage or installation of the Work. All directions given to Superintendent by Owner shall be as binding on the Contractor as if they were given directly to Contractor. If Contractor’s Superintendent or any of his assistants are or become unsatisfactory to Owner then the unsatisfactory employees shall be promptly replaced upon request of Owner at no additional expense to the Owner. 

      If the total amount of the Contract Price exceeds one million dollars ($1,000,000.00), the Contractor will furnish a CPM schedule both in hardcopy and in electronic media format. 

      If the total amount of the Contract Price does not exceed one million dollars (1,000,000.00), the Contractor may use a Bar Scheduling Chart in hardcopy. 

      Contractor shall diligently prosecute the Work, providing sufficient labor, materials and other supplies at all times to assure performance of the Work in an orderly fashion according to the schedule and to ensure that the Work is complete by the time set for Completion.

    • “OR-EQUAL” ITEMS

      The Contract, if awarded, will be on the basis of material and equipment specified or described in the Proposal Documents for Submittal without consideration of possible “or- equal” items. Whenever it is specified or described in the Proposal Documents For Submittal that an “or-equal” item of material or equipment may be furnished or used by the Contractor if acceptable to the Resident Engineer, Application for Acceptance will not be considered by the Resident Engineer until after the execution of Contract.

    • 8. BONDS, WORKMAN COMPENSATION. PUBLIC LIABILITY AND PROPERTY DAMAGE INSURANCE

      Pursuant to Title 54, Chapter 19 of the Idaho Code, before execution of the contract by the ACHD Commission, Contractor shall furnish bonds acceptable to the Owner for a sum equal to the full amount of the Contract Price for a Performance Bond and the full amount of the Contract Price for a Labor and Material Payment Bond. Such bonds shall become binding upon the award of the Contact to the Contractor. Such bonds shall be conditioned on the faithful performance of the Work required by this project.

      Surety companies providing the bonds noted above shall be listed on the current Federal Treasury List published annually in the FEDERAL REGISTER.

      Worker’s Compensation. Contractor shall provide Certificates of Insurance showing statutory Worker’s Compensation coverage and showing Employer’s Liability coverage with minimum limits of $1,000,000. Owner need not be named as additional insured on the Employer’s Liability coverage or the Worker’s Compensation coverage. Owner must be given 30 days prior written notice of cancellation of either coverage.

      Automobile. Contractor must provide Certificates of Insurance showing that it maintains Comprehensive Automobile Liability Insurance for all owned, non-owned and hired vehicles with single limits of at least $2,000,000 per occurrence. Such coverage must name Owner as a co-insured and Contractor shall provide a Certificate to the Owner showing such coverage and showing that such coverage will not be canceled by the insuring company without 30 days prior written notice to Owner.

      General Liability. Contractor shall procure and maintain until the Work has been completed and accepted by the Owner, Commercial General Liability coverage with combined single limits of not less than $2,000,000 per occurrence. Contractor shall provide Certificates of Insurance which show broad form property damage coverage including, but not limited to, damage arising from blasting and collapse of structure. The Policy shall include Contractor’s Protective Liability Insurance and completed operations coverage. Coverage shall be extended to include Contractor, Subcontractor(s) and any independent contractors directly or indirectly employed by all of them. The General Liability policy shall be endorsed to include personal injury, libel, slander, and false arrest. All policies shall be written on an occurrence basis rather than claims made. Such coverage shall be provided by the Contractor either by separate policy for Contractor and for Owner, or by naming Owner as an Additional Named Insured. If coverage is obtained by naming Owner as an Additional Named Insured, the policy shall contain a Separation of Insured Clause and the Certificate shall so indicate. If the required coverage is obtained through a Commercial General Liability policy backed with Umbrella Coverage, the certificate for Umbrella Coverage shall show that Owner will be given 30 days prior written notice of cancellation.

      Failure to file acceptable bonds and insurance declarations as specified herein with Owner by the date and time specified by Owner in the “Notice of Intent to Award Letter,” may be just cause for the refusal to award and forfeiture of the Contractor’s Bid Security to Owner as liquidated damages.

    • STATE AND LOCAL SALES AND USE TAXES
      1. State and local sales and use taxes, as required by the laws and statutes of the State and its political subdivisions, shall be paid by the Bidder. Prices quoted in the proposal shall include sales and/or use tax, unless provisions are made in the Contract Documents form to separately itemize such taxes.
      2. The Bidder is advised that in accordance with Idaho Code Chapter 15, Title 63, Collection of Taxes from Public Works Contractors, Section 63-1502; that as a condition precedent for the construction of any public works in this state, the Bidder will be required to show proof that they are authorized to do business in the State of Idaho and furnish evidence that they have paid or secured, to the satisfaction of the respective taxing unit, all taxes for which the Bidder and the Bidder property is liable then due or delinquent. Verification that all taxing requirements have been met may be obtained from the State of Idaho, Department of Revenue and Taxation, State Tax Commission, at 700 West State Street, Boise, Idaho 83722.
    • 9. LANDS FOR WORK

      The Owner shall provide, as indicated on the drawings, the lands on which Work under this agreement is to be done, rights-of-way for access to same, and such other lands as are designated on the drawings for use by all parties performing work, or the inspection thereof, within the Work area. 

      The Contractor shall provide, at his sole expense and without liability to the Owner, any additional lands and access thereto that may be required for temporary construction facilities, and/or storage of materials. 

    • NAMING OF STATUTORILY-REQUIRED SUBCONTRACTORS
      1. Pursuant to Idaho Code, Section 67-2310, the Bidder shall be required to include in their proposal the name and address or names and addresses of the subcontractor(s) who shall perform the plumbing, heating, ventilation, and/or air conditioning (HVAC); and/or electrical work under the construction contract in the event the Bidder secures said contract. If the Bidder intends to self-perform the plumbing, HVAC, and/or electrical work, then the Bidder must be licensed by the State of Idaho to perform such work. The Bidder shall demonstrate compliance with this requirement by listing on the Bid Proposal the Bidder’s valid license number for the plumbing, HVAC, and/or electrical work to be performed by the Bidder.
      2. Failure to name subcontractors as required shall render any bid submitted by a Bidder unresponsive and void.
    • 10. DIFFERING SITE CONDITIONS

      The Contractor shall promptly, and before such conditions are disturbed, notify the Resident Engineer in writing of unknown physical conditions at the site, of an unusual nature differing materially from those ordinarily encountered and generally recognized as inhering in work of the character provided in the Construction Documents.

      The Resident Engineer shall promptly investigate the conditions and if he finds that such conditions do materially so differ and cause an increase or decrease in the Contractor’s costs of, or time required for performance of, any part of the Work under the Contract Documents (whether or not changed as a result of such condition), an equitable adjustment shall be made and the agreement modified in writing accordingly. 

      No claim of the Contractor for differing site conditions shall be considered or allowed unless the Contractor shall have given notice as required herein.

      No claim by the Contractor for an equitable adjustment hereunder shall be allowed if asserted after final payment under this agreement. 

    • 11. MATERIALS, APPLIANCES, SUBCONTRACTORS, EMPLOYEES AND EQUIPMENT

      Unless otherwise stipulated, the Contractor shall provide and pay for all materials, labor, water, tools, equipment, light, power, transportation, and other facilities necessary for execution and completion of the Work.

      The Contractor shall pay each subcontractor for satisfactory performance of its contract no later than 20 calendar days from receipt of each payment the Contractor receives from ACHD.  The Contractor shall return retainage to each subcontractor within 20 calendar days after receiving retainage.  The Contractor shall certify with each “Request for Progress Payment” that payment to subcontractors has been made within the prescribed time frames.  The certification will be made on forms provided by the ACHD and returned within 20 calendar days of receiving the estimate payment.

      Unless otherwise specified, all materials incorporated in the permanent Work shall be new; both workmanship and materials shall be of good quality. The Contractor shall, if required, furnish the Owner satisfactory evidence as to the kind and quality of materials used in said construction.

      The Contractor shall at all times enforce strict discipline and good order among his employees, and shall seek to avoid employing on the job any unfit person or persons, or anyone not skilled in the work assigned to him. In the event any of the Contractor’s employees are found to be incompetent, unreliable, fail to perform in a workmanlike manner, or as instructed, or who shall commit trespass upon any public or private property in the vicinity of said Work, such employee shall be discharged by the Contractor immediately and shall not again be employed on said project.

      It shall be the duty of the Contractor herein to prevent employees, agents, or Subcontractors of the Contractor, from performing work in a negligent manner. The Contractor agrees to indemnify, save and hold harmless Owner from any and all negligent acts, liability, loss, or damages caused by or arising out of the negligence of the Contractor’s employees, Subcontractors, officers, or agents. 

      The Contractor’s tools and equipment used on the Work shall be furnished in sufficient quantity and of a capacity and type that will safely perform the work specified, and shall be maintained and used in a manner that will not create a hazard to persons or property, or cause a delay in the progress of the work. 

    • MODIFICATION OF PROPOSAL

      In all instances, after having submitted an electronically sealed proposal to ACHD via the eProcurement Portal, a Bidder may only modify their Proposal at any time prior to the scheduled closing date and time for the receipt of bids via the eProcurement Portal.

      In all instances, Proposal modifications that are not submitted via the eProcurement Portal, or that contain irregularities that make the Proposal incomplete, indefinite, or ambiguous, will be rejected.

    • WITHDRAWAL OF PROPOSAL

      eProcurement Portal withdrawn prior to the scheduled time for the opening of proposals via the eProcurement Portal (by Bidder or authorized agent). No proposal may be withdrawn after the time scheduled for opening of proposals, unless the time specified in Item 15, Award of Contract, of these Instructions to Bidders shall have elapsed. Please note the only exception under Idaho Code 54-1904B and 54-1904C.

    • 12. PROTECTION OF THE PUBLIC, OF WORK AND PROPERTY

      The Contractor shall observe and comply with all applicable local, city, county, state and federal laws, rules, ordinances and regulations in effect with respect to the obstruction and/or work upon streets, keeping open passageways and protecting same where they are exposed or would be dangerous to public travel during the entire period of Work.

      No road shall be closed by the Contractor to the public except by written permission of the Resident Engineer or in accordance with contract provisions. The Contractor shall provide a minimum of 48-hours notice of any impending closure to either the owner or manager of a business that will be affected by any driveway closure. Traffic control devices shall be in accordance with the “Manual on Uniform Traffic Control Devices”, published by the US Department of Transportation, Federal Highway Administration, as adopted by the Idaho Department of Transportation, current edition, and all revisions and amendments thereto. 

      The Contractor shall have sole responsibility to provide, erect, and/or maintain any and all traffic control devices (such as signing, striping, barricades, barriers, lights, flares, danger signals, or flagging) necessary to effectively guard and protect the public from accidents, dangers or injury. The failure of the Resident Engineer to notify the Contractor to maintain traffic control devices shall not operate to relieve the Contractor from this liability. 

      All traffic control devices including signs, barricades, vertical panels, drums, warning lights, arrow boards, changeable message signs, cones and tubular markers that meet the requirements of American Traffic Safety Services Association (ATSSA), “Quality Standard for Work Zone Traffic Control Devices” (latest edition) shall be used on this project. Copies of the publication are available for the Contractor’s use prior to construction from ATSSA, 5440 Jefferson Davis Highway, Fredericksburg, VA 22407; telephone 703/898-5400 or FAX 703/898-5510. Compliance with these requirements will be considered incidental to the contract and no extra compensation will be allowed. 

      The Resident Engineer or his designated Project Inspector will be the judge in determining the acceptability of the condition and appearance of the traffic control and work zone devices. Devices determined to be unacceptable are to be immediately removed from the site and replaced with acceptable devices. 

      The Contractor shall continuously maintain adequate protection of all work from damage, and shall take all reasonable precautions to protect the Owner’s property from injury or loss arising out of, or in connection with, this agreement. The Contractor shall reimburse Owner for any and all damages or loss to the Work or to the property of the Owner resulting from lack of reasonable protective precautions or negligence of Contractor, except as may be due to error in the Contract Documents or caused by agents or employees of the Owner.

      The Contractor shall protect the Work and materials from damage due to the nature of the work, the elements, carelessness of other contractors, or from any cause whatever until the completion and acceptance of the Work. Unless otherwise provided, all loss or damage arising out of the nature of the Work to be done under the Contract Documents from any unforeseen obstructions or defects which may be encountered in the prosecution of the Work or from the action of the elements, shall be sustained by the Contractor. 

      The Contractor shall at all times safely guard the Owner’s property from injury or loss in connection with the Work. The Contractor shall at all times safely guard and protect from damage its own work, and that of adjacent property, as provided by law or the Contract Documents.  All passageways, guard fences, lights, and other facilities required for protection by state or municipal laws, regulations and local conditions, must be provided for and maintained.

      In an emergency affecting the safety of life or property, the Contractor is hereby permitted to act at his discretion to prevent such threatening loss or injury. Any compensation claimed by the Contractor as a result of said emergency shall be determined pursuant to the terms of the Contract Documents. 

      All loads of gravel, sand, dirt, landscape bark and other loose material hauled upon the public roadways within Ada County by the contractor or any of its subcontractors, shall be covered and properly secured so as to prevent the load from dropping, sifting, leaking, or otherwise escaping from the vehicle or becoming loose, detached, or in any manner a hazard to other uses of the public roadway.  Each violation of this requirement shall be subject to liquidated damages in an amount not less than $500.00 and not more than $1,000.00 as determined by the ACHD Director, and such liquidated damages shall be cumulative and in addition to any other liquidated damages that might be imposed upon the contractor. 

