Active SLED Opportunity · ARIZONA · CITY OF AVONDALE
AI Summary
City of Avondale seeks bids for PW 26-065 Dysart Sewer Replacement Phase II -A, involving installation of a 12-inch sanitary sewer system, manholes, pavement work, and traffic control. Licensed General Engineering or KA Dual Engineering contractors are invited to submit bids by June 3, 2026. Project includes compliance with federal regulations and Buy America provisions.
The Work included in this Project consists of of the installation of a new 12-inch sanitary sewer, including PVC sewer piping, precast composite polymer manholes, bypass pumping, sewer stub-outs, asphalt concrete pavement removal and replacement, striping and marking, sewer pipe and manhole abandonment/removal, temporary traffic control, and all incidental items to complete the work.. The City is issuing this IFB to secure a qualified A General Engineering or KA Dual Engineering Licensed Contractor to perform the Work and provide Materials as more particularly described in the Specifications attached to this IFB, and incorporated herein by reference. Bidders must submit Bids encompassing the entire Project, inclusive of the related Plans, Specifications, related construction drawings and Reference Documents. Failure to do so may result in a determination that the Bid is non-responsive.
In addition to other provisions required by the City, the Consultant shall comply with the following provisions, as applicable.
THE WORK SHALL BE DONE IN ACCORDANCE WITH THE MOST CURRENT EDITION(S) OF THE FOLLOWING SPECIFICATIONS AND PLANS. SHOULD TWO OR MORE OF THESE REQUIREMENTS CONFLICT, THE MORE RESTRICTIVE OPTION AS DETERMINED BY THE ENGINEER SHALL GOVERN.
The Work included in this Project consists of of the installation of a new 12-inch sanitary sewer, including PVC sewer piping, precast composite polymer manholes, bypass pumping, sewer stub-outs, asphalt concrete pavement removal and replacement, striping and marking, sewer pipe and manhole abandonment/removal, temporary traffic control, and all incidental items to complete the work.. The City is issuing this IFB to secure a qualified and licensed A General Engineering or KA Dual Engineering Contractor to perform the Work and provide Materials as more particularly described in the Special Provisions attached to this IFB, and incorporated herein by reference. Bidders must submit Bids encompassing the entire Project, inclusive of the related Plans, Specifications, related construction drawings and Reference Documents. Failure to do so may result in a determination that the Bid is non-responsive.
Site Location: Along Dysart Road from Harrison Eliseo C Felix Way alignment, just north of Agua Fria River embankment to Harrison Drive and, Along Harrison Drive from Dysart Road to 7th Street..
The Contractor shall perform the Work required in conformance with MAG Specifications and the MAG Supplement, each of which is incorporated herein by reference. In the event of a conflict between the MAG Specifications and the MAG Supplement, the MAG Supplement shall prevail. The Contractor shall also perform the Work in accordance with the Reference Documents.
Vendor must be registered on System for Award Management (“Sam.gov”) before submitting an offer, provide a valid Unique Entity Identifier Number and continue to maintain an active SAM registration during which it has an active Federal award.” The Unique Entity Identifier Number must be entered on the Offer page.
Except as set forth in Article III of this IFB in the section titled "Contract Amendments", no alteration may be made to this IFB or the resultant Contract without the express, written approval of the City in the form of an official IFB addendum or Contract amendment. Any attempt to alter this IFB/Contract without such approval is a violation of this IFB/Contract and the City Procurement Code. Any such action is subject to the legal and contractual remedies available to the City including, but not limited to, Contract cancellation and suspension and/or debarment of the Bidder or Contractor.
See section "Attachments" for Technical Specifications, Plans & Reports.
The successful Contractor is responsible to download and print Plans and Specifications for this Project available at the following website: https://www.avondaleaz.gov/government/departments/finance-budget/procurement
Bidders are invited to participate in the competitive bidding process for the Project specified in this IFB. Bidders shall review their Bid submissions to ensure the following requirements are met.
The Contract Time for this Project shall be thirty (30) weeks from the Notice to Proceed. All Work on the Project shall be completed on or before the expiration of the Contract Time.
Affirmative steps must include:
Within 30 Days of the issuance of the Notice of Award, the Contractor shall attend a pre-construction conference. The City will contact the Contractor to schedule a specific date, time and location for the pre-construction conference. The purpose of this conference is to outline specific items and procedures and to address items that require special attention on the part of the Contractor. The Contractor may also present proposed variations in procedures that the Contractor believes may (A) improve the Project, (B) reduce cost or (C) reduce inconvenience to the public. Any necessary coordination and procedures for construction inspection and staking will be addressed during the pre-construction conference. The Contractor will be required to provide the following items at, or prior to, the pre-construction conference, each of which is subject to review and approval by the Engineer:
(24 CFR 75 is applicable to HUD-funded projects awarded ON or AFTER to November 30, 2020)
Insertion in all contracts and sub-contracts funded with Community Development Block Grant (CDBG) dollars when the CDBG Award to the Grantee is greater than $200,000 and the CDBG Project includes Construction and/or Demolition Activities**:
1. Section 3 of the Housing and Urban Development Act of 1968: The work to be performed under this contract is subject to the requirements of Section 3 of the Housing and Urban Development Act of 1968, as amended, 12 U.S.C.1701u (Section 3). The purpose of Section 3 is to ensure that employment and other economic opportunities generated by the U.S. Department of Housing and Urban Development (HUD) assistance or HUD-assisted projects covered by Section 3, shall, to the greatest extent feasible, be directed to low- and very low-income persons, particularly persons who are recipients of HUD assistance for housing.
2. Contractor Certification of Compliance: The parties to this contract agree to comply with HUD's regulations in 24 CFR 75, which implement Section 3. As evidenced by their execution of this contract, the parties to this contract certify that they are under no contractual or other impediment that would prevent them from complying with the 24 CFR 75 regulations.