    • BID SECURITY
      1. Proposals must be accompanied by a photocopy or electronic version, e.g. PDF, FAX, etc. of certified check, cashier's check, or a bid bond (collectively referred to hereafter as “Bid Security”) issued by a surety authorized to issue such bonds in the State of Idaho, in the amount of ten percent (10%) of the total amount of the proposal submitted. If a photocopy or electronic version of a certified check, or cashier's check is provided with the proposal, an original certified check or cashier's check shall be submitted to ACHD within 48 hours of the bid opening. Failure to include or timely provide a Bid Security as required herein shall be an informality and irregularity which may be waived by ACHD as provided in Item 24 and if not waived, will render said proposal void and non-responsive.
      2. Any Contractor submitting a certified check or cashier's check for bid guarantee will be required to submit within 48 hours of the bid opening, a letter from their bonding company stating that it will guarantee bonding for the Contractor, in the event said Contractor is notified via a “Notice of Intent to Award Letter,” that it is the apparent low Bidder and may be awarded the contract; or provide a letter identifying the type, par value and maturity date (maturity date must coincide with the completion date of this project) of the government obligation to be provided in lieu of performance and payment surety bonds. Said letter is to be included with the bid documents, and shall name the Contractor, project number, and the amount of bonding value being guaranteed.
      3. The Bid Security shall be given as a guarantee that the Bidder will not withdraw their proposal for a period of 60-days after bid opening, unless stated in the ITB, and that, if awarded the contract, the successful Bidder will execute the attached contract and furnish the performance bond, payment bond, and insurance herein specified.
      4. The attorney-in-fact (resident agent) who executes this bond on behalf of the surety must attach a notarized copy of the Bidder power-of-attorney as evidence of authority to bind the surety on the date of execution of the bond.
      5. Surety companies providing bonds shall be listed on the current Federal Treasury List published annually in the FEDERAL REGISTER and authorized to do business in the State of Idaho.
      6. The Bid Bond form included in the contract documents is for the optional use of the contractor and bonding company.
    • 13. PROTECTION OF EXISTING STRUCTURES, UTILITIES AND WORK

      Where work performed by the Contractor could cause damage or inconvenience to railway, telegraph, telephone, television, power, oil, gas, water, sewer, irrigation systems or services or utilities of a similar nature, work shall be suspended until all arrangements necessary for the protection of these utilities and services have been made by the contractor at no additional cost to the Owner.  (Contact Dig Line for line locations.)

      Contractor shall notify all utility and other similar companies that may be affected by the construction operations at least two (2) working days in advance of such operation. Under no circumstances shall Contractor expose any utility without first obtaining permission from the appropriate agency. Once permission has been granted, Contractor shall locate, expose, and provide temporary support for all existing underground utilities.

      Power poles and telephone poles within the right-of-way shall be protected at no cost to the Owner. If interfering power poles, telephone poles, guy wires, or anchors are encountered, Contractor shall notify the Resident Engineer and the appropriate utility company at least two (2) working days in advance of construction operations to permit the necessary arrangements for protection or relocation of the interfering structure. 

      The Contractor shall be solely and directly responsible to the operators of such properties for any damage, injury, expense, loss, inconvenience, delay, suits, actions, or claims of any character brought because of any injuries or damage that may result from the construction operations under this contract, and shall indemnify the Owner from any loss therefrom. 

      If the Contractor, while performing construction operations, discovers utility facilities not identified by the Owner in the contract drawings or specifications, he shall immediately notify the Resident Engineer and the utility in writing. 

      During installation of ACHD storm water facilities, the Contractor will ensure that the State-required separations from known water supply pipelines are achieved. At known crossings, the Contractor will over excavate an additional 18 inches to check that separation will be achieved. Under no circumstances shall the Contractor alter any utility infrastructure (excluding adjustments to grade for paving), turn any water main valves, or affect sanitary sewer flows without written approval from the utility. Only a certified water operator working for the utility may turn water valves.

    • RETURN OF BID SECURITY

      Within 15-calendar days after award of the contract, the ACHD will return Bid Securities, other than bid bonds, to all Bidders whose proposals are not to be further considered in awarding the contract. The Bid Security, other than bid bond, of the Successful Bidder shall be retained until the contract has been fully executed and the Successful Bidder has furnished all required contract security and met all other conditions of the Notice of Award. Any guarantees which have been forfeited shall be retained.

    • 14. COORDINATION

      Contractor shall cooperate in the coordination of the separate activities in a manner that will provide the least interference with the Owner’s operation, other contractors, and utility companies working in the area, and in the interfacing and connection of the separate elements of the overall project Work.

      If any difficulty or dispute should arise in the accomplishment of the above, the problem shall be brought immediately to the attention of the Resident Engineer for resolution. 

      All contractors working on the site are subject to this requirement for cooperation, and all shall abide by the Resident Engineer’s decision in resolving project coordination problems without additional cost to the Owner. Wherever work being done by the Owner’s employees, or any other contractor is contiguous to Work covered by these Contract Documents, the respective rights of the various interests involved shall be established by the Resident Engineer to secure the completion of the various portions of the work in general harmony.

    • AWARD OF CONTRACT
      1. Within 60-calendar days after the opening of proposals, unless otherwise stated in the Invitation to Bid, the ACHD will accept one of the proposals or will act in accordance with "Basis of Award," below.
      2. ACHD intended acceptance of the proposal will be by written "Notice of Intent to Award Letter," mailed or delivered to the address designated in the proposal.
      3. In the event of failure of the lowest cost responsive Bidder to sign and return the contract, together with the acceptable performance bond, payment bond, and insurance prescribed herein, within the time specified, ACHD may award the contract to the next lowest responsive Bidder.
    • 15. SAFETY

      The Contractor shall be solely and completely responsible for safety conditions at the job site, including safety of all persons (including employees) and property during performance of the Work.  This requirement shall apply continuously and not be limited to normal working hours.

      Safety provisions shall conform to U.S. Department of Labor (OSHA), the State Occupational Safety and Health Act, and all other applicable federal, state, county and local laws, ordinance, codes, those requirements set forth below and any regulations that may be detailed in other parts of these Contract Documents. When any of these requirements are in conflict, the more stringent requirement shall be followed. The Contractor’s failure to thoroughly familiarize himself with all safety requirements shall not relieve him from compliance with the obligations and penalties set forth herein.

      The Contractor shall develop and maintain for the duration of the Work, a safety program that will effectively incorporate and implement all required safety provisions. The Contractor shall appoint an employee who is qualified and authorized to supervise and enforce compliance with the safety program. 

      The duty of the Resident Engineer to conduct construction reviews of the Contractor’s work is not intended to include a review or approval of the adequacy of the Contractor’s safety supervisor, the safety program, or any safety measures taken in, on, or near the construction site. 

      The Contractor, as part of his safety program, shall maintain at the job site, safety equipment applicable to the work prescribed by the aforementioned authorities, all articles necessary for giving first-aid to the injured, and shall establish the procedure for the immediate removal to a hospital or a doctor’s care of persons (including employees) who may be injured on the job site. 

      Contractor shall designate a qualified and experienced safety representative at the Work site whose duties and responsibilities shall be the prevention of accidents and the maintaining and supervising of safety precautions and programs.

      If death or serious injuries or damages are caused, the accident shall be reported immediately by telephone or messenger to the Owner.  In addition, the Contractor must promptly report in writing to the Owner all accidents whatsoever arising out of or in connection with the performance of the Work (whether on or adjacent to the site) giving full details and statements of witnesses. 

      If a claim is made by anyone against the Contractor, or any Subcontractor on account of any accident, the Contractor shall promptly report the facts in writing to the Owner, giving full details of the claim.

    • 16. ROYALTIES AND PATENTS

      Contractor shall pay all license fees and royalties and assume all costs incident to the use in the performance of the Work or the incorporation in the Work of any invention, design, process, product, or device which is the subject of patent rights or copyrights held by others. If a particular invention, design, process, product, or devise is specified in the Contract Documents for use in the performance of the Work and if, to the actual knowledge of Owner, its use is subject to patent rights or copyrights calling for the payment of any license fee or royalty to others, the existence of such rights shall be disclosed by Owner in the Contract Documents. To the fullest extent permitted by laws and regulations, Contractor shall indemnify and hold harmless Owner, Resident Engineer, Owner’s Consultants, and the officers, directors, partners, employees or agents, and other consultants of each and any of them from and against all claims, costs, losses and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to any infringement or patent rights or copyrights incident to the use in the performance of the Work or resulting from the incorporation in the Work of any invention, design, process, product, or device not specified in the Contract Documents. 

    • BASIS OF AWARD
      1. The award will be made by ACHD on the basis of the proposal from the lowest cost and responsive Bidder which, in ACHD sole and absolute judgment, will best serve the interests of the ACHD.
      2. ACHD reserves the right to accept or reject any or all proposals, and to waive any informalities and irregularities in said proposals and provided in Item 3.24.
      3. The ACHD reserves the right to reject all bids, including the apparent low bid, when these bids are in excess of ten percent (10%) over the Engineer’s Estimate.
    • 17. TAXES

      Contractor shall pay all applicable sales, consumer, use and other similar taxes required to be paid by Contractor in accordance with the law and regulations of the State of Idaho and federal government during the performance of the Work. 

      In the event of the Contractor’s default on the payment of taxes, excises, and license fees as set forth in Idaho Code 63-1503 (as amended), the Owner shall have the authority to withhold from any payment due Contractor under these Contract Documents, the estimated amount of such accrued and accruing taxes, excises, and license fees for the benefit of all taxing authorities to which Contractor is liable.  In compliance with Idaho Code 63-1504 (as amended), the Contractor shall submit a completed Final Billing Certification affidavit with its final construction payment request certifying that it has paid all taxes, excises, and license fees due to the state and its taxing units, due and payable during the term of the contract for such construction, and that it has secured all such taxes, excises, and license fees liability for the payment of which has accrued during the term of such contract, notwithstanding they may not yet be due or payable.  The Owner shall submit to the Idaho Tax Commission a Request for Tax Release form and ACHD’s receipt of a Public Works Contract Tax Release issued by the Idaho Tax Commission, and the Contractor’s Final Billing Certification affidavit shall each be conditions precedent to final payment.

    • EXECUTION OF CONTRACT
      1. The apparent low-cost Bidder shall, by the date and time specified by ACHD in the “Notice of Intent to Award Letter," execute the contract and file the executed contract, Contract Certification, acceptable bond, and insurance declarations as required in these documents.
      2. Upon receipt of the executed contract, Contract Certification, acceptable bonds, and insurance declarations, ACHD will execute the contract.
      3. Signature by both parties constitutes execution of the contract.
      4. Upon execution of the contract, Owner will post the Bid Abstract on the eProcurement Portal.
    • 18. COMPLIANCE WITH LAWS, RULES, ORDINANCES AND REGULATIONS

      The Contractor agrees to comply with all federal, states, county and city laws, rules, ordinances or regulations as well as all currently adopted specifications of Ada County Highway District for highway construction in effect at the time the contract is awarded, except where otherwise noted in the Contract Documents.  

      Constructor shall comply with the provisions of Chapter 10, Title 44, Idaho Code, relating to the employment of residents of the State of Idaho.

      “Contractor shall comply with the provisions of Idaho Code Title 44, Chapter 10, relating to the employment of residents of the State of Idaho. This citation requires in all state, county, municipal, and school construction, repair, and maintenance work under any of the laws of this state the contractor or person in charge thereof must employ ninety-five percent (95%) bona fide Idaho residents as employees on any such contracts except where under such contracts fifty (50) or less persons are employed the contractor may employ ten percent (10%) non-residents, provided however, in all cases such employers must give preference to the employment of bona fide Idaho residents in the performance of such work; provided, that in work involving the expenditure of federal aid funds this act shall not be enforced in such a manner as to conflict with or be contrary to the federal statutes prescribing a labor preference to honorably discharged soldiers, sailors, and marines, prohibiting as unlawful any other preference or discrimination among the citizens of the United States.”

      Contractor shall waive all notices and comply with all laws, rules, ordinances and regulations applicable to the performance of the Work unless expressly exempt by applicable laws, rules ordinances and regulations. Owner shall not be responsible for monitoring Contractor’s compliance. 

      If Contractor performs any work knowing or having reason to know that it is contrary to any laws, rules, ordinances or regulations, Contractor shall bear all claims, costs, losses, and damages (including, but not limited to all fees, fines, and charges of engineers, attorneys or other professionals as well as all costs of any action, administrative, judicial or other) relating to the violation of such laws, rules, ordinances or regulations.

      DISCRIMINATION PROHIBITED.  Notwithstanding the foregoing; in performing this agreement, contractor shall not discriminate against any person on the basis of race, color, religion, sex, sexual orientation, gender identity, genetic information, national origin, age or non-job related handicap, or because of prior military service or current military status, and shall comply with all applicable federal and state laws and regulations and executive orders of governmental agencies relating to civil and human rights. 

      CERTIFICATION OF ANTI-BOYCOTT AGAINST ISRAEL.  Contractor certifies in compliance with Idaho Code § 67-2346, the “Anti-Boycott Against Israel Act” (the “Act”), that it is a “company” not currently engaged in, and will not for the duration of this Contract, engage in a “boycott” of goods or services from the “state of Israel” or “territories under its control” as those terms are defined in the Act.  

      GOVERNMENT OF CHINA PROHIBITION CERTIFICATION.  CONSULTANT/VENDOR/ CONTRACTOR certifies in compliance with Idaho Code § 67-2359, prohibiting public entities in Idaho from entering into contracts with companies owned or operated by the “government of China”, that it is a “company” not currently owned or operated by the “government of China” and that it will not for the duration of this Contract, be owned or operated by the “government of China” as those terms are defined in Idaho Code § 67-2359.  

      SPECIFIED INDIVIDUAL OR COMPANY BOYCOTT PROHIBITION CERTIFICATION.  certifies in compliance with Idaho Code § 67-2347A, that it is a “company” not currently engaged in and will not for the duration of this Contract engage in, a “boycott”, as those terms are defined in Idaho Code § 67-2347A, of those certain individuals or companies described in Idaho Code § 67-2347A.

    • PERFORMANCE AND LABOR AND MATERIAL BONDS
      1. The apparent low cost responsive Bidder shall provide to ACHD a Performance Bond and a Labor and Material Bond on forms acceptable to ACHD in the amount stated in the General Conditions as security for the faithful performance of the contract and the payment of all persons supplying labor and materials for the construction of the work; and to cover all guarantees against defective workmanship or materials (or both) for a period of two (2) years after the date of Construction Completion of the work by ACHD.
      2. The Surety furnishing these bonds shall have a sound financial standing and a record of service satisfactory to the Owner and shall be authorized to do business in the State of Idaho. Surety companies providing bonds shall be listed on the current Federal Treasury List published annually in the FEDERAL REGISTER.
      3. The attorney-in-fact (resident agent) who executes the performance and payment bonds in behalf of the surety must attach a notarized copy of the Contractor’s power-of-attorney as evidence of this authority to bind the surety on the date of execution of the bonds. The successful Bidder may provide government obligations, meeting the requirements of Idaho Code 54-1926A, in lieu of performance and labor and material bonds specified herein.
    • 19. SHOP DRAWINGS

      All required shop drawings, machinery details, layout drawings, etc., shall be submitted in four copies to the Resident Engineer for review and approval. Submission shall be sufficiently in advance of construction requirements to afford ample time for checking, including time for correcting, resubmitting, and rechecking, if necessary.  Each item submitted for review and approval shall be identified by its appropriate bid item number.

      The Contractor shall review and approve all drawings prior to submittal to the Resident Engineer. The approval shall bear a stamp or specific written indication that Contractor has satisfied Contractor’s obligations under the Contract Documents.  Any drawings submitted without the Contractor’s approval will not be considered and will be returned to him for proper re-submission.  Before submitting each drawing, the Contractor shall have determined and verified:

      all field measurements, quantities, dimensions, specified performance criteria, installation requirements, materials, catalog numbers, and similar information with respect thereto;

      all materials with respect to intended use, fabrication, shipping, handling, storage, assembly, and installation pertaining to the performance of the Work;

      all information relative to means, methods, techniques, sequences, and procedures of construction and safety precautions and programs incident thereto; and

      Contractor shall have reviewed and coordinated each shop drawing with other shop drawings and with the requirements of the Work and the Contract Documents.

      If any drawings show variations from the requirements of the Contract Documents because of standard shop practice or other reason, the Contractor shall make specific mention of such variations in his letter of transmittal in order that, if acceptable, suitable action may be taken for proper adjustment of Contract Price and/or Contract Time; otherwise, the Contractor will not be relieved of the responsibility for executing the Work in accordance with the Contract Documents even though drawings with variations may have been approved.

      Such review and comment by the Resident Engineer is only for general conformance with the information given in the Contract Documents and does not relieve the contractor of responsibility of correctness of the details and dimensions, nor does it waive any requirements of the specifications.

    • REQUIRED INSURANCE

      The apparent low-cost responsive Bidder shall provide to ACHD evidence of the following insurances in the amounts stated:

      Type Limits

      Workman’s Compensation Statutory

      Employer’s Liability $1,000,000

      Commercial General Liability $2,000,000

      Automobile $2,000,000

    • 20. GENERAL GUARANTY

      In addition to any other warranties contained in the Contract Documents, the Contractor warrants, except as provided in paragraph (i) of this section, that Work conforms to the Contract Documents and is free of any defect in equipment, material, or design furnished, or workmanship performed by the Contractor or any Subcontractor or supplier at any tier.

      This warranty shall continue for a period of two (2) years from the date of Construction Completion of the Work.  If the Owner takes possession of any part of the Work before Construction Completion, this warranty shall continue for a period of two (2) years from the date the Owner takes possession.

      The Contractor shall remedy at the Contractor’s expense any failure to conform, or any defect.  In addition, the Contractor shall remedy at the Contractor’s expense any damages to Owner-owned or controlled real or personal property, when that damage is the result of:  

       Contractor’s failure to conform to contract requirements; or

       Any defect of equipment, material, workmanship, or design furnished.

      The Contractor shall restore any work damaged in fulfilling the terms and conditions of this section.  The Contractor’s warranty with respect to work repaired or replaced will be two (2) years from the date of repair or replacement.

      The Resident Engineer shall notify the Contractor, in writing, within a reasonable time after the discovery of any failure, defect or damage. 

      If the Contractor fails to remedy any failure, defect or damage within a reasonable time after receipt of notice, the Owner shall have the right to replace, repair, or otherwise remedy the failure, defect, or damage at the Contractor’s expense.

      With respect to all warranties, expressed or implied, from Subcontractors, manufacturers, or suppliers for work performed and materials furnished under the Contract Documents, the Contractor shall:

      Obtain all warranties that would be given in normal commercial practice;

      Require all warranties to be executed in writing, for the benefit of the Owner, if directed by the Resident Engineer; and

      Enforce all warranties for the benefit of the Owner, if directed by the Resident Engineer.

      In the event the Contractor’s warranty under paragraph (b) of this clause has expired, the Owner may bring suit at its expense to enforce a Subcontractor’s, manufacturer’s or supplier’s warranty.

      This warranty provision shall not limit the Owner’s rights with respect to latent defects, gross mistakes or fraud.

    • FAILURE TO EXECUTE CONTRACT, FURNISH BONDS AND INSURANCES

      The apparent low cost responsive Bidder who has received the “Notice of Intent to Award Letter,” and who fails to execute the contract and furnish the executed contract, Contract Certification, required performance bond, payment bond and insurance declarations, by the date and time specified by ACHD in the “Notice of Intent to Award Letter,” may forfeit the Bid Security that accompanied the bid submitted; the Bid Security may be retained, as liquidated damages, by ACHD and it is agreed that this sum is a fair estimate of the amount of damages ACHD will sustain in case the Bidder fails to enter into a contract and furnish the performance bond, payment bond, and insurance certificates as hereinbefore provided. Bid Security deposited in the form of a certified check, or cashier's check shall be subject to the same requirements as a bid bond.

    • 21. WARRANTY OF TITLE

      No material, supplies, or equipment to be installed or furnished under the Contract Documents shall be purchased, subject to any chattel mortgage or under a conditional sale, lease purchase, or other agreement by which an interest therein or in any part thereof is retained by the seller or supplier. 

      The Contractor shall warrant good title to all materials, supplies, or equipment installed or incorporated in the Work and upon completion of all construction work, shall deliver the same together with all improvements and appurtenances constructed or placed thereon by him to Owner free from claims, liens, or charges. Neither the Contractor nor any person, firm, or corporation furnishing any material or labor for any work covered by this contract shall have any right to a lien upon any improvement or appurtenance thereon. Nothing contained in this paragraph, however, shall defeat or impair the right of persons furnishing materials or labor to recover under any bond given by the Contractor for their protection or any rights under any law permitting such persons to look to funds due the Contractor in the possession of Owner. The provisions of this requirement shall be given to all persons furnishing materials for the work when no formal contract is entered into for such materials. 

      Title to property shall be passed to the Owner upon payment unless otherwise agreed to by the Owner and Contractor.  

    • DISQUALIFICATION OF BIDDERS

      More than one proposal submitted pursuant to an ITB from an individual, firm, partnership or corporation under the same or different names will not be considered. Evidence of collusion between Bidders will be sufficient cause for rejection of bids so submitted.

    • 22. CERTIFICATE OF COMPLIANCE WITH STANDARDS AND CODES

      A certificate of compliance shall be furnished for materials specified to a recognized standard or code prior to use of any such materials in the Work.  The Resident Engineer may permit the use of certain materials or assemblies prior to sampling and testing, if accompanied by a certificate of compliance. 

      The certificate shall be signed by the manufacturer of the material or the manufacturer of assembled materials and shall state that the materials involved comply in all respects with the requirements of the specifications. A certificate of compliance shall be furnished with each lot of material delivered and the lot so certified shall be clearly identified in the certificate. 

      All materials used on the basis of a certificate of compliance may be sampled and tested at any time. The fact that material is used on the basis of certificate of compliance shall not relieve the Contractor of responsibility for incorporating material in the work which conforms to the requirements of the Contract Documents and any such material not conforming to such requirements will be subject to rejection whether in place or not. 

      The Resident Engineer reserves the right to refuse permission for use of material on the basis of a certificate of compliance. 

      The form of the certificate of compliance and its disposition shall be as directed by the Resident Engineer.

    • TIME OF COMPLETION OF THE WORK

      The time of completion of the Work to be performed under this contract is of the essence. Delays and extensions of time may be allowed in accordance with the provisions stated in the General Conditions. The time allowed for the completion of the Work or for Substantial Completion is stated in the Contract Agreement.

    • 23. INDEMNITY AND HOLD HARMLESS

      To the fullest extent permitted by laws and regulations, Contractor shall indemnify and hold harmless Owner, its commission, employees and consultants, from and against all claims, costs, losses, and damages (including, but not limited to all fees and charges of engineers, architects, attorneys and other professional and all court or arbitration or other dispute resolution costs) arising out of or relating to the performance of the Work, provided that any such claim, cost, loss or damage:

      is attributable to bodily injury, sickness, disease or death or to injury to or destruction of tangible property (other than the Work itself) including the loss of use resulting therefrom; and 

      is caused in whole or in part by any negligent act or omission of Contractor, any Subcontractor, any supplier, or any individual or entity directly or indirectly employed by any of them to perform any of the Work or anyone for whose acts any of them may be liable, regardless of whether or not caused in part by any negligence or omission of any individual or entity hereunder or whether liability is imposed upon such indemnified party by laws and regulations regardless of the negligence of any such individual or entity.

      In any and all claims against Owner, its commission, employees and consultants,  by any employee (or the survivor or personal representative of such employee) of Contractor, any Subcontractor, any supplier, or any individual or entity directly or indirectly employed by any of them to perform any of the Work, or anyone for whose acts any of them may be liable, the indemnification obligation under paragraph (a) shall not be limited in any way by any limitation on the amount or type of damages, compensation, or benefits payable by or for the Contractor or any such Subcontractor, supplier, or other individual or entity under worker’s compensation acts, disability benefits acts, or other employee benefit acts.

      This indemnification and hold harmless obligation of Contractor shall survive the expiration or termination of this Contract for as long as any applicable statute of limitations provided in Idaho laws. For purposes of this indemnification and hold harmless obligation, the applicable statute of limitations shall not begin to accrue until the Contractor’s warranty period of for the Work has expired.

    • NON-RESPONSIVE CRITERIA

      All bid proposals submitted that fail to meet the following criteria shall be deemed void and non-responsive:

      1. Provide proof of licensure.
      2. Provide name and valid contractor license number for plumbing; electrical; and/ or heating, ventilation, and air conditioning (HVAC) subcontractors.
      3. Submit their bid or proposal in the manner required by the date and time stated in the Invitation to Bid, Request for Proposal, Request for Qualifications, or other solicitation.
    • 24. TESTS AND INSPECTIONS

      Contractor shall give Resident Engineer timely notice, but no less than one working day of readiness of the work for all required inspections, tests or approvals and shall cooperate with inspection and testing personnel to facilitate required inspection or tests.

      If laws or regulations of any public body having jurisdiction require any work (or part thereof) specifically to be inspected, tested or approved by an employee or other representative of such public body, Contractor shall assume full responsibility for arranging and obtaining such inspections, tests or approvals, pay all costs in connection therewith, and furnish Resident Engineer the required certificates of inspection or approval. 

      If any work (or the work of another) that is to be inspected, tested, or approved is covered by Contractor without written concurrence of Resident Engineer, it must, if requested by Resident Engineer, be uncovered for observation.  If such work is found to be in accordance with the Contract Documents, the Owner shall pay the cost of re-inspection and replacement.  If such work is not in accordance with the Contract Documents, the Contractor shall pay all costs.

    • INFORMALITIES AND IRREGULARITIES

      Informalities and irregularities may be waived by the ACHD Director following notification by ACHD Procurement and Contracting and upon the Director’s findings that: (1) the subject bid amount is lower than the ACHD estimate; (2) the informality and irregularity has no substantive impact on any substantial or material requirements of the project; (3) waiver of the informality and irregularity will not create an advantage for the subject Bidder; and (4) the informality and irregularity can be corrected by the subject Bidder within 48 hours of the waiver being granted by the ACHD Director. In all other circumstances, waiver of informalities and irregularities can only be considered by the ACHD Commission as part of the bid award process and at the request of the affected Bidder. If not waived, these informalities and irregularities shall result in a bid proposal being deemed void and non-responsive.

      Based upon the foregoing, the informalities and irregularities that may be waived include, but are not limited to, the following:

      1. Failure to timely provide the required original Bid Security.
      2. Failure to provide all other required Bid Security documentation.
      3. Failure by the Bidder to sign their bid or proposal.
      4. Failure by the Bidder to obtain from ACHD and submit official Ada County Highway District Contract Documents, Plans, and/or Addenda.
      5. Minor mathematical errors.
      6. Omissions, erasures, or alterations not initialed by an authorized representative of the Bidder.
      7. Additions of any kind or prices which are uncalled for in the Request for Proposal.
    • 25. AUTHORIZED CHANGES IN THE WORK

      Without invalidating the Contract Documents, and without notice to any surety, the Resident Engineer may, at any time or from time to time, order additions, deletions, or revisions in the Work by a Written Amendment, a Change Order, or a Work Change Directive.  Upon receipt of any such document, Contractor shall promptly proceed with the work to be performed under the applicable conditions of the Contract Documents (except as otherwise specifically provided).

      If Resident Engineer and Contractor are unable to agree on entitlement to, or on the amount or extent, if any, of an adjustment in the Contract Price or Contract Time, or both that should be allowed as a result of a Written Amendment, a Change Order or a Work Change Directive, the Change will be governed by either Extra, Altered and Force Account Work provision or payment based upon Bid Schedule unit prices.

      Contractor shall not be entitled to an increase in Contract Price or an extension of the Contract Time with respect to any work performed that is not required by the Contract Documents as amended, modified or supplemented except in the case of any emergency affecting the safety or protection of persons or the Work or property at the site or adjacent thereto and the Contractor gives the Resident Engineer prompt written notice.

      Resident Engineer and Contractor shall execute appropriate Change Orders covering:

      changes in the Work which are:  (i) ordered by the Resident Engineer; (ii)  required because of acceptance of defective work or Resident Engineer’s correction of defective work; or (iii) agreed to by the parties;

      changes in the Contract Price or Contract Time which are agreed to by the parties, including any undisputed sum or amount of time for work actually performed in accordance with a Change Order or Work Change Directive; and

      changes in the Contract Price or Contract Time which embody the substance of any written decision rendered by Resident Engineer pursuant to the Claims and Disputes provision; provided that the Contractor may appeal any written decision by the Resident Engineer in accordance with this provision, but during any such appeal, Contractor shall carry on the Work and adhere to the schedule as provided in section 7(c) of these General Conditions.