3. Contract Language Requirement: The contractor agrees to include this Section 3 Contract Requirements clause in every sub-contract subject to compliance with regulations in 24 CFR 75, and agrees to take appropriate action, as provided in an applicable provision of the sub-contractor in this Section 3 Contract Requirements clause, upon a finding that the sub-contractor is in violation of the regulations in 24 CFR 75. The contractor will not sub-contract with any subcontractor where the contractor has notice or knowledge that the sub-contractor has been found in violation of the regulations in 24 CFR 75.
4. Contracting Requirements: To the greatest extent feasible, and consistent with existing Federal, state, and local laws and regulations, the CDBG Grantee and contractors and sub-contractors for the CDBG project shall ensure contracts and sub-contracts for work awarded in connection with the project are awarded to business concerns that provide economic opportunities to Section 3 Workers; and where feasible in the following order of priority: (1) Section 3 Business concerns that provide economic opportunities to Section 3 Workers residing within the metropolitan area (or nonmetropolitan county) in which the HUD funded assistance is provided/in which the HUD funded/CDBG project is occurring; and (2) YouthBuild programs.
5. Employment and Training Requirements: To the greatest extent feasible, and consistent with existing Federal, state, and local laws and regulations, the CDBG Grantee and contractors and sub-contractors for the CDBG project shall ensure employment and training opportunities generated in connection with the project are filled by Section 3 Workers; and where feasible, in the following order of priority: (1) low- and very low-income persons residing within the metropolitan area (or nonmetropolitan county) in which the CDBG assistance is expended (i.e., in which the CDBG project is occurring); and (2) participants in YouthBuild programs.
6. Section 3 Definitions [24 CRF 75]: Definitions for Section 3 terms per 24 CFR 75 are as follows: Section 3 Worker: An employee who currently fits (if hired more than five (5) years before starting work on the CDBG project), or fit at the time of hire (if hired within five (5) years of starting work on the CDBG project), at least one (1) of the following categories: (1) is employed by a Section 3 Business concern; or (2) is a low- or very low-income resident (i.e., a local person living within the Section 3 service area as defined in 24 CFR 75.5, with an individual annualized income at the time of hire (if hired within five (5) years of starting work on the CDBG project), or currently as of date of starting work on the project (if hired more than five (5) years before starting work on the CDBG project) that was/is at or below the low income (80%) threshold established by HUD for a Family of 1 for the county in which the person lives) [Note: The HUD income threshold must be from the HUD Income Limits for the CDBG program that are in effect at the time of hire (if hired within five (5) years of starting work on the CDBG project), or currently in effect as of the date the worker started work on the CDBG project (if hired more than five (5) years prior to starting work on the CDBG project). The HUD Income Limits are updated annually, typically in March or April.]; or (3) is a YouthBuild participant. Targeted Section 3 Worker: An employee who is employed by a Section 3 Business concern; or who currently fits (or when hired fit) at least one (1) of the following categories as documented within the past five (5) years: (1) lives/lived within the Section 3 service area or the neighborhood of the CDBG project as defined in 24 CFR 75.5; or (2) is a YouthBuild participant. Section 3 Business concern: A business that fits at least one (1) of the following categories: (1) 51% or more owned by low- or very low-income persons; or (2) 75% or more of the labor hours are performed by low- or very low-income persons; or (3) 51% or more owned by current residents of public housing or Section 8-assisted housing. Section 3 Service Area: An area within one (1) mile of the CDBG project’s location (i.e., street address); or an area within a circle centered around the CDBG project site that encompasses 5,000 people [if less than 5,000 people live within a one (1) mile radius of the CDBG project site].
7. Reporting Labor Hours: CDBG Grantee and contractors and sub-contractors for the CDBG project shall report all worker (see exception on next page)* labor hours on the project as follows: (1) the total number of labor hours worked; (2) the total number of labor hours worked by Section 3 Workers; and (3) the total number of labor hours worked by Targeted Section 3 Workers. The labor hours reported shall include the total number of labor hours worked on the financially assisted project by workers employed by the CDBG Grantee, and employed by their contractors and sub-contractors, during the reporting period specified by HUD and the State CDBG Program. The labor hours reported may be based on the employer's good faith assessment of the labor hours of a full-time or part-time employee informed by the employer's existing salary or time and attendance based payroll systems, unless the project or activity is otherwise subject to requirements specifying time and attendance reporting. [Note: Construction contractors required to maintain certified payroll records to meet federal labor standards requirements shall report actual work hours as reported on the certified payroll records.] *Exception for positions that require an advanced degree or professional certification: Reporting of hours for positions requiring an advanced degree or professional certification is not required, but the hours may be reported to demonstrate Section 3 “best efforts”. The CDBG Grantee, contractors and sub-contractors may report the labor hours by Section 3 Workers and Targeted Section 3 Workers without including labor hours from employees in positions requiring an advanced degree or professional certification in the total number of labor hours worked, but if the contract covers both work requiring an advanced degree or professional certification and other work, the labor hours for the other work under the contract that are not from employees in positions requiring an advanced degree or professional certification must still be reported.
8. Section 3 Benchmarks: The HUD Section 3 Final Rule (24 CFR 75) establishes “safe harbor” benchmarks that are quantitative benchmarks and prioritized qualitative efforts that funding recipients must complete to assist low- and very low-income persons with employment and training opportunities: (1) 25% or more of all labor hours worked must be worked by Section 3 Workers; and (2) 5% or more of all labor hours worked must be worked by Targeted Section 3 Workers. If the “safe harbor” benchmarks are not met over the course of the project, then the CDBG Grantee and contractors and sub-contractors for the CDBG project shall provide evidence of completing qualitative efforts to assist low and very low-income persons with employment and training opportunities. Supporting documentation of these completed efforts must also be maintained in the CDBG Grantee’s and contractors’ CDBG project files, to be made available upon request for monitoring purposes.
9. Demonstrating Best Efforts: When the Section 3 benchmarks are not met, the CDBG Grantee and contractors and sub-contractors for the CDBG project shall demonstrate and report qualitative efforts made in an attempt to meet the benchmarks, which may include but are not limited to the following:
(1) Engage in outreach efforts to generate job applicants who are Targeted Section 3 Workers.