      If notice of any change affecting the general scope of the Work or a provision of the Contract Documents  (including, but not limited to, Contract Price or Contract Time) is required by the provision of any bond to be given to a surety, the giving of any such notice shall be Contractor’s responsibility.  The amount of each applicable bond will be adjusted to reflect the effect of any such change

    • 26. DELAY/ EXTENSIONS OF CONTRACT TIME

      Force Majeure: If Contractor is prevented from performing any of its obligations under the Contract Documents by reason of fire, flood, windstorm, earthquake, other Acts of God, civil disturbance, riots, order of any court or administrative body (not due to the fault of Contractor), or any other cause beyond the control of Contractor and without the fault on the part of Contractor, the time allotted by the Contract Documents for performance of the obligations that are so prevented shall be extended one day for each day of delay. Contractor shall make no claim for extension of Contract Time pursuant to this paragraph unless it notifies the Resident Engineer, in writing, of the existence of any delay excused herein within 24 hours after the beginning of such force majeure and of the termination of such period of delay within 24 hours after its termination. 

      Normal Weather Conditions: There shall be no extension of time granted to Contractor for delay due to normal weather conditions. Normal weather conditions shall be considered based upon historical weather patterns as established by recognized weather service bureaus. Normal weather patterns include such seasonal variations (including but not limited to windstorms) as might be reasonably expected by the Contractor to occur from year to year. Only delays resulting from weather conditions substantial (more adverse than seasonal averages that might be anticipated based upon historical data) shall be considered for a time extension.

      Delay Caused by Owner or Others,  No-Damage-for Delay: Should Contractor’s progress be interfered with or the completion of the Work be prevented through failure of Owner to provide required services, or for any reason attributable to Owner, its agents, or others, including but not limited to utilities, then in that event, Contractor will be entitled to an extension of time, day for day, with which to complete the Work. This is a NO-DAMAGE-FOR-DELAY-CONTRACT, and Contractor’s only remedy for delay shall be an extension of time as provided herein. 

      Time and Evidence Required for Claim Submission: Claims for extension of time pursuant to (b) and (c) shall be made in writing to the Resident Engineer no more than ten (10) days after the occurrence of the delay; otherwise they shall be waived. In the case of a continuing cause for delay, only one claim is necessary. 

      Accompanying the claim shall be a narrative setting forth the category that the Contractor is basing the claim (a-c) on as well as the specific damages that the Contractor suffered as a result of the delay.

    • 27. SCHEDULING UPDATES

      The Contractor shall provide an updated schedule in the manner set forth in section 7(c) including narratives explaining any modifications or changes to the Resident Engineer simultaneously with the Contractor’s “Request for Progress Payment”. Failure to provide updated schedule will delay payment as provided for in section 34. 

    • 28. SELECTION OF EQUIPMENT BY OWNER

      If the Owner or his agent reserves the sole right to select equipment to be installed, the Contractor shall be responsible only for its installation according to the plans, specifications and manufacturer’s requirements, and shall not be held liable for its operating performance. 

    • 29. VARIATIONS IN QUANTITIES

      The estimate of quantities listed in the Bid Proposal are approximate only and the Owner shall have the right to increase or decrease the quantities of contract items.

      Where the quantity of a pay item in this contract is an estimated quantity and where the actual quantity of such pay item varies by more than 15% above or below the estimated quantity stated in the contract, an equitable adjustment in the contract price shall be made upon demand of either party to the contract. The equitable adjustment shall be based upon any increase or decrease in costs due solely to the variations above 115% or below 85% of the estimated quantity. When the total pay quantity of an item of work is less than 85 percent of the contract bid quantity, payment for the work will in no case exceed the payment that would have been made for performance of 85% of the bid item quantity at the contract unit price. Detailed pricing information shall be provided for all negotiated pricing adjustments. 

      If the quantity variation is such as to cause an increase in the time necessary for completion, the Contractor may request, in writing, an extension of Contract Time, to be received by the Resident Engineer within ten (10) days from the beginning of the delay, or within such further period by the Resident Engineer before the date of final settlement. Upon the receipt of a written request for an extension, the Resident Engineer shall ascertain the facts and make an adjustment for extending the completion date if warranted, in the judgment of the Resident Engineer. 

    • 30. CORRECTIONS, REMOVAL OR ACCEPTANCE OF DEFECTIVE WORK

      Prompt notice of all defective work of which Resident Engineer has actual knowledge will be given to Contractor.  All defective work may be rejected, corrected, or accepted as provided in this provision.

      If the work is defective, or Contractor fails to supply sufficient skilled workers or suitable materials or equipment, or fails to perform the work in such a way that the completed Work will conform to the Contract Documents, Resident Engineer may order Contractor to stop the work, or any portion thereof, until the cause for such order has been eliminated; however this right of Resident Engineer to stop the work shall not give rise to any duty on the part of the Resident Engineer to exercise this right for the benefit of the Contractor, any Subcontractor, any supplier, any other individual or entity, or any surety for, or employee or agent of any of them.

      A Contractor shall correct all defective work, whether or not fabricated, installed, or completed, or if the work has been rejected by the Resident Engineer, remove it and replace it with work that is not defective and is consistent with Contract Documents.  Contractor shall pay all claims, all fees and charges of engineers, attorneys, architects, and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to such correction or removal including, but not limited to all costs of repair or replacement of work of others.

      Correction Period.

      If within two (2) years after the date of Construction Completion or such longer period of time as may be prescribed by laws or regulations or by the terms of any applicable special guarantee required by the Contract Documents or by any specific provision of the Contract Documents, any work is found to be defective, whether latent or patent, or if the repair of any damages to the land or areas made available for Contractor’s use by Owner or permitted by laws or regulations is found to be defective, Contractor shall promptly, without cost to Owner and in accordance with Resident Engineer’s written instructions:  (i) repair such defective land or areas or (ii) correct such defective work or, if the defective work has been rejected by Resident Engineer, remove from the project and replace it with work that is not defective and conforms with the Contract Documents, and (iii) satisfactorily correct or repair or remove and replace any damage to the work of others or other land or areas resulting therefrom.  If Contractor does not promptly comply with the terms of such instructions or in an emergency where delay would cause serious risk of loss or damage, Resident Engineer may have the defective work removed and replaced.  All claims, all fees and charges of engineers, attorneys, architects, and other professionals and all court or arbitration or other dispute resolution costs arising out of or relating to such correction or removal including, but not limited to, all costs of repaid or replacement of work of others will be paid by Contractor.

      In special circumstances where a particular completed portion of Work is placed in use as provided by section 40(e), the correction period for that completed portion may start at an earlier date if so provided in the Specifications or by Written Amendment.

      Where defective work (and damage to other work resulting therefrom) has been corrected or removed and replaced under this section, the correction period with respect to such work will be extended for an additional period of two (2) years after such correction or removal and replacement has been satisfactorily completed.

      Contractor’s obligations under this section are in additional to any other obligation or warranty.  This section shall not be construed as a substitute for or a waiver of the provisions any applicable statute of limitation or repose. 

      Acceptance of Defective Work.   If, instead of requiring correction or removal and replacement of defective work, Resident Engineer prefers to accept, the Resident Engineer may do so.  Contractor shall pay all claims, all fees and charges of engineers, attorneys, architects, and other professionals and all court or arbitration or other dispute resolution costs attributable to Resident Engineer’s evaluation of and determination to accept such defective work and the diminished value of the work.  If any such acceptance occurs prior to the Resident Engineer’s recommendation of final payment, a Change Order will be issued incorporating the necessary revisions in the Contract Documents with respect to the Work and Owner shall be entitled to an appropriate decrease in Contract Price reflecting the diminished value of Work accepted.  If such acceptance occurs after final payment, Contractor will pay to the Owner the difference between the value of the non-defective Work and the defective Work. 

      Correction of Defective Work by Owner.

      If Contractor fails within a reasonable time after written notice from Resident Engineer to correct defective work or to remove and replace rejected work as required by Resident Engineer, or if Contractor fails to perform the work in accordance with the Contract Documents, or if Contractor fails to comply with any other provision of the Contract Documents, Resident Engineer may, after seven (7) calendar days notice to Contractor, correct and remedy any such deficiency.

      In exercising the rights and remedies under this subsection, Resident Engineer shall proceed expeditiously.  In connection with such corrective and remedial action, Resident Engineer may exclude Contractor from all or part of the site, take possession of all or part of the work and suspend Contractor’s services related thereto, take possession of Contractor’s tools, appliances, construction equipment and machinery at the site and incorporate in the work all materials and equipment stored at the site or for which Owner has paid Contractor but which are stored elsewhere.  Contractor shall allow Resident Engineer, other contractors and consultants access to the site to enable Owner/Resident Engineer to exercise the rights and remedies under this subsection.

       All claims, costs, losses, and damages (including but not limited to all fees and charges of   engineers, attorneys, architects, and other professionals and all court or arbitration or other dispute resolution costs) incurred or sustained by Owner in exercising the rights and remedies under this section will be charged against the Contractor.  A Change Order will be issued incorporating the necessary revisions in the Contract Documents with respect to the Work; and Owner shall be entitled to an appropriate decrease in the Contract Price.  Such claims, costs, losses and damages will include but not be limited to all costs of repair, or replacement of work of others destroyed or damaged by correction, removal or replacement of Contractor’s defective work.

      Contractor shall not be allowed an extension of the Contract Time (or Milestones) because of any delay in the performance of the Work attributable to the exercise by the Owner/Resident Engineer of the rights and remedies under this subsection.

    • 31. LIQUIDATED DAMAGES

      Contractor guarantees the completion date stated in the Contract Agreement including any extension granted thereto.  Failure to complete the Work shall entitle the Owner to deduct from the monies due to the Contractor as liquidated damages.

      It is agreed that the actual damages and loss which Owner would incur as a result of Contractor’s default in its obligation to complete the Work by such firm completion date would be impracticable and extremely difficult to determine.  It is therefore agreed that in the event of such delay or default, Contractor shall pay Owner the amount stated in the Contract Documents per calendar day as liquidated damages and not as a penalty, for each calendar day, until the actual date of completion of the Work. Contractor agrees that all sums payable by Contractor to Owner as liquidated damages pursuant to this section may be deducted by Owner from the Contract Price to be paid to Contractor for the Work. It is further agreed that this section shall not constitute a waiver of any rights of Owner to damages or other remedies of Owner under the Contract Documents or otherwise for Contractor’s improper performance or default in performance, including delay or failure of Contractor to complete the Work.

    • 32. OWNER’S RIGHT TO TERMINATE CONTRACT/SUSPENSION AND TERMINATION FOR CONVENIENCE
      1. a.    The Contract may be terminated in whole or in part by the Owner in accordance with this section, whenever the Owner shall determine that such termination is in its best interest. Termination shall be effected by delivery to the Contractor of a written notice of termination specifying the extent to which the contract is terminated and the date upon which such termination becomes effective.

        b.    After receipt of a written notice of termination, and except as other directed by the Resident Engineer, the Contractor shall:

        1)    Stop work on the date and to the extent specified in the Notice of Termination;

        2)    Place no further orders or subcontracts for materials, services or facilities, except as may be necessary for completion of such portion of the Work not terminated;

        3)    Terminate all orders and subcontracts to the extent that they relate to the performance of work terminated by the notice of termination;

        4)    Settle all outstanding liabilities and all claims arising out of such termination of orders and subcontracts with the approval of the Resident Engineer;

        5)    Transfer title and deliver to the Owner, in the manner, at the times, and to the extent, if any, directed by the Resident Engineer, the fabricated or unfabricated parts, work in process, completed and accepted work, supplies, and other materials produced as a part of, or acquired in connection with the performance of the Work terminated by the notice of termination; and the completed or partially completed plans, drawings, information, and other property not previously furnished by the Owner and which, if the Work had been completed, would have been required to be furnished to the Owner;

        6)    Complete performance of such part of the work not terminated by the notice of termination; and

        7)    Take such action as may be necessary, or as the Resident Engineer may direct, for the protection and preservation of property which is in the possession of the Contractor and in which the Owner has or may acquire an interest.

        c.    At any time, but no later than submittal of the Contractor’s termination claim (d), the Contractor may submit to the Resident Engineer a list, certified as to quantity and quality, of any or all remaining items in possession of the Contractor, ordered by the Contractor to use in this Work and now no longer useful due to Notice of Termination.  The Contractor may request the Resident Engineer to remove such items or enter into a storage agreement covering them.  No later than fifteen (15) days thereafter, the Resident Engineer will accept title to such items and remove them or enter into a storage agreement with Contractor, provided that the list submitted to the Resident Engineer shall be subject to verification.  Within forty-five (45) days from the date of submission of the certified list, any necessary adjustment to correct the list shall be made prior to final settlement.

        d.    After receipt of a notice of termination, the Contractor shall submit to the Resident Engineer its termination claim certified pursuant to General Condition section 37(6).  Such claim such be submitted promptly, but no later than ninety (90) days from date upon which such termination becomes effective, unless an extension is requested by the Contractor and is granted upon good cause by the Resident Engineer in writing.  If the Contractor fails to submit the termination claim within the time allowed and any extensions granted, the Resident Engineer may determine, on the basis of information available to the Resident Engineer, the amount, if any, due to the Contractor by reason of the termination and shall thereupon pay to the Contractor the amount so determined.

        e.    Subject to the provisions of paragraph (d), the Contractor and the Resident Engineer may agree upon the whole or any part of the amount or amounts to be paid to the Contractor by reason of the total or partial termination of work pursuant to this section. Such amount or amounts may include an allowance for profit on work done equal to that provided in “Extra, Altered or Force Account Work” section, provided, that such agreed amount or amounts, exclusive of settlement costs, shall not exceed:  (1) the total Contract Price as reduced by the amount of payments previously made and (2) the Contract Price of work not terminated.  The Contract shall be by change order pursuant to General Provision  25, accordingly, and Contractor shall be paid the agreed amount.  Nothing in paragraph (f) of this section shall be deemed to limit, restrict or affect the amount or amounts which may be agreed upon to be paid to the Contractor by the Owner in this paragraph (e).

        f.    In the event Contractor and the Resident Engineer fail to agree, as to the total amount to be paid to Contractor by reason of the termination, the Owner shall pay to Contactor the amounts determined as follows, without duplication of any amounts agreed upon paragraph in (e):

        1)    With respect to Contract Work performed prior to the date upon which termination becomes effective, the total (without duplication of any items) of:

        i)    the cost of such completed and accepted work;

        ii)    the cost of settling and paying claims arising out of the termination  under the subcontracts or orders as provided in (b)(4) above, exclusive of the amounts paid or payable on account of supplies or materials delivered or services furnished by the subcontractor prior to the effective date of the notice of termination of work under these Contract Documents, which amounts shall be included in the cost on account of which payment is made under (i) above; and

        iii)    a combined sum for overhead and profit on work performed equal to that provided in  “Extra, Altered or Force Account Work”, General Provision 46; provided, that if it appears that the Contractor would have sustained a loss on the entire contract had it been  completed, no profit shall be included or allowed under this subparagraph and appropriate adjustment shall be made reducing the amount of the settlement to reflect the indicated rate of loss; and

        2)    The reasonable cost of the preservation and protection of property incurred under (b)(7); and any other reasonable cost incidental to the termination, including accounting, legal, clerical and other expenses reasonably necessary to the determination of the amount due the Contractor as the result of the termination. 