(2) Provide training or apprenticeship opportunities.
(3) Provide technical assistance to help Section 3 Workers compete for jobs (e.g., resume assistance, coaching).
(4) Provide or connect Section 3 Workers with assistance in seeking employment including: drafting resumes, preparing for interviews, and finding job opportunities connecting residents to job placement services.
(5) Hold one or more job fairs.
(6) Provide or refer Section 3 Workers to services supporting work readiness and retention (e.g., work readiness activities, interview clothing, test fees, transportation, child care).
(7) Provide assistance to Section 3 Workers to apply for/or attend community college, a four-year educational institution, or vocational/technical training.
(8) Assist Section 3 Workers to obtain financial literacy training and/or coaching.
(9) Engage in outreach efforts to identify and secure bids from Section 3 Business concerns.
(10) Provide technical assistance to help Section 3 Business concerns understand and bid on contracts.
(11) Divide contracts into smaller jobs to facilitate participation by Section 3 Business concerns.
(12) Provide bonding assistance, guaranties, or other efforts to support viable bids from Section 3 Business concerns.
(13) Promote use of business registries designed to create opportunities for disadvantaged and small businesses.
(14) Conduct outreach, engagement, or referrals with the state one-stop system as defined in Section 121(e)(2) of the Workforce Innovation and Opportunity Act.
10. Recordkeeping & Reporting: The CDBG Grantee and contractors and sub-contractors for the CDBG project shall maintain all records demonstrating compliance with 24 CFR 75, including contracting information and documents, worker income certifications (for Section 3 Worker status determinations), and worker labor hours on CDBG project; and provide data and reporting documents as requested and required by the State CDBG Program and/or HUD. Grantee and contractor records may be monitored for compliance by the State CDBG Program and/or HUD. Contractor and all subcontractors will be required to complete an Employer/Employee Section 3 Certification Form and a Section 3 Labor Hours Tracking form.
11. Non-Compliance: Non-compliance with HUD's regulations in 24 CFR 75 may result in sanctions, termination of this contract for default, and debarment or suspension from future HUD assisted contracts.
12. Indian Housing Assistance Project Specifications: With respect to work performed in connection with Section 3 covered Indian housing assistance, Section 7(b) of the Indian Self-Determination and Education Assistance Act (25 U.S.C. 450e) also applies to the work to be performed under this contract. Section 7(b) requires that to the greatest extent feasible: (i) preference and opportunities for training and employment shall be given to Indians; and (ii) preference in the award of contracts and sub-contracts shall be given to Indian organizations and Indian-Owned Economic Enterprises. Parties to this contract that are subject to the provisions of Section 3 and Section 7(b) agree to comply with Section 3 to the maximum extent feasible, but not in derogation of compliance with section 7(b).
** This language is required to be included in contracts and sub-contracts for a HUD funded project that are funded in whole or in part with the federal dollars, and the CDBG/HUD Funded Award to the Grantee is greater than $200,000 and awarded 11/30/2020 or later, and the CDBG/HUD Funded Project includes construction (including building/structural rehabilitation) and/or demolition activities. CDBG projects awarded on or after 11/30/2020, for which the CDBG/HUD funded Award is less than $200,000 and/or for which Planning, Public Services, or Financial Assistance (e.g., loans for economic development) are the only activities, with no construction and no demolition in the project scope of work, are not subject to these Section 3 requirements and reporting. Insertion of this Section 3 Clause is strongly recommended to be included in ALL contracts and sub-contracts for a HUD funded project that is subject to Section 3 requirements, regardless of the funding source for the specific contract, to help avoid issues with compliance and reporting later in the project cycle if the funding source changes. All subcontractors of a prime contractor that is funded in whole or in part with CDBG/HUD funding are subject to the same Section 3 requirements as the prime contractor.
A Prospective Bidders’ Conference may be held. If scheduled, the date and time of the Prospective Bidders’ Conference will be indicated in the timeline of this IFB. The Prospective Bidders’ Conference may be designated as mandatory or non-mandatory in the timeline of this IFB. Bids shall not be accepted from Bidders who do not attend a mandatory Prospective Bidders’ Conference. Bidders are strongly encouraged to attend those Prospective Bidder’s Conferences designated as non-mandatory. The purpose of the Prospective Bidders’ Conference will be to clarify the contents of the IFB in order to prevent any misunderstanding of the City’s requirements. Any doubt as to the requirements of this IFB or any apparent omission or discrepancy should be presented to the City at the Prospective Bidders’ Conference. The City will then determine if any action is necessary and may issue a written amendment or addendum to the IFB. Oral statements or instructions will not constitute an amendment or addendum to the IFB.
Within 45 Days of the issuance of the Notice of Award the City may issue a written Notice to Proceed. The Notice to Proceed shall stipulate the actual Contract start date, the Contract Time and the dates of Substantial Completion and Final Completion. The time required for the Contractor to obtain permits, licenses and easements shall be included in the Contract Time and shall not be justification for a delay claim by the Contractor. The time required for the Contractor to prepare, transmit and obtain approval of applicable submittals shall be included in the Contract Time and shall not be justification for a delay claim by the Contractor. No Work shall be started until after all required permits, licenses, and easements have been obtained. The Contractor shall notify the Engineer, in writing, at least 72 hours before the following events:
In addition to other provisions required by the City, the Contractor shall comply with the following provisions, as applicable.
Recipients of an award of Federal financial assistance from a program for infrastructure are hereby notified that none of the funds provided under this award may be used for a project for infrastructure unless:
All subcontracts must contain the following language: The Grantee must comply with the requirements of the Build America, Buy America (BABA) Act, 41 USC 8301 note, and all applicable rules and notices, as may be amended, if applicable to the Grantee’s infrastructure project. Pursuant to HUD’s Notice, “Public Interest Phased Implementation Waiver for FY 2022 and 2023 of Build America, Buy America Provisions as Applied to Recipients of HUD Federal Financial Assistance” (88 FR 17001), any funds obligated by HUD on or after the applicable listed effective dates, are subject to BABA requirements, unless excepted by a waiver.