        The total sum to be paid to Contractor under (1) above shall not exceed (1) the total Contract Price as reduced by the amount of payments previously made and (2) the Contract Price of work not terminated.  Except for normal spoilage, and except to the extent that the Owner shall have otherwise expressly assumed the risk of loss, there shall be excluded from the amounts payable to the Contractor under (1) above, the fair market value, as determined by the Resident Engineer, of property which is destroyed, lost, stolen, or damaged so as to become undeliverable to the Owner.

        g.    The Contractor shall have the right of appeal, as provided in General Provision 37 from any decision or determination by the Resident Engineer under this section.

        h.    In arriving at the amount due Contractor under this section there shall be deducted:  all unliquidated advances or other payments on account theretofore made to the Contractor, applicable to the terminated portion of these Contract Documents; and any claim which the Owner have against the Contractor in connection with these Contract Documents.

        i.    If the termination is partial, the contractor may file a proposal with the Resident Engineer for equitable adjustment of the price(s) of the continued portion of the Work pursuant to General Condition section 37 within ninety (90) days from the notice of partial termination/suspension unless extended in writing by the Resident Engineer.

        j.    Limitation of Liability.  Notwithstanding anything to the contrary contained herein, Contractor hereby waives any form of consequential or indirect damages.  Such prohibited damages include, but are not limited to, lost profits; home office overhead, or any form of overhead not directly incurred at the project site; wage or salary increases; ripple or delayed damages; loss of productivity; increased cost of funds for the project; extended capital costs; loss opportunity to work on other projects; inflation on costs of labor, material or equipment; non-availability of labor, material or equipment due to delays; increase of cost of bon-ding due to- delays; or any other indirect loss arising from the conduct of the parties. 

    • 33. CONTRACTOR’S RIGHT TO STOP WORK OR TERMINATE CONTRACT

      If work should be stopped by an order of any court or other public authority for a period of 3-months or more, through no fault of the Contractor or of anyone employed by him, or if the Owner should fail to pay the Contractor within 45-calendar days any sum certified by the Resident Engineer, then the Contractor may upon 7-calendar days written notice to the Resident Engineer, stop work or terminate this Contract Agreement and recover from the Owner payment for all work acceptably completed through the date of termination.

    • 34. PAYMENTS WITHHELD PRIOR TO FINAL ACCEPTANCE OF WORK

      The Owner may withhold or, on account of subsequently discovered evidence, nullify the whole or part of any certificate of payment to such extent as may be necessary to protect itself from loss on account of: 
              
      Defective work not remedied.

      Claims filed, or reasonable evidence indicating public filing, of claims by other parties against the Contractor.

      Failure of the Contractor to make payments properly to all Subcontractors, as required in General Condition 11, or for material or labor, or to certify such payments, as required in General Condition 11.  Additional payments will not be made until the required certification forms have been submitted to ACHD, as required in General Condition 11.

      Damage to another contractor or individual not remedied. 

      Work not completed.

      The Contract Price that has been reduced by Written Amendment or Change Order.

      Owner has been required to correct defective work.

      Contractor’s persistent failure to perform the work in accordance with the Contract Documents (including, but no limited to, failure to supply sufficient skilled workers or suitable materials or equipment or failure to adhere to the progress schedule established in the Contract Documents). 

      Contractor’s disregard of laws, rules, ordinances or regulations of any public body having jurisdiction. 

      Contractor’s disregard of the authority of the Resident Engineer through his Project Inspector to include failure to consistently respond to Field Directives (AVOs) in a timely manner.

      Failure to provide scheduling update simultaneous with “Request for Progress Payment”.

      As the above grounds for withholding are removed, payment shall be made for amount withheld.

    • 35. ASSIGNMENT

      The Contractor shall not assign the Contract Agreement in whole or in part, without the express written consent of the Owner; nor shall the Contractor assign any monies due, or to become due to him hereunder, without the previous written consent of the Owner. Assigning the Agreement shall not relieve the Contractor or his surety from any contract obligation. 

    • 36. SEPARATE CONTRACTS

      The Owner reserves the right to let other contracts or otherwise have work performed in connection with this Work. The Contractor shall afford other contractors reasonable opportunity for the execution of their work, and shall properly schedule and coordinate his work so as to minimize conflicts.  Contractor shall cooperate and coordinate its work with other contractors employed by Owner in order to insure that the work of each shall be commenced and completed without delay

    • 37. CLAIMS REVIEW PROCESS
      1. Request for Review of Claim.  Contractor may file a written request to the Managing Engineer to review any claim for additional compensation, for a time extension or for other relief not approved by the Resident Engineer.

       

      1. If the impact of the claim is continuing, the Contractor shall supplement the General Information and Specific Documentation required below, in a timely manner.
      2. During the performance of any disputed work, the Contractor shall keep complete records of extra costs and time incurred.
      3. The Contractor shall provide to the Managing Engineer the General Information and Specific Documentation required below, to support the claim no later than 30 calendar days following the date the claim has fully matured or the date the project is completed, whichever occurs first.
      4. All records pertaining to the claim shall be retained by the Contractor, subcontractors, and all low tier sub-contractors until the claim is fully resolved.

       

      1. General Information Required.  Claimant shall promptly submit a written statement setting forth the following:

       

        1. The nature and circumstances which caused the claim;
        2. The date or dates of events giving rise to the claim;
        3. The contract provisions upon which the claim is based;
        4. A complete explanation of why ACHD is responsible for the Contractor’s additional claimed costs;
        5. The amount of additional compensation claimed;
        6. The time extension claimed; and
        7. A description of any other relief requested and the factual basis for such relief.

       

      1. Specific Documentation Required.  Full documentation of the claim shall contain the following elements.

       

        1. A detailed chronological description of events and circumstances which caused the claim, identifying the dates, locations, and items of work affected by the claim.
        2. Reference to the specific provisions of the contract or laws which support the claim and a statement of the reasons why such provisions support the claim.
        3. Copies of any of the Contractor’s documents and the substance of any oral communication that would support the claim. Manuals that are standard to the industry, which are used by the Contractor, may be included by reference.
        4. If an adjustment of time for the performance of the contract is sought:
      1. The specific days and dates for which it is sought;
      2. The specific reasons the Contractor believes a time adjustment should be granted and is compensable, if overhead costs are being claimed;
      3. The specific provisions of the Contract Documents under which a time adjustment should be granted;
      4. If required by the contract, the Contractor’s detailed analysis of the critical path on the as – built or actual schedule to demonstrate the justification for a time adjustment;
      5. The Contractor’s Daily Record of work performed, Request for Information Log, Submittal Log, Change Order Log; and
      6. If required by the contract, an approved baseline schedule and monthly updates in electronic format and all “look ahead” schedules.
        1. If additional monetary compensation is sought, the exact amount sought and a breakdown of that amount into the following the categories:
          1. Labor. Listing of individuals, classification, hours worked etc.
          2. Materials. Invoices, purchase orders, etc.
          3. Equipment. Listing detailed description (make and model), hours of use and dates of use. Equipment rates shall be at the applicable Blue Book Rate, which was in effect when the work was performed, as set forth in General Condition 44.
          4. Detailed Job Site Overhead costs.
          5. Home Office Overhead (General and Administrative)
          6. Other categories as specified by the Contract Documents or ACHD. 
        2. The General Information and Specific Documentation submitted shall be accompanied by a notarized statement from the Contractor containing the following certification:

       

      Under penalty of law for perjury or falsification, the undersigned,

      _______________________________________________________   

                                                            (Name)

      _______________________________________________________

                                                            (Title)

      _______________________________________________________

                                                            (Company)

       

      hereby certifies that the claim is made in good faith; that the supporting data is   accurate and complete to the best of my knowledge and belief; that the amount requested accurately reflects the actual cost and/or time adjustment for which the Contractor believes the Ada County Highway District is liable; and that I am duly authorized to certify the claim on behalf of the Contractor.

       

      (Signature)_______________________________________

      (Date)______________________

      Subscribed and sworn before me this       day of _____, 2024.

                                                                      

       

       

      (Notary Seal)

       

       

       

      (Notary Signature)_____________________________

      Reside at: _____________________________________

      My commission expires:                                            ___

       

        1. The Contractor shall permit the Managing Engineer access to these and any other records needed for evaluating the claim.

       

      1. Audits. All records of the Contractor, subcontractors and all lower tier subcontractors pertaining to any claim shall be open to inspection and/or audit by representatives of the District.  Inspection and/or audit may be performed by employees of the District or by an independent consultant under contract with the District. The Contractor, subcontractors, or lower tier subcontractors shall provide adequate facilities, acceptable to the District and its auditors, for the inspection and/or audit process during normal business hours. The Contractor, subcontractors, and lower tier subcontractors shall make a good faith effort to cooperate with the auditors. The District shall provide reasonable advance notice of the scheduling of an audit. Information obtained in such audits shall be maintained as confidential information by the District to the extent provided by law.

       

      Failure of the Contractor, subcontractors, or lower tier subcontractors to maintain and retain sufficient records to allow the auditors to verify all or a portion of the claim or failure to permit the auditor access to the records of the Contractor, subcontractors, or lower tier subcontractors shall be grounds for denial of that portion of the claim.

       

      The auditors shall have available to them the following documents pertaining to the claim:

      All daily time sheets and contractor/subcontractor daily reports.

      All union agreements.

      All insurance records.

      All payroll and employee benefits records.

      All materials, equipment rental and subcontractor invoices and payment records.

      All Contractor-owned equipment records.

      All job cost reports.

      All cash disbursement journals.

       

      For claims seeking recovery of home office overhead, all financial statements for all years reflecting the operations on this contract and, if deemed appropriate, additional financial statements for three (3) years preceding execution of the contract. All other documents which support the amount of the claim.

       

      All documents and computation sheets used in bidding the project to the extent the claim is based upon any portion of the original bid.

       

      All scheduling documentation.

       

      1. Grounds for Claim Denial.

       

      12. Failure of the Contractor, subcontractors, or lower tier subcontractors to provide all of the required General Information and Specific Documentation shall be grounds for denial of that portion of the claim;

      13. If the District determines that the General Information and Specific Documentation (including Audit information, if applicable) provided does not support the claim or a portion thereof, the District shall have grounds to deny the portion of the claim that is not supported;

      14. Failure of the Contractor, subcontractors, or lower tier subcontractors to maintain and retain sufficient records to allow the auditors to verify all or a portion of the claim or failure to permit the auditor access to the records of the Contractor, subcontractors, or lower tier subcontractors shall be grounds for denial of that portion of the claim.

      Managing Engineer Decision/Further Review, Arbitration or Litigation.  The Managing Engineer shall issue a written decision on the claim within thirty (30) days, or such other period as the parties agree, after full documentation of the claim is submitted.  Failure of the Managing Engineer to issue a decision within such time shall be deemed a denial of the claim.  In the event the Contractor does not accept the decision of the Managing Engineer or denial of the claim by reason of failing to issue a decision, the Contractor may request the Director to review the claim.  If the Director fails to issue a written decision on the claim within thirty (30) days (or such other period as the parties agree) after receiving the Contractor’s request or upholds the decision of the Managing Engineer, the parties may, by written agreement, submit the matter to mediation or binding arbitration in accordance with procedures set forth in such agreement.  In the absence of a resolution of the claim or an agreement to arbitrate, either party may pursue its remedies in court.

    • 38. COVENANT AGAINST CONTINGENT FEES OR GRATUITIES

      The Contractor warrants that no individual, firm, partnership, or corporation has been employed or retained to solicit or secure this agreement upon an agreement or understanding for a commission, percentage, brokerage, or contingent fees, excepting bona fide employees of the Contractor or bona fide firms owned by the Contractor established for the purpose of securing business. For breach of this warranty Owner shall have the right to annul this agreement without liability, or in its discretion, to deduct from the Contract Price or otherwise recover, the full amount of such commission, percentage, brokerage or contingent fee.

      The Owner may by written notice to the Contractor terminate the right of the Contractor to proceed, if it is found after notice and hearing by the Owner or its duly authorized representative, that gratuities (in the form of entertainment, gifts, or otherwise) were offered or given by the Contractor or by any agent or representative of the Contractor to any officer or employee of the Owner with a view toward securing a contract, or the making of any determination with respect to the performance of such contract.

    • 39. SITE RESTORATION AND CLEANUP

      At all times during construction of the Work, Contractor shall keep the premises clean and orderly, and upon completion of the Work shall repair all damages caused by him and leave the area free of rubbish or excess materials of any kind.

      Contractor shall stockpile excavated materials in a manner that will cause the least damage to adjacent lawns, grassed areas, gardens, shrubbery, or fences, regardless of whether these are on private property, or on State of Idaho or Owner’s rights-of-way. Contractor shall remove all excavated materials from grassed and planted areas; leave these surfaces in a condition equivalent to their original condition, and replace topsoil areas with topsoil, raked and graded to conform to original contours.

      Upon completion of operations, Contractor shall hand-rake and drag all former grassed and planted areas, leaving all disturbed areas free from rocks, gravel, clay or any other foreign material and ready, in all respects for seeding. The finished surface shall conform to the original surface, and shall be free-draining and free from holes, ruts, rough spots, or other surface features detrimental to a seeded area.

      All existing drainage and irrigation facilities shall be cleaned and graded and natural drainage restored. Facilities broken or damaged shall be restored to their original condition and location.

    • 40. WORK HOURS/TIME OF COMPLETION

      Work shall begin and be completed as provided in the Contract Agreement. Once begun, the Contractor shall diligently continue operations to bring the Work to completion without interruption or delay.

      Except as otherwise stated in the Contract Documents, all Work at the Site shall be performed during regular working hours. Regular working hours shall be 7am to 7pm, Monday through Friday. Contractor shall not perform work at Site outside of the regular working hours or on the following listed holiday’s without Owner’s prior written consent. Such requests shall be submitted a minimum of 48 hours prior to the proposed period of extra working hours. Holidays are New Year’s Day, Presidents’ Day, Memorial Day, Independence Day, Labor Day, Veterans Day, Thanksgiving Day, the day after Thanksgiving, the day before Christmas, and Christmas Day. When any of these holidays occur on a Sunday, the following Monday shall be the nonworking day. When the holiday falls on a Saturday, the preceding Friday shall be the nonworking day.

      1. Substantial Completion.
        1. The Work is Substantially Complete when the Resident Engineer determines the Owner has full and unrestricted use and benefit of the facilities, both from an operational and safety standpoint, and only minor incidental work or correction or repair remains for the physical completion of the total Contract. Substantial Completion of roadway improvement projects is defined as having all construction traffic control items removed and all lanes of traffic open, unless otherwise approved by the Resident Engineer; the area cleaned, maintained and swept; paving complete; striping and pavement markings complete; curb, gutter, sidewalk and traffic islands complete; storm drain, irrigation and associated appurtenances complete; manhole adjustments and concrete collars complete; traffic signal and street lighting appurtenances complete and operational; and traffic signing complete.
        2. The determination by the Resident Engineer of Substantial Completion shall halt the continuing accrual of Contract Time and/or liquidated damages, except as noted in Failure to Complete Pre-Punch List and Final Punch List.
      2. Procedure for Determination of Substantial Completion.
        1. Contractor shall notify Resident Engineer, in writing five (5) working days prior to seeking a determination of Substantial Completion. During the five-day period, the Resident Engineer, or his authorized representative and the Contractor or his representative, shall perform a pre-final inspection of the Work to verify Substantial Completion and prepare a Pre-Final Punch List. The Contractor shall provide a list to the Resident Engineer at the pre-final inspection of all remaining pay items that need to be completed. If the Resident Engineer declares the Work Substantially Complete, the Owner will prepare and issue a Substantial Completion Notice to the Contractor. The Contractor may request a portion of retainage be released once the Substantial Completion Notice is issued. The Owner, in its sole discretion, shall determine the portion of retainage to be released to the Contractor. It is intended that 150% of the value of the remaining items identified on the Pre-Final Punch List, to be completed or repaired, will be withheld in retainage. If the Resident Engineer declares the Work to not be Substantially Complete, the Resident Engineer will supply the Contractor a written description of the items that need to be completed for the project to be considered Substantially Complete. Until those items are completed to the satisfaction of the Resident Engineer, Contract time and Liquidated damages will accrue per the terms of the Contract.
        2. The Contractor shall complete all of the Pre-Final Punch List items and all remaining pay items within the time frame noted in the General Notes of the Special Provisions or Invitation to Bid. The Contractor will be notified in writing that the Substantial Completion Notice has been issued. The Contractor may pick up a copy of the Notice at the Owner’s Construction Section office. The accounting of time to complete the Pre-Final Punch List items and remaining pay items will begin on the date of issuance of the Pre-Final Punch List / Substantial Completion Notice. Once all pay items and the Pre-Final Punch List are complete, the Contractor shall notify the Resident Engineer that the project is ready for a final walk through. At the completion of the final walk through, the Contractor will be given a Final Punch List. The Final Punch List shall be completed within thirty (30) calendar days. It shall be the Contractor’s obligation to notify the Resident Engineer when the Work is ready for a determination of Construction Completion, at which time the Resident Engineer shall inspect the Work.
        3. The Contractor may request that items identified on the Final Punch List, which cannot be completed within (30) calendar days, be removed from the Final Punch List and placed in an extension request where time/dates and possible Liquidated Damages will be determined by the Engineer. Such items may include hydro-seeding or items that are contingent on supplier availability or weather.
      3. Failure to Complete Pre-Final Punch List and Remaining Pay Items Within Time Allowed. If the Pre-Final Punch List and remaining pay item work is not completed within the allotted contract time, Liquidated Damages shall be assessed at $250 per calendar day. The Owner also reserves the right to engage another contractor to complete the remaining pay items and Pre-Final Punch List Work and deduct the costs from final payment/retainage.
      4. Failure to Complete the Final Punch List Within Time Allowed. If the Final Punch List work is not completed within thirty (30) calendar days of issuance, Liquidated Damages shall be assessed at $100 per calendar day, based on the Owner’s ongoing administrative costs to monitor completion of the Final Punch List. The Owner also reserves the right to engage another contractor to complete the Final Punch List Work and deduct the costs from final payment/retainage.
      5. Use of Completed Portions. The Owner may at any time during progress of the work, after written notice to the Contractor, take over and place in service any completed portions of the Work which are ready for service, although the entire Work per the Contract Documents is not fully completed, notwithstanding that the time for completion of the entire Work may not have yet expired. In such case, the Resident Engineer shall issue a certificate of acceptance for such portion of the Work, but taking possession thereof shall not be deemed an acceptance of any other portions of the Work nor any incomplete portions, nor of any Work not completed in accordance with the Contract Documents.
      6. Construction Completion: At the date of issuance of Construction Completion all warranties as provided in the Contract Documents shall commence. The Contractor may request additional retainage be released once Construction Completion is issued. The Owner, in its sole discretion, shall determine the portion of retainage released to the Contractor. The remaining retainage shall be withheld until the Final Pay Estimate is processed.
      7. Project Completion: The Project and Contract will be considered complete when the Final Pay Estimate has been processed.
      8. Warranty/NOT Period: Contractor shall remain responsible for maintaining all stormwater/erosion control Best Management Practices (BMPs) until the Contractors Notice of Termination (NOT) is filed. Contractor shall notify the Resident Engineer when in their opinion the Project is ready to have the NOT filed, so that ACHD can review and make a determination. Once the NOT has been filed the Contractor shall be responsible for removing all BMPs. No additional compensation will be granted for maintaining or removing BMP’s. The Contractors Right-of-Way Bond shall remain in place until the warranty period is over or the NOT has been filed, which ever comes later. Cost Information and Certification
      9. Documents Available for Inspection.
        1. For the purposes of determining equitable adjustments in the Contract Price as a result of proposed or actual additions to, deletions from or changes in the performance of Work under the Contract Documents, or when proceeding under General Condition 37 (Claims and Disputes) or General Condition 44, Extra, Altered or Force Account, Contractor’s wage, payroll, and cost records pertaining to request for additional costs shall be open to inspection and/or audit by representatives of ACHD. The Contractor shall retain these records on the premises. Cost records of all subcontractors and all lower tier subcontractors shall be retained and open to similar inspection and/or audit process during normal business hours. The Contractor, subcontractors, and lower tier subcontractors shall make a good faith effort to cooperate with the auditors. The Contractor will be provided with reasonable notice before the first day the audit is scheduled to commence. All cost records shall be retained until the claim is resolved. Information obtained in such audits shall be maintained by ACHD to the extent provided by law as confidential information.
        2. Failure of the Contractor, subcontractors, or lower tier subcontractors to maintain and retain sufficient records to allow the auditors to verify all or a portion of the claim or to permit the auditor access to the books, ledgers or any other records of the Contractor, subcontractors, or lower tier subcontractors shall constitute a waiver of that portion of the claim.
        3. At a minimum, the auditors shall have available to them the following manner provided herein prior to further pursuing their claim by binding documents pertaining to the claim:
          1. All daily time sheets and supervisors daily reports.
          2. All union agreements.
          3. All insurance, welfare, and benefits records.
          4. All payroll registers.
          5. All earnings statements and records.
          6. All payroll tax statements and records.
          7. All materials records, invoices and requisitions.
          8. All materials cost distribution sheets.
          9. All equipment records.
          10. All vendors, rental agencies, subcontractor’s and lower tier subcontractor’s invoices.
          11. All subcontractor’s and lower tier subcontractor’s payment certificates.
          12. All canceled checks for both payroll and vendors.
          13. All Job cost reports.
          14. All job payroll ledgers.
          15. All general ledgers.
          16. All cash disbursement journals.
          17. All financial statements for all years reflecting the operations this contract.
        4. In addition, ACHD may require, if it deems appropriate, additional financial statements for three (3) years preceding execution of the contract and three years following final acceptance of the project.
        5. All documents that relate to each and every construction claim for this project together with all documents that support the amount of damages as to each claim for this project.
        6. Worksheets, Accounting Spreadsheets or any other documents used to prepare the elements of the construction claim including but not limited to labor, benefits and insurance, materials, equipment, subcontractors, all documents which establish the time periods, individuals involved, the hours for the individuals, and the rates for all the individuals.
        7. All documents and computation sheets used during the course of bidding to the extent the claim is based upon the original bid.
        8. All scheduling documentation.
      10. Certification. All Certifications required by ACHD shall meet the certification requirements set forth in General Condition 37.
    • 41. MANNER OF PAYMENT

      Pay Period. Pay periods under this contract are from the first day of the month through the last day of the month.

      The Contractor shall be responsible to certify a “Request for Progress Payment” on or before the 25th day of each month. The “Request for Progress Payment” shall include an affirmation that there is no basis to withhold payment based upon section 34. The “Request for Progress Payment” shall be reviewed by the Resident Engineer and if the Resident Engineer concurs, a Certificate of Payment will be issued. If there is any disagreement to the correctness or the failure to currently meet all requirements contained in section 34, a meeting shall be held between the Resident Engineer or his representative and the Contractor. Failure to reach agreement by the third working day of the following month may result in a 30-day delay in payment.

      All items shown or noted on the plans and in the Contract Documents that are not specifically identified as bid items are considered incidental items. The cost of furnishing and installing all incidental items will not be paid for separately, but shall be included in the contract unit or lump sum prices for other items.

      Separate estimates of work completed shall be required for each Bid Schedule called for in the contract each month work is performed.

      Retainage. Owner shall retain 5% of all partial payments until final inspection and acceptance of Work has been completed. All retainage minus any and all monies due and owing by the Contractor to the Owner will be paid as a part of the final payment. No interest will be paid on retainage.

      Final Payment.Within 60-calendar days after the completion and issuance of Final Acceptance of Work, the Owner shall pay the Contractor the full amount of the Contract Price, less all partial payments previously made, any monies due under General Condition 42 and any further monies due to the Owner.

    • 42. CONTRACTOR FOR PUBLIC WORKS TO PAY OR SECURE TAXES

      Pursuant to Idaho Code section 63-1503 (as amended), the Contractor, in consideration of securing the business of erecting or constructing public works in this state, recognizing that the business in which he is engaged is of a transitory character, and that in the pursuit thereof, his property used therein may be without the state when taxes, excises, or license fees to which he is liable become payable, agrees:

      1. To pay promptly when due all taxes, (other than on real property), excises and license fees due to the state, its subdivisions, and municipal and quasi-municipal corporations therein, accrued or accruing during the term of this contract, whether or not the same shall be payable at the end of such term;
      2. That if the said taxes, excises, and license fees are not payable at the end of said term, but liability for the payment thereof exists, even though the same constitute liens upon his property, to secure the same to the satisfaction of the respective officers charged with the collection thereof; and
      3. That, in the event of his default in the payment or securing of such taxes, excises, and license fees, to consent that the department, officer, board, or taxing unit entering into this contract may withhold from any payment due him hereunder the estimated amount of such accrued and accruing taxes, excises, and license fees for the benefit of all taxing units to which said contractor is liable.
      4. That in compliance with Idaho Code 63-1504 (as amended), the Contractor shall submit a certification with each construction payment request certifying that it has paid all taxes, excises, and license fees due to the state and its taxing units, due and payable during the term of the contract for such construction, and that it has secured all such taxes, excises, and license fees liability for the payment of which has accrued during the term of such contract, notwithstanding they may not yet be due or payable.
    • 43. Cost Information and Certification

      For the purposes of determining equitable adjustments in the Contract Price as a result of proposed or actual additions to, deletions from or changes in the performance of Work under the Contract Documents, or when proceeding under General Condition 37 (Claims and Disputes) the Contractor shall (when requested to do so by the Resident Engineer) provide the Owner with copies of payrolls and other cost data applicable to the Work. All such cost information shall be certified by the Contractor and/or his Subcontractors as being true, complete and correct and shall be furnished to the Owner within three (3) working days following the Resident Engineer’s written request.

    • 44. Payment for Extra Work

      Adjustments, if any, in the amounts to be paid to the Contractor by reason of any change, addition, or deduction shall be determined by one of the following method:

      By an acceptable lump sum proposal which includes supporting documentation regarding labor, material and equipment estimates from the Contractor; or

      By contract unit prices contained in the contract, or by unit prices mutually agreed upon by the Contractor and the Owner; or

      By force account.

      It is the responsibility of the Contractor, before proceeding with any change, to satisfy himself that the change has been properly authorized by the Owner. No charge for extra work or any other change will be allowed unless the extra work or change has been authorized in writing by the Owner and the compensation or method thereof is stated in such written authority.

      When payment for extra work is by lump sum, agreed price(s), or by unit prices mutually agreed upon by the Contractor and the Owner, the Contractor shall include in such agreed-upon prices any and all applicable taxes on taxable materials used in such work.

    • 45. Extra, Altered and Force Account Work

      In General.Extra, altered or force account work performed in accordance with the requirements of the provisions regarding Authorized Changes in Work (GC25) or Variations in Quantities (GC 29) will be paid for at the unit prices or agreed prices stipulated in the order authorizing the work, or Owner may require the Contractor to do such work on a force account basis. The extra, altered or force account shall be compensated in the following manner:

      Labor.For all labor and foremen in direct charge of the specific operations, the Contractor shall receive the rate of wage, or scale, agreed upon in writing before beginning work for each and every hour that said labor and foremen are actually engaged in such work. Supervisory services are considered to be included in the overhead and profit and is not a separate pay item.