The Buy America preference only applies to articles, materials, and supplies that are consumed in, incorporated into, or affixed to an infrastructure project. As such, it does not apply to tools, equipment, and supplies, such as temporary scaffolding, brought to the construction site and removed at or before the completion of the infrastructure project. Nor does a Buy America preference apply to equipment and furnishings, such as movable chairs, desks, and portable computer equipment, that are used at or within the finished infrastructure project, but are not an integral part of the structure or permanently affixed to the infrastructure project.
Waivers
When necessary, recipients may apply for, and the agency may grant, a waiver from these requirements. The agency should notify the recipient for information on the process for requesting a waiver from these requirements.
A request to waive the application of the domestic content procurement preference must be in writing. The agency will provide instructions on the format, contents, and supporting materials required for any waiver request. Waiver requests are subject to public comment periods of no less than 15 days and must be reviewed by the Made in America Office.
There may be instances where an award qualifies, in whole or in part, for an existing waiver described at [link to awarding agency web site with information on currently applicable general applicability waivers].
Definitions[2]
“Construction materials” includes an article, material, or supply—other than an item of primarily iron or steel; a manufactured product; cement and cementitious materials; aggregates such as stone, sand, or gravel; or aggregate binding agents or additives[3]—that is or consists primarily of:
“Domestic content procurement preference’’ means all iron and steel used in the project are produced in the United States; the manufactured products used in the project are produced in the United States; or the construction materials used in the project are produced in the United States.
“Infrastructure” includes, at a minimum, the structures, facilities, and equipment for, in the United States, roads, highways, and bridges; public transportation; dams, ports, harbors, and other maritime facilities; intercity passenger and freight railroads; freight and intermodal facilities; airports; water systems, including drinking water and wastewater systems; electrical transmission facilities and systems; utilities; broadband infrastructure; and buildings and real property. Infrastructure includes facilities that generate, transport, and distribute energy.
‘‘Project’’ means the construction, alteration, maintenance, or repair of infrastructure in the United States.
[2] Federal agencies may choose to provide definitions on a public-facing website and reference that website in the terms and conditions, rather than including all definitions in the terms and conditions itself. If an agency chooses to do provide definitions on a public-facing website, it is not considered a deviation from the terms and conditions provided and does not need to be reviewed by OMB.
[3] IIJA, § 70917(c)(1).
[1] Excludes cement and cementitious materials, aggregates such as stone, sand, or gravel, or aggregate binding agents or additives.
All Materials to be provided by the Contractor and included in the Bid shall be new, unless otherwise stated in the Specifications.
The Contractor shall keep fully informed of all rules, regulations, ordinances, statutes or laws affecting the Work herein specified, including existing and future (A) City and County ordinances and regulations, (B) State and Federal laws and (C) Occupational Safety and Health Administration (“OSHA”) standards.
https://www.ecfr.gov/current/title-29/section-1926.62 This section applies to all construction work where an employee may be occupationally exposed to lead.
It is the policy of the City that suppliers of goods or services to the City adhere to a policy of equal employment opportunity and demonstrate an affirmative effort to recruit, hire, and promote regardless of race, color, religion, gender, national origin, age or disability. On any Contract in excess of six months, the Contractor shall provide an annual report to the Engineer highlighting its activities to comply with this Section.
Work shall be performed at the unit prices as set forth in the electronic pricing table on the City's OpenGov portal and incorporated herein by reference. Bid prices shall be submitted on a per unit basis by line item, when applicable. Transaction privilege tax, sales tax and use tax should be entered as a separate line. In the event of a disparity between the unit price and extended price, the unit price shall prevail. NOTE: All unit prices must be filled in. Unless a "No Bid" option has been provided and selected, empty or unfilled spaces for pricing shall result in a determination that a Bid is non-responsive.
The Contractor shall obtain a right-of-way permit for any of the Work completed in the public right-of-way. The Contractor will be responsible for any required Maricopa County permits or other agency permits. The City will provide any necessary easements for Work specified under this Contract, and the Contractor shall not enter or occupy with workers, tools, equipment or materials any private ground outside the property of the City without the written consent of the owner thereof. The Contractor, at its own expense, is responsible for the acquisition of any additional easements or rights-of-way.
Any Bid that requires payment in less than 30 Days shall not be considered. Payment discounts of 30 Days or less will not be deducted from the Bid Price in determining the low Bid. The City shall be entitled to take advantage of any payment discount offered, provided payment is made within the discount period. Payment discounts shall be indicated on Price Sheet.
Each Contractor must inform itself fully of the conditions relating to the construction of the Project and the employment of labor thereon. Failure to do so will not relieve the Contractor of its obligation to furnish all material and labor necessary to carry out the provisions of this Contract. Insofar as possible in carrying out its work, the Contractor must employ such methods or means as will not cause any interruption of or interference with the Work of any other contractor. Contractor affirms that it has inspected the jobsite and has thoroughly reviewed this Contract including, without limitation, the Specifications attached to this IFB as the same may be revised by the City, and is not relying on any opinions or representations of City. Contractor agrees to perform and complete such Work in strict accordance with this Contract and under the general direction of the City. Contractor agrees that any exclusions of any Work must be approved in writing by the City prior to acceptance of this Contract or same shall not be excluded hereunder. Contractor shall provide all competent supervision necessary to execute all Work and any Work incidental thereto in a thorough, first-class, workmanlike manner. It is Contractor’s responsibility that all of the Work and any Work incidental thereto conforms to, and is performed in accordance with, all applicable Federal, State, County and City laws, codes, ordinances, regulations (including National Pollutant Discharge Elimination System and air pollution standards) and orders of public authorities bearing on performance of the Work.
The City is exempt from Federal Excise Tax, including the Federal Transportation Tax. Please be advised that ARIZ. REV. STAT. § 42-5075(P) applies to the Project contemplated within this Contract. Transaction privilege tax, sales tax and use tax, if any, shall be entered as a separate line. It shall not be considered a lump sum payment item. Bidder should not include tax on any allowances. It is the sole responsibility of the Bidder to determine any applicable tax rates and calculate the tax accordingly. Failure to accurately tabulate any applicable taxes may result in a determination that a Bid is non-responsive. The Bidder shall not rely on, and shall independently verify, any tax information provided by the City.
Contractor is responsible for all safety precautions and programs and shall perform the Work in accordance with a safety plan that is compliant with OSHA, American National Standards Institute and National Institute for Occupational Safety and Health standards. Contractor shall provide all protection and necessary supervision to implement said safety plan. Contractor shall take all reasonable precautions for the safety of and provide reasonable protection to prevent damage, injury or loss to: (A) employees or others on the Project, (B) the Work and materials and (C) other property at the Project or adjacent thereto. Contractor shall designate a responsible person on the Project whose duty shall be prevention of accidents.
All traffic affected by the Work under this Contract shall be regulated in accordance with the then-current version of the City of Phoenix-Traffic Barricade Manual (the “Barricade Manual”) which is incorporated herein by reference; provided, however, that this Contract shall govern in a conflict with the terms of the Barricade Manual. At the time of the pre-construction conference, the Contractor shall designate an employee who is well qualified and experienced in construction traffic control and safety to be responsible for implementing, monitoring and altering traffic control measures, as necessary. At the same time, the City will designate a representative who will be responsible to see that all traffic control and any alterations are implemented and monitored to the extent that traffic is carried through the Work area in an effective manner and that motorists, pedestrians, bicyclists and workers are protected from hazard and accidents.
It is the responsibility of the Bidder to verify and comply with federal requirements that may apply to the Work (the “Federal Requirements”). It is also the responsibility of the Bidder to incorporate any necessary amounts in the Bid to accommodate for required federal record-keeping, necessary pay structures or other matters related to the Federal Requirements. Federal Requirements, if any, shall be attached to this IFB. In addition to any applicable Federal Requirements, this procurement is subject to a number of state and City regulations. In general, where these rules conflict, the more stringent law or rule applies.
To the fullest extent permitted by law, the Contractor shall indemnify and hold harmless the City and each council member, officer, employee or agent thereof (the City and any such person being herein called an “Indemnified Party”), for, from and against any and all losses, claims, damages, liabilities, costs and expenses (including, but not limited to, reasonable attorneys’ fees, court costs and the costs of appellate proceedings) to which any such Indemnified Party may become subject, under any theory of liability whatsoever (“Claims”) to the extent that such Claims (or actions in respect thereof) are caused by the negligent acts, recklessness or intentional misconduct of the Contractor, its officers, employees, agents, or any tier of subcontractor in connection with Contractor’s work or services in the performance of this Agreement. The amount and type of insurance coverage requirements set forth below will in no way be construed as limiting the scope of the indemnity in this Section.
Bids submitted for consideration should be prepared simply and economically, providing adequate information in a straightforward and concise manner. The City does not reimburse the cost of developing, presenting or providing any response to this solicitation; the Bidder is responsible for all costs incurred in responding to this IFB. All materials and documents submitted in response to this IFB become the property of the City and will not be returned.
Before any contract is executed by the City, the Contractor shall be required to furnish non-revocable security binding the Contractor to provide faithful performance of this Contract in the amount of one hundred percent (100%) of the total Contract Price payable to the City. Performance security shall be in the form of a performance bond, certified check, cashier’s check or irrevocable letter of credit. The Contractor shall furnish the performance bond to Procurement Administrator ten (10) days after receipt of Notice of Intent to Award. If the Contractor fails to execute and deliver the security instrument as required, the Contractor may be deemed non-responsible and City shall not execute the contract. The required performance bonds must be submitted using the form provided in the Downloads/Attachments section, duly executed by the Contractor as Principal and having as Surety thereon a Surety company approved by the City and holding a Certificate of Authority to transact surety business in the State of Arizona by the Arizona Department of Insurance. Individual sureties are unacceptable. All Insurers and Sureties shall have, at the time of submission of the performance bond, an A.M. Best’s Key Rating Guide of “A-” or better as currently listed in the most recent Best Key Guide, published by the A.M. Best Company.
Before any contract is executed by the City, the Contractor shall be required to furnish non-revocable security for the protection of all persons supplying labor and material to the Contractor or any Subcontractor for the performance of any Work related to this Contract. Payment security shall be in the amount of one hundred percent (100%) of the total Contract Price and be payable to the City. Payment security shall be in the form of a payment bond, certified check, cashier’s check or irrevocable letter of credit. The Contractor shall furnish the payment bond to Procurement Administrator ten (10) days after receipt of Notice of Intent to Award. If the Contractor fails to execute and deliver the security instrument as required, the Contractor may be deemed non-responsible, and City shall not execute the contract. The required payment bonds must be submitted using the form provided in the Downloads/Attachments section, duly executed by the Contractor as Principal and having as Surety thereon a Surety company approved by the City and holding a Certificate of Authority to transact surety business in the State of Arizona by the Arizona Department of Insurance. Individual sureties are unacceptable. All Insurers and Sureties shall have, at the time of submission of the payment bond, an A.M. Best’s Key Rating Guide of “A-” or better as currently listed in the most recent Best Key Guide, published by the A.M. Best Company.
All Bids shall become the property of the City. After Contract award, Bids shall become public records and shall be available for public inspection in accordance with the City’s Procurement Code, except that any portion of a Bid that was designated as confidential pursuant to the "Confidential Information" Section of this IFB shall remain confidential from and after the time of Bid opening to the extent permitted by Arizona law.