      The Contractor shall receive the actual costs paid to, or in behalf of workers by reason of subsistence and travel allowances, health and welfare benefits, pension fund benefits, or other benefits, when such amounts are required by collective bargaining agreement or other employment contract generally applicable to the classes of labor employed on the work.

      An amount equal to 20 percent of the above items for a combined overhead and profit will be paid to the Contractor.

      Bonds, Insurance and Taxes.For property damage, liability and workers’ compensation insurance premiums, unemployment insurance contributions, bonds and social security taxes on the force account work; Contractor shall receive the actual cost, to which cost 6 percent will be added. The Contractor shall furnish satisfactory evidence of the rate or rates paid for such bond, insurance and taxes.

      Materials.For materials accepted by the Resident Engineer and used, the Contractor shall receive the actual cost of such materials delivered on the work, including transportation charges paid by the Contractor, exclusive of machinery rentals as hereinafter set forth, to which cost 15 percent will be added for a combined overhead and profit.

      Equipment.For any machinery or special equipment, other than small tools, the Contractor shall receive rental rates as established herein and agreed to in writing before the work is begun plus those transportation costs directly attributable to the extra, altered or force account work for the actual time the equipment is in operation on such work.

      General -The Rental Rate Blue Book published by Dataquest, Inc. San Jose, California (hereinafter referred to as the Blue Book), as modified herein, will be used to establish rental rates for equipment approved for use by the Resident Engineer on the extra, altered or force account work. The effective date of each section of the Blue Book when revised by the publisher shall be the date the revision is received by the Resident Engineer. The rates established prior to the extra, altered or force account work shall apply until the ordered work is complete. No markups will be allowed on equipment set forth in subsection (g), except as provided herein.

      Rental Rate -Rental rates for equipment will be paid on an hourly basis for each hour the equipment is used, in accordance with the following formula:

      Hourly Rate = [(MR+A T) x RA x RF]+ OC

      176 hours/month

      Where:

      MR = Blue Book Monthly Base Rate

      AT = Blue Book Monthly Attachment Rate

      RA = Blue Book Rate Adjustment Factor

      RF = Blue Book Regional Adjustment Factor

      OC = Blue Book Operating Costs

      Five percent (5%) will be added to the above established hourly rate.

      Limitations:The attachment rate will be included in the rental rate only when deemed applicable and essential to the extra, altered or force account work ordered by the Resident Engineer. When multiple attachments are approved for use and the attachments are being used interchangeably on the extra, altered or force account work, only the one attachment having the higher rate will be eligible for payment. Shop tools: Rental will not be allowed for equipment listed in Section 18-Shop Tools of the Blue Book, having a listed daily rate of less than $5.

      Standby Rate -When ordered by the Resident Engineer, standby time shall be paid in accordance with the following formula:

      Hourly Rate = [(MR+AT) x RA x RF] x 1/2

      176 hours / month

      Where:

      MR = Blue Book Monthly Base Rate

      AT = Blue Book Monthly Attachment Rate

      RA = Blue Book Rate Adjustment Factor

      RF = Blue Book Regional Adjustment Factor

      Limitations: Operating costs for equipment will not be included in the standby rate.

      No more than eight hours of standby time will be paid during 24-hour period more than 40 hours of standby time will be paid during a one-week period.

      Rental Invoices -If Contractor-owned equipment is not available and equipment is rented from outside sources, payment will be on the basis of actual invoice cost. The Resident Engineer reserves the right to disallow invoice payment on rates higher than those set forth herein. When the invoice specifies that the rental rate does not include fuel, lubricants, repairs and servicing, an amount equal to 15 percent of the invoice will be added for such items. Cost of equipment rented from outside sources will be paid at the rate established above plus 5 percent.

      Owner-Operated Equipment -Applies Only to Trucks. Owner-operated equipment shall be paid on the basis of actual invoice costs. It will not be necessary to segregate the labor and equipment costs. Cost of owner-operated equipment will be paid at invoice cost plus 5 percent. The Resident Engineer reserves the right to disallow invoice payment based on rates higher than those set forth herein.

      Transportation Costs -The rental rates established herein are based on the Contractor having the equipment available on the project site to accomplish the extra, altered or force account work. In the event the required equipment is not on the site and it is necessary to furnish equipment from off-site exclusively for extra, altered or force account work, the cost of transporting the equipment to the work site and returning it will be allowed as an additional item of expense. Cost of transportation by common carrier shall be paid at invoice cost plus 5 percent (5%). Self-propelled equipment, other than trucks, will be paid at a rate equal to 75 percent of the rental rates established herein for transportation plus 5 percent.

      Equipment Condition and Job Conditions -The rental rates established herein are for equipment of modern design and in good working condition. When equipment is used that does not meet such requirements or is not operated in a manner as to provide normal output or production, the Resident Engineer may disapprove the use of such equipment or allow its use only at an agreed reduced rate. Job conditions that are substantially more severe than average and that would result in conditions substantially increasing “normal wear and tear” may require an upward adjustment of rental rates established herein as agreed to by the Contractor and the Resident Engineer.

      Unlisted Equipment -In the event proposed equipment to be used on extra, altered or force account work is unlisted, the Contractor and Resident Engineer shall agree on an equitable rental rate.

      Miscellaneous. No additional allowance will be made for general superintendence, the use of small tools, or other costs for which no specific allowance is herein provided.

      Statements. No payment will be made for work performed on an extra, altered or force account basis until the Contractor has furnished the Resident Engineer with duplicate itemized statements of the cost of such extra, altered or force account work detailed as follows:

      Name, classification, dates, daily hours, total hours, labor rate, and extension for each laborer and foreman.

      Designation, dates, daily hours, total hours, rental rate, and extension for each unit of machinery and equipment.

      Quantities of materials, prices and extensions.

      Transportation of materials.

      Costs of property damage, liability and workers’ compensation insurance premiums unemployment insurance contributions, bonds and social security tax.

      Statements shall be accompanied and supported by receipted invoices for all materials used and transportation charges. However, if materials used on extra, altered or force account work are not specifically purchased for such work but are taken from the Contractor’s stock, then in lieu of the invoices the Contractor shall furnish an affidavit certifying that such materials were taken from stock, that the quantity claimed was actually used, and that the price and transportation claimed represent the actual cost to the Contractor.

      Subcontractors. When work on extra, altered or force account basis is performed by an approved first or lower tier Subcontractor, an amount based on the following table will be allowed in addition to the percentages in a, b, c and d above, to reimburse the prime Contractor for the administrative expenses incurred in connection with the work. Bid items with a price per unit in the original contract, which are included in extra, altered or force account work, are not eligible for administrative expenses.

      Agreed Price of first or lower tier Subcontractors’ work

      Amount Adjustment Maximum

      To $1,000 (lump sum) $100 $100

      Over $1,000 to $10,000 $100 plus 5% of excess over $1,000 $500

      Over $10,000 to $150,000 $550 plus 3% excess over $10,000 $4,750

      Over $150,000 $5,000 $5,000

      Approval of this additional amount will be made after receipted invoices are furnished by the Contractor.

      Additional markups for overhead and profit, above the percentages contained in subsections a, b, c, and d, will not be allowed.

      Reporting. Extra, altered or force account shall be adjusted daily upon duplicate report sheets furnished by the Resident Engineer and signed by both parties. These daily reports shall be considered the true record of the extra, altered or force account work done.

    • 46. CONSTRUCTION/SURVEYS
      1. Unless otherwise specified, the Owner shall furnish initial land survey, base line, and construction stakes for locating the principal component parts of the Work, together with a suitable number of benchmarks adjacent to the work.
        1. The Contractor shall carefully preserve benchmarks, construction stakes, and reference points within the construction limits as shown on the plans and shall immediately notify the Resident Engineer or the Owner’s Project Representative of any existing federal, state, county, city and private land monuments encountered which are not shown on the plans.
        2. The Contractor shall also preserve all lot, block, property corners and street intersection monuments outside the construction limits. If such monuments are disturbed, the Contractor shall have them replaced by a licensed surveyor at the Contractor’s sole expense, otherwise the Owner shall contract a licensed surveyor to reestablish the lost monument in accordance with the provisions of the Corner and Perpetuation and Filing Act, Idaho Code 55-1601 through 55-1613 and this cost will be deducted from the final payment. All costs associated with maintaining or replacing monuments shall be incidental to the project.
      2. Construction staking shall be provided to the Contractor as follows:
        1. Construction Staking: Construction staking shall include but not be limited to staking lines, grades, pipes, minor structures, major structures, curb and gutter, sidewalk, manholes and drop inlets. The District or Consultant may check grade at periodic intervals to assure compliance with the contract. Remeasurement work or proof of correct staking shall be done if the District determines that any portion does not conform to line grade and dimensions shown on the plans or as directed.
        2. Provided to Contractor: Construction staking shall be provided to the Contractor as follows: One set of construction stakes will be provided by the District or a Consultant to establish reasonable horizontal and vertical control to delineate the work to be accomplished. The District or Consultant also will provide project staking, sub-grade and gravel-grade sheets to the contractor for use by his personnel and sub-contractors.
        3. Notice Required for Staking: At least forty-eight (48) hours (2 business day) notice from the Contractor through the Project Representative is required to begin construction staking. As example, if the survey crew receives a request for staking at 2:00 P.M. on Friday, the Owner will be on site no later than 2:00 P.M. two business days later (Tuesday).
        4. Slope Stakes: When necessary, slope stakes and reference hub & stake shall be established at cut and fill Catch Points on both sides of centerline at 50-foot stations. Cut and Fill catch points shall be marked with paint and shall be referenced with an offset hub and stake; with offset distance and grade to the Catch Point; and offset distance and grade to Hinge Point or Shoulder at that station. In taper sections, centerline distance shall also be referenced on the stake.
        5. Sub-Grade Elevation: The Owner at the request of the District’s Project Representative shall check sub-grade elevation when the sub-grade is within 0.3’ of final grade. It shall be the Contractor’s responsibility to rough grade the road from the provided reference hubs, slope stakes or curb & gutter construction stakes. The Owner shall paint Cuts and Fills those locations where the sub-grade is checked and will provide the Contractor with cut sheets for those areas checked.
        6. Ballast Course – Design Gravel Base Course or Uncrushed Aggregate Base: Ballast Course (Pit Run) stakes shall be set when base course is within 0.3’ of grade. Hubs shall be set to the nearest 0.1’ of the design grade and a stake with a Cut or Fill will be placed at that location where the grade is greater than 0.5’. Pit Run stakes shall be set at 50-foot stations on centerline, grade breaks and at edge of pavement line if curb and gutter is not being constructed. Where roadways are 44-feet or greater in width, quarter crown stakes also will be set.
        7. Finishing ¾” Gravel Stakes or Blue Tops: Finishing stakes or Blue Tops shall be set when ¾” gravel base course is within 0.2’ of final grade. The stakes shall be set to the nearest 0.02’ of the design grade line. Blue tops shall be set at 50-foot stations on centerline, grade breaks and at edge of pavement line if curb and gutter is not being constructed. Where roadways are 44-feet or greater in width, quarter crown stakes also will be set.
        8. Pipe and Ditch Staking: Pipe and ditch staking shall be with hub and stake on an offset line and shall not fall within trench excavation limits. Pipes and Ditches shall be staked on 100-foot stationing and at the beginning, ending, angle points and grade breaks. Offsets shall be to centerline of pipe or structure and marked with cut or fill (C/F) to flow line (FL). The Contractor will provide the necessary excavation to field verify match elevations where needed prior to final grade setting.
        9. Minor Structures: Minor structures such as irrigation structures, sand and grease traps, drop inlets and manholes shall be staked to the centerline of structure or as called out on the plans.
        10. Major Structures: Major structures such as Bridges and MSE Walls shall be staked by setting hub and tack or other suitable monument with guard stake on each side of the major structural parts and centerline control. This will include the ends of the bridge and wing wall angle points; and the beginning, end and angle points for the MSE Wall. A Bench Mark will be set in close proximity to the structure.
        11. Curb & Gutter and Edge of Pavement Staking: Top Back of Curb (TBC) and Edge of Pavement (EP) hub and stakes shall be placed every 50-feet. It shall include extra points for grade breaks/changes, high/low point on vertical curves, PC, PT, Angle Points, and Radius Points for curves with a radius under 50-feet, or where practical. The stakes shall have an offset distance and cut or fill (C/F) to TBC or EP. The Contactor shall request TBC stakes only after the roadway surface has been brought up to grade and the TBC offset hubs can be set within a distance of 10’ from TBC.
        12. Driveway Locations: The Owner will not stake driveway locations. It shall be the Contractor’s responsibility to locate the driveways in conformance with the locations specified in the contract drawing or otherwise provided by the Owner.
      3. Contractor’s Responsibility
        1. It shall be the Contractor’s responsibility to protect survey construction stakes once requested. Construction survey stakes destroyed after being requested by the Contractor will be restored at contractor’s expense. The District will keep a record of the time and cost to replace lost stakes and these costs will be forwarded to the Construction Supervisor. These costs shall be deducted from progress estimates. Third party damage by disgruntled property owners, vandalism or Acts of God will be replaced at the Owner expense.
        2. The Contractor shall comply with all laws, ordinances, rules and regulations bearing on the conduct of his work. If the Contractor observes that the drawings and specifications are at a variance therewith, he shall notify the Engineer, in writing.
        3. The Contractor shall remove all construction stakes remaining at project completion. The cost of this work shall be considered incidental to the project.
    • 47. PROJECT MAINTENANCE
      1. Trenches: All trenches in pavement cut by the Contractor on roadways that are used for access in or around the project shall be backfilled and immediately covered with temporary or permanent pavement. These trenches must be backfilled and paved prior to opening the access to vehicular traffic, or as approved by the Resident Engineer.
      2. Signage: The Contractor is responsible to maintain any and all required regulatory and street signage, including but not limited to, directional, safety, traffic signage, street name signs, etc. in service during construction and provide continuous maintenance thereof. The Contractor shall provide any temporary signage necessary as directed by the Resident Engineer.
      3. Driving Surfaces: All surfaces used for vehicle access in or around the project shall be maintained in a manner to ensure safe and reasonable passage of vehicles, and minimize the impact to the environment. This may require blading, sweeping, watering or other maintenance of the surface and peripheral streets on a daily or more frequent basis as determined by the Resident Engineer. The Contractor shall employ reasonable dust abatement methods as directed by the Resident Engineer.
        1. If the Contractor fails to comply with these provisions, the Owner shall (at its sole discretion):
          1. have the work performed by third parties and offset the cost thereof from the amount due to the Contractor, including any monthly progress pay estimates; or
          2. suspend all other Contractor work activities on the project site or his Sub-contractors until such time that the requirement is met to the satisfaction of the Resident Engineer.
        2. The Contractor shall not be entitled to reimbursement on payment of any additional costs incurred in complying with this provision, including but not limed to, costs associated with maintenance.
    • 48. POWER AND WATER SERVICE

      The Contractor shall coordinate with the Project Inspector to arrange for power service for lighting and power and water service for sprinkler irrigation. The Contractor will provide a minimum of 30 days advance notice to arrange for power and water services. No additional time will be awarded to the Contractor for delays caused by a failure to provide this advanced notice.