If a Vendor/Bidder believes that a Bid, Specification, or protest contains information that should be withheld from the public record, a statement advising the Procurement Agent of this fact shall accompany the submission and the information shall be clearly identified. The information identified by the Vendor or Bidder as confidential shall not be disclosed until the Procurement Agent makes a written determination. The Procurement Agent shall review the statement and information with the City Attorney and shall determine in writing whether the information shall be withheld. If the City Attorney determines that it is proper to disclose the information, the Procurement Agent shall inform the Vendor or Bidder in writing of such determination.
The City may, without invalidating this Contract, order changes in the Work consisting of additions, deletions or other revisions to this Contract and the Contract Price and the Contract Time shall be adjusted as provided below. The Contract Price and/or the Contract Time may only be changed by the City’s written approval authorizing said change, and said changes shall be performed under the applicable conditions of this Contract. The Contract Price shall be adjusted as a result of a change in the Work as follows:
When the Contractor considers that the Work is Substantially Complete, the Engineer shall prepare and submit to the Contractor a comprehensive list of Punch List items, which the Contractor may edit and supplement. The Contractor shall proceed promptly to complete and correct Punch List items. Failure to include an item on the Punch List does not alter the responsibility of the Contractor to complete all Work in accordance with the Contract Documents. The City shall determine when the Project and the Contractor’s Work is substantially complete. “Substantial Completion” means construction has been completed in accordance with the Contract Documents to the extent that the City can use or occupy the entire Project, or the designated portion of the Project, for the use intended without any outstanding, concurrent construction at the site, except as may be required to complete or correct Punch List items. A prerequisite for Substantial Completion, over and above the extent of construction completion required, is receipt by the City of acceptable documentation that Contractor has successfully tested and demonstrated all systems for their intended use. The date of Substantial Completion shall be confirmed by a Certificate of Substantial Completion signed by the City and Contractor. The Certificate of Substantial Completion signed by the City and Contractor shall state the respective responsibilities of the City and the Contractor for security, maintenance, utilities, damage to the Work and insurance. The Certificate of Substantial Completion shall also include the Punch List as created by the Contractor and modified by the City and establish the time for completion and correction of all Punch List items. If the City and the Contractor cannot agree as to the appropriate date of Substantial Completion, such issue shall be submitted for dispute resolution in accordance with the procedures set forth in Article III, Part B below. Notwithstanding such disagreement, the Contractor shall diligently proceed with completion of the Punch List items.
Prior to the award of the Contract, the successful Bidder shall (A) be registered with the Arizona Corporation Commission and authorized to do business in Arizona and (B) have a completed Vendor Registration Packet on file with the City Finance and Budget Department. Bidders shall provide license and certification information with the Bid. Upon the City’s request, corporations and limited liability companies shall provide Certificates of Good Standing from the Arizona Corporation Commission.
The City shall determine when the Project and the Contractor’s Work is finally completed. “Final Completion” means completion of the Project by the Contractor in accordance with the Contract Documents, certified to the City by the Contractor. Final Completion shall be achieved only upon the City’s written acceptance of (A) the construction, (B) all testing, (C) demonstration by Contractor that the Work functions as required by the Contract Documents and meets all Contract requirements, (D) resolution of all outstanding system deficiencies and Punch List items, if any, (E) delivery of all as-built documentation, drawings, completed record documents (with revisions made after Substantial Completion), annotated submittals and design document deliverables, (F) submittal, acceptance, and delivery of the one hundred percent (100%) complete O&M manuals, (G) delivery of warranties, inspection certificates, bonds and all other required documents, (H) all pre-requisites for final payment and (I) submittal of Contractor’s request for final payment and acceptance enclosing all required documentation. Upon Final Completion the Engineer shall issue a Certificate of Final Completion to the Contractor on behalf of the City. Following receipt of payment from the City, the Contractor shall make all payments due to the Subcontractors.
Payment shall be conditioned upon Contractor’s compliance with the payment terms and conditions set forth below. Contractor expressly acknowledges and agrees that (A) the Contract Price is an estimated amount based upon an engineer’s estimate of the quantities of the Materials deemed necessary to perform the Work and (B) the amount of any payment to be made pursuant to this Contract shall be determined by the field-measured quantities of Materials actually installed by Contractor. Material or equipment delivered to the Project by or on behalf of Contractor shall not constitute material or equipment furnished in the performance of the Work until same has been incorporated into the improvements constituting the Project. Payment shall not constitute acceptance by the City or evidence thereof of any Work performed.
By submitting a Bid, the Bidder certifies:
[END OF PART A]
PART B - PERFORMANCE OF THE WORK
All Vendors desiring to prepare a responsive Bid shall submit a non-revocable bid security payable to the City in the amount of ten percent (10%) of the total Bid Price. This security shall be in the form of a bid bond, certified check or cashier’s check and must be in the possession of the City Representative by the Bid Deadline. All bid security from Contractor(s) who have been issued a Notice of Award shall be held until the successful execution of all required Contract Documents and bonds. If the Contractor fails to execute the required contractual documents and bonds within the time specified, or 10 Days after Notice of Award if no period is specified, the Contractor may be found to be in default and this Contract terminated by the City. In case of default, the City reserves all rights inclusive of, but not limited to, the right to purchase material and/or to complete the Work and to recover any actual excess costs associated with such completion from the Contractor. All bid bonds shall be executed in the form attached to this IFB in the Vendor Questionnaire, duly executed by the Bidder as Principal and having as Surety thereon a Surety company holding a Certificate of Authority from the Arizona Department of Insurance to transact surety business in the State of Arizona. Individual sureties are unacceptable. All insurers and sureties shall have, at the time of submission of the proposal, an A.M. Best’s Key Rating Guide of “A-” or better as currently listed in the most recent Best Key Guide, published by the A.M. Best Company. As soon as is practicable after the completion of the evaluation, the City will (A) issue a Notice of Award for those Offers accepted by the City and (B) return all checks or bonds to those Bidders who have not been issued a Notice of Award.
The Contractor shall produce and provide a project videotape to the Engineer as required by MAG Supplement Section 105.5.3. All costs associated with the Project videotape produced in accordance with this Section shall be deemed incidental.
In addition to conformance to MAG Specifications, Section 102.4 (Examination of Plans, Special Provisions and Site Work), the Contractor shall make its own determinations as to the soil and subsurface conditions, including rock, caliche and ground water and shall complete the Work in whatever material and under whatever conditions may be encountered or created, without extra cost to the City pursuant to the provisions of the MAG Supplement Section 102.4.1.
Time is of the essence for this Contract. Contractor shall provide the Engineer with any requested scheduling information and a proposed schedule for performance of the Work within the Contract Time in a form acceptable to the Engineer and approved by the Engineer, in his sole and absolute discretion, providing for commencement and completion of the Work (the “Schedule”). The Schedule shall include the date for Substantial Completion of the Work. The Engineer may revise the Schedule during the course of the Work. Contractor, to induce the City to enter into this Contract, has and does hereby agree to fully perform and complete the Work for the Contract Price within the Schedule.
The Contractor or his authorized representative shall be present at the Work site at all times during working hours. Instructions and information provided by the Engineer to the Contractor’s representative shall be considered as having been given to the Contractor, per MAG Supplement Section 105.5.2.
The Contractor shall prosecute the Work so that the portion of the Work completed at any point in time shall be not less than as required by the Schedule. If the delay is an Inexcusable Delay, as defined below, the Contractor shall prepare a recovery schedule for the Engineer’s review and approval, showing how the Contractor will compensate for the delays and achieve Substantial Completion by the date(s) shown on the Schedule. If the Contractor is unable to demonstrate how it will overcome Inexcusable Delays, the Engineer may order the Contractor to employ such extraordinary measures as are necessary to bring the Work into conformity with the Substantial Completion date(s) set forth therein, the costs of which shall be included as part of the Cost of the Work. If the delay is an Excusable Delay, as defined below, the Engineer shall either (A) authorize an equitable extension in the Schedule to account for such delay, and equitably adjust the contract sum on account of such delay or (B) request that the Contractor prepare a recovery schedule showing how (if possible) the Contractor can achieve Substantial Completion by the applicable date shown on the Schedule, and equitably adjust the Contract Price in accordance with the provisions of this Contract on account of any extraordinary activities required of the Contractor on account of such recovery schedule.
It is expressly understood that should Contractor fail to complete the Work covered hereby within the Contract Time, the Contractor agrees to pay and shall pay to the City upon request therefore for each Day of delay beyond the original or revised scheduled time of completion of Contractor’s Work as liquidated damages, and not as a penalty, in the amount per day as set forth in MAG Specifications for each Day of delay.
The City may, upon 30 Days’ written notice to the Contractor, terminate this Contract, in whole or in part, for the convenience of the City without prejudice to any right or remedy otherwise available to the City. Upon receipt of such notice, the Contractor shall immediately discontinue all Services affected unless such notice directs otherwise. In the event of a termination for convenience of the City, the Contractor’s sole and exclusive right and remedy shall be payment for all Work performed through the date of termination. The Contractor shall not be entitled to be paid any amount as profit for unperformed Services or consideration for the City’s termination by convenience.
The City is obligated only to pay its obligations set forth in this Agreement as may lawfully be made from funds appropriated and budgeted for that purpose during the City’s then current fiscal year. The City’s obligations under this Agreement are current expenses subject to the “budget law” and the unfettered legislative discretion of the City concerning budgeted purposes and appropriation of funds. Should the City elect not to appropriate and budget funds to pay its Agreement obligations, this Agreement shall be deemed terminated at the end of the then-current fiscal year term for which such funds were appropriated and budgeted for such purpose and the City shall be relieved of any subsequent obligation under this Agreement. The parties agree that the City has no obligation or duty of good faith to budget or appropriate the payment of the City’s obligations set forth in this Agreement in any budget in any fiscal year other than the fiscal year in which this Agreement is executed and delivered. The City shall be the sole judge and authority in determining the availability of funds for its obligations under this Agreement. The City shall keep Contractor informed as to the availability of funds for this Agreement. The obligation of the City to make any payment pursuant to this Agreement is not a general obligation or indebtedness of the City. Contractor hereby waives any and all rights to bring any claim against the City from or relating in any way to the City's termination of this Agreement pursuant to this section.
Contractor expressly agrees that if overtime or additional workers or materials are necessary to meet the Schedule, that such overtime will be performed or additional workers or materials will be procured by the Contractor, and the additional expense thereof shall be borne by Contractor unless the delay requiring overtime was directly caused by the City, in which event Contractor shall be entitled to compensation for such overtime Work. If the City requests Contractor to perform additional Work in connection with the Project (“Additional Work”), Contractor shall charge the City a negotiated fixed amount for the Additional Work. In the event a fixed amount cannot be negotiated, Contractor shall invoice the City on a time and materials basis for the Additional Work at the unit prices set forth in the price sheet.
Contractor shall adjust its operations to conform to any progress schedule changes and hereby waives and releases the City from any liability for damages or expenses that may be caused to or sustained by Contractor by reason of such changes or by reason of delays in the Work, whether caused in whole or in part by conduct on the part of the City, including without limitation, any breach of this Contract or delays by other contractors or Subcontractors. Contractor’s exclusive remedy in the event of delay or Additional Work by the City shall be an extension of time hereunder to complete the Work.
Contractor shall assume the risk of loss occasioned by fire, theft or other damage to Materials, machinery, apparatus, tools and equipment relating to the Work prior to actual installation in final place on the Project and acceptance by the City. Contractor shall be responsible for damage to the Materials, machinery, apparatus, tools, equipment and property of the City and other contractors resulting from the acts or omissions of its Subcontractors, employees, agents, representatives Subcontractors, and for payment of the full costs of repair or replacement of any said damage.
The Contractor shall properly guard and protect all finished or partially finished Work and shall be responsible for the same until the entire Contract is completed and accepted by the Engineer. The Contractor shall turn over the entire Work in full accordance with this Contract before final settlement shall be made.