    • 49. PROPERTY ACCESS POINTS

      No later than 14 calendar days following the placement of a property access, such as asphalt and concrete driveways, the Contractor shall complete the specified access construction or repair to any adjacent properties, unless otherwise approved by the Resident Engineer. The Contractor shall conduct and perform all repair activities in a diligent manner without delay until completed. If the Contractor fails to comply with this provision, the Owner shall suspend all other work activities on the project site until such time that this provision is fully completed to the satisfaction of the Owner. The Contractor shall not be compensated for any additional costs incurred for compliance with this provision.

    Submission Requirements

    • Bidder's Information (required)

      Example: ABC Contractor

    • Bidder's Firm "Full Address" (required)

      Must provide the "Full Address" (Address, City, State, and Zip)

      Example: 123 Any Street 
                      City, State 12345

    • Contractor Public Works License Information (required)

      The Contractor must provide its valid Public Works Contractor License Number, including the applicable Class and Specialty type designation (1, 2, 3 or 4), formatted as follows:

      License Number – Class – Specialty Code
      (e.g., PWCL 010125 – A – 4)

      Example provided for formatting purposes only; not an actual license number.

    • State of Domicile (required)
    • Bidder's Contact Name and Title (required)

      Must provide the "Full Name" and "Title" of the Individual responsible for overseeing this contract.

      Example: Joe Smith, Estimator

    • Bidder's Contact Phone Number (required)

      Must provide Bidder's Contact Phone Number of the individual responsible for overseeing this contract.

      Sample: 123-456-7890

    • Bidder's Fax Number (required)

      Please provide the firm's fax number. 

      Note: If the firm no longer utilizes a fax line, you may indicate "N/A."

      Sample: 123-456-7890

    • E-Mail Address (required)

      Must provide the Email Address of the Individual responsible for overseeing this contract. 

    • COMPLIANCE CERTIFICATION (required)

      Employment of Residents of Idaho

       

      As part of this Bid Proposal submitted to Ada County Highway District (ACHD) the Contractor acknowledges the ACHD requirement to submit a certification that the Contractor will comply with Idaho Code Title 44, Chapter 10. This citation requires, in part:

       

      “…44-1001 Employment of residents of Idaho - Wage scale - Federal funds. In all state, county, municipal, and school construction, repair, and maintenance work under any of the laws of this state the contractor, or person in charge thereof must employ ninety-five percent (95%) bona fide Idaho residents as employees on any such contracts except for procurement authorized in Section 67-2808 (2), Idaho Code, or where under such contracts fifty (50) or less persons are employed the contractor may employ ten percent (10%) nonresidents, provided however, in such a case employers must give preference to the employment of bona fide Idaho residents in the performance of such work; provided, that in work involving the expenditure of federal aid funds this act shall not be enforced in such a manner as to conflict with or be contrary to the federal statutes prescribing a labor preference to honorably discharged members of the United States armed forces, including airmen, soldiers, sailors, and marines, prohibiting as unlawful any other preference or discrimination among the citizens of the United States…”.

       

      “. . . 44-1003. DEFINITIONS OF TERMS USED. Labor is hereby defined to be all services performed in the construction, repair, or maintenance of all state, county, municipal, and school work.

       

      A bona fide resident of Idaho is hereby declared to be a person, who, at the time of his said employment and immediately prior thereto, has resided in this state for not less than one (1) year. . .”.

       

      Pursuant to Idaho Code Title 44, Chapter 10, the Contractor, being duly sworn, depose, and certify that the Contractor shall be in compliance with Idaho Code 44, Chapter 10, throughout the execution of the Project identified herein.

       

    • Bid Security
    • Bid Security (required)

      How is the Bid Security being provided?

    • Electronic Bid Bond

      Please enter your Bid Bond information from Surety2000 below.

    • Bid Security

      Upload a copy of your Bid Security or verified through Surety 2000 above.

    • Proposal Information
    • Proposal Statement Confirmation (required)

      1. The undersigned, hereinafter called Bidder, declares that the only persons or parties interested in this proposal are those named herein, that this proposal is, in all respects, fair and without fraud, and that it is made without collusion with any official of Ada County Highway District (ACHD) or with any person submitting another proposal for this contract.

      2. The Bidder further declares that the Contract Documents have been carefully examined for the construction of the project, that the Bidder has personally inspected the site and has been satisfied as to the work involved, including materials, equipment and conditions.

      3. The Bidder further acknowledges, declares and represents that the Bidder has carefully examined all omissions, erasures and/or alterations (collectively “modifications”) to the Proposal Documents for Submittal made by the Bidder and approves of all such modifications and that the individual(s) initialing any such modifications has authorization to do so on behalf of the Bidder.

      4. The Bidder acknowledges the fact that the description of the quantities of work and materials, as included herein, is intended only to indicate the general nature of the work and that this proposal is made according to the provisions and under the terms of the contract documents, which documents are hereby made a part of this proposal.

      5. The Bidder further agrees that they have exercised their own judgment regarding the interpretation of subsurface information and has utilized all data believed pertinent, both from the ACHD and other sources in arriving at the Bidder’s conclusions.

      6. The Bidder agrees that if it is notified via a “Notice of Intent to Award Letter,” that it is the apparent low Bidder and may be awarded the contract, the Bidder will sign the contract in the form annexed hereto, and deliver to ACHD the executed contract, Contract Certification, bonds and insurance required herein by the date and time specified by ACHD in the “Notice of Intent to Award Letter;” and will to the extent of the Bidder’s proposal, furnish all labor, machinery, tools, apparatus, and other means of construction to do the work and furnish all the materials necessary to complete the work in the manner, in the time, and according to the methods specified in the contract documents and required by ACHD.

      7. The Bidder further agrees to complete the construction, in all respects, for which their proposal is accepted within the time period set forth in the Contract Documents.

      8. In the event the Bidder is awarded the contract and shall fail to complete the work within the time specified for completion, as more particularly set forth in the Contract Documents, liquidated damages shall be paid to ACHD at the daily rate indicated in the Contract Agreement until the work shall have been finished as provided by the contract documents.

      9. The Bidder agrees that all applicable sales and use taxes are included in the stated bid prices for the work, unless provision is made herein for the Bidder to separately itemize the amount of such taxes.

      10. The Bidder further proposes to accept as full payment for the work proposed herein the amounts computed under the provisions of the Contract Documents and based on the lump sum or unit price amounts, it being expressly understood that the unit prices are independent of the exact quantities involved. The Bidder agrees that the lump sum prices and the unit prices represent a true measure of the labor and materials required to perform the work, including all allowances for indirect costs, overhead and profit for each type or unit of work called for in these Contract Documents.

      11. Proposals must be accompanied by a certified check, cashier's check, or an original bid bond issued by a surety authorized to issue such bonds in the State of Idaho, in the amount of ten percent (10%) of the total amount of the proposal submitted. Failure to include a Bid Security as required with the bid will render said proposal void and non-responsive. Any Contractor submitting a certified check or cashier's check for bid guarantee will be required to submit with the proposal a letter from the Bidder’s bonding company stating that it will guarantee bonding for the Contractor, in the event said Contractor is notified via a “Notice of Intent to Award Letter,” that it is the apparent low bidder and may be awarded the contract. Said letter is to be included with the bid documents, and shall name the Contractor, project number, and the amount of bonding value being guaranteed.

      12. The Bidder further agrees that in case of its default in executing such contract or providing the required Contract Certification and all required bonds and insurance, the bid security accompanying Proposal Documents for Submittal and any money payable thereon, shall be and remain the property of ACHD.

      13. In accordance with Idaho Code 67-2348, and to the extent permitted by Federal laws and regulations, whenever ACHD shall let for bid any contract to a contractor for any public works, the contractor domiciled outside the boundaries of Idaho shall be required, in order to be successful, to submit a bid the same percent less than the lowest bid submitted by a responsible contractor domiciled in Idaho as would be required for such an Idaho domiciled contractor to succeed over the bidding contractor domiciled outside Idaho on a like contract being let in the Bidder’s domiciliary state.

      14. In accordance with Idaho Code 67-2349, and to the extent permitted by Federal laws and regulations, whenever ACHD shall let for bid any contract for purchase of any material, supplies, services, or equipment, the Bidder domiciled outside the boundaries of Idaho shall be required, in order to be successful, to submit a bid the same percent less than the lowest bid submitted by a responsible Bidder domiciled in Idaho as would be required for such an Idaho domiciled Bidder to succeed over the Bidder domiciled outside Idaho on a like con-tract being let in the Bidder’s domiciliary state.

      14.1 For the purposes of this section, any Bidder domiciled outside the boundaries of the State of Idaho may be considered as an Idaho domiciled Bidder, provided that there exists for a period of one (1) year preceding the date of the bid a significant Idaho economic presence as defined herein. A significant economic presence shall consist of the following:

      14.1.1 That the Bidder maintain in Idaho fully staffed offices, or fully staffed sales offices or divisions, or fully staffed sales outlets, or manufacturing facilities, or warehouses or other necessary related property; and

      14.1.2 If a corporation be registered and licensed to do business in the State of Idaho with the office of the Secretary of State.”

      15. The Bidder shall acknowledge by their submitting this Proposal that the Addendum have been received by the Bidder and that the Bidder has incorporated their content into the Bid attached hereto.

       

    • Statutorily Required Sub-Contractor Information - Type of Work, Name, Address, and License Number

      Idaho Code 67-2310 requires that Bidders comply with rules regarding listing of subcontractors for specific areas of licensed work:

      1 The Bidder shall include in this Proposal form the name and address or names and addresses of the subcontractor(s) who the Bidder shall subcontract the plumbing, heating, ventilation, and/or air conditioning; and/or electrical work, in the event the Bidder is awarded the contract.

      2 The Bidder shall not name any subcontractor in Proposal form unless the Bidder has received communication from the subcontractor(s) concerning their willingness to participate in the work identified in the Contract Documents. For the purposes of this section, “communication” shall include telephone, mail, facsimile machine, in person, or by computer using the Internet or a bid service.

      3 At the time subcontractor(s) are named by the Bidder in this Proposal form, they each shall possesses the appropriate licenses or certificates of competency issued by the State of Idaho covering the contractor work classification in which each respective sub-contractor is named.

      4 The Bidder shall comply with Idaho Code 54-1902 (3) which prohibits any public works contractor to accept a bid from any person who at that time does not possess the appropriate public works license for the project involved; or to accept bids to sublet any part of any contract for specialty construction from a specialty contractor who at that time does not possess the appropriate license. This provision does not apply to public works funded in whole or in part by federal aid funds.

      5 In the event the Bidder secures the contract and if the Bidder and a named subcontractor cannot finalize the terms of agreement between them for the work for any reason other than cost, the Bidder shall name another subcontractor by written notification within ten (10) days of being awarded the public works contract. The Bidder shall disclose to ACHD the cost for work to be performed by the substitute subcontractor. If the amount of the substitute subcontractor cost is less than the original subcontractor’s bid, the reduction in cost shall be passed through to the benefit of ACHD.

      6 Failure to name subcontractors as required by this section and Idaho Code shall render any bid submitted by the Bidder as unresponsive and void. Knowing failure to comply with Idaho Code 54-1914, 54-1920, and 67-2310 may result in civil and/or criminal penalties.

      7 Ada County Highway District has determined that the following licensed subcontractor(s) are required for the Proposed Project:

      None

      Contractor must provide the List Required Sub-Contractor Information as follows: (indicated above)

      • Sub-Contractor Name
      • Sub-Contractor Associated License (such as Electric Board License, HVAC Board License, or Plumbing Board License). Plus the Class of the License.
      • Sub-Contractor Address

      (e.g., ELE 010125 – A) (e.g., HVAC 010125 – A) (e.g., Plumber 010125 – A)

      Example provided for formatting purposes only; not an actual license number.

    • Authorize Representative Signature (required)

      Once you start your proposal you will be asked to complete a DocuSign form.

    • Contract Number: (required)
    • Project Number: (required)
    • GIS Number:
    • Project Location: (required)
    • Work Shall Consist of? (required)

      Please enter the information needed to explain the work shall consist of?

    • Expected Contract Bonding Requirement: (required)

      Example: $500,000

    • Dates of Advertisement (required)

      Example: April 5 and 12, 2022

    • Number of Plan Sheets (required)

      Sample: Eighteen (18)

    • Project Notice to Proceed (required)

      Example: April 18, 2022

    • Project Completion Date (required)

      Example: April 18, 2022

    • Liquidated Damages (required)

      Example: $1,000

    • Will this project include irrigation? (required)

      If yes, a legal Notice with irrigation information will be added

      If no, the standard legal Notice will be added

    • Statutorily Required Subcontractors (required)

    Key dates

    1. April 7, 2026Published
    2. April 22, 2026Responses Due

    AI classification tags

    Frequently asked questions

    SLED stands for State, Local, and Education. These are solicitations issued by state governments, counties, cities, school districts, utilities, and higher education institutions — as opposed to federal agencies.

    SamSearch Platform

    Stop searching. Start winning.

    AI-powered intelligence for the right opportunities, the right leads, and the right time.