Only skilled foremen and workers shall be employed on portions of the Work requiring special qualifications. When required by the Engineer, the Contractor shall discharge any person who is, in the opinion of the Engineer, disorderly, dangerous, insubordinate, incompetent or otherwise objectionable. The Contractor shall indemnify and hold harmless the City from and against damages or claims for compensation that may occur in the enforcement of this Section. The Contractor shall be responsible for ensuring the legal working status of its employees and its Subcontractor’s employees. The Contractor agrees that once assigned to Work under this Contract, key personnel shall not be removed or replaced without written notice to the City. If key personnel are not available for Work under this Contract for a continuous period exceeding 30 Days, or are expected to devote substantially less effort to the Work than initially anticipated, the Contractor shall immediately notify the City and shall, subject to the concurrence of the City, replace such personnel with personnel of substantially equal ability and qualifications.
The methods, equipment and appliances used on the Work shall be such as will produce a satisfactory quality of Work, and shall be adequate to complete this Contract within the Contract Time. Except as is otherwise specified in this Contract, the Contractor’s procedure and methods of construction may, in general, be of its own choosing, provided such methods (A) follow best general practice and (B) are calculated to secure results which will satisfy the requirements of this Contract. The Work covered by this Contract shall be carefully laid out in advance and performed in a manner to minimize interference with normal operation and utilization of the City’s right-of-way. The Contractor shall exercise caution during the course of this Work to avoid damage to all known existing or possible unknown existing underground utilities. It shall conduct its operations in such a manner as to avoid injury to its personnel and to avoid damage to all utilities. Any damage done will be repaired without delay and at the expense of the Contractor.
The Contractor shall provide safety construction fencing around all open trenches and excavations during all non-working hours. In addition, the Contractor shall provide safety fencing around the Project site during working hours in order to ensure public safety. The Contractor shall provide for the safety and welfare of the general public by adequately fencing all excavations and trenches that are permitted by the Engineer to remain open when construction is not in progress. Fencing shall be securely anchored to approved steel posts located not less than six feet on center, having a minimum height of six feet, and shall consist of wire mesh fabric of sufficient weight and rigidity to adequately span a maximum supporting post separation of six feet. The fencing, when installed about the periphery of excavations and trenches, shall form an effective barrier against intrusion by the general public into areas of construction. The Contractor, at all times when construction is not in progress, shall be responsible for maintaining the fencing in good repair, and upon notification by the Engineer, shall take immediate action to rectify any deficiency. Prior to the start of any excavation or trenching required for the execution of the proposed Work, the Contractor shall submit to the Engineer for approval, detailed plans showing types of materials and methods of fabrication for the protective fencing. There will be no separate measurement or payment for furnishing, installing, or maintaining protective fencing. The cost shall be considered incidental to the cost of the pipe, bridge, and any other structures for which trenching is necessary.
All submittals shall conform to MAG Specifications, Section 105.2 (Plans and Drawings) as modified by the MAG Supplement. Contractor shall furnish, within three business days following request therefore by the City, detailed drawings of the Work, samples of Materials and other submittals required for the performance or coordination of the Work. Substitutions shall be equal or superior to Materials specified in the Contract Documents, shall be clearly identified on submittals as “proposed substitutions” and shall be approved by the City in accordance with the "Inquiries; Interpretations of Plans, Specifications and Drawings" Section of Article II of this IFB. Contractor shall be fully responsible for the adequacy, completeness and promptness of all such submittals. Materials shall not be furnished to the jobsite unless same is in strict compliance with the Specifications or otherwise approved in writing by the City. Approval by the City shall not relieve Contractor of full responsibility for compliance with scope, intent and performance in accordance with this Contract.
The Contractor shall comply with the requirements of MAG Specifications 105.6, as modified by the MAG Supplement.
Sampling and testing shall conform to the requirements of the MAG Specifications, Section 106, as modified by the MAG Supplement.
The Contractor shall comply with the requirements of MAG Specifications, Section 105.7, as modified by the MAG Supplement.
Unless otherwise permitted by the Engineer, construction will be restricted as listed in the following table:
| May 1 - October 31 | November 1 - April 30 |
| 5:00 a.m. to 7:00 p.m. | 6:00 a.m. to 7:00 p.m. |
Construction Work shall not begin Work prior to 7:00 a.m. and shall stop by 7:00 p.m. on Saturdays, Sundays and all City, State and Federal holidays.
Construction survey and as-built record drawings shall conform to the requirements of the MAG Specifications, Section 105.8 (Construction Stakes, Lines and Grades), as modified by the MAG Supplement.
Existing survey markers (either brass caps or iron pipes) shall be protected by the Contractor or removed and replaced under direct supervision of the Engineer. Survey monuments shall be constructed to the requirements of MAG Specifications, Section 405. Lot corners shall not be disturbed without knowledge and consent of the property owner. The Contractor shall replace benchmarks, monuments or lot corners moved or destroyed during construction at no expense to the City. Contractor and its sureties shall be liable for correct replacement of disturbed survey benchmarks except where the City elects to replace survey benchmarks using its own forces.
When excavations are made, resultant loose earth shall be (A) utilized for filling by compacting in place or (B) disposed of off-site. Excess or unsuitable material, broken asphaltic concrete and broken portland cement concrete excavated from the right-of-way shall be removed from the Project Site and disposed of by the Contractor. Disposal of material within the Avondale City Limits or Planning Area must be approved by the Engineer. Waste material shall not be placed on private property without express permission of the property owner. The Contractor shall, at all times, keep the premises free from accumulation of waste materials or rubbish caused by its operations. At the completion of the Work, Contractor shall remove all equipment, tools and surplus materials, and shall completely clean the premises, removing and disposing of all debris and rubbish and cleaning all stains, spots, marks, dirt, smears or other blemishes. When the Work premises are turned over to the City, they shall be thoroughly clean and ready for immediate use. Clean-up shall include removal of all excess pointing mortar materials within pipes and removal of oversized rocks and boulders left after finish grading. The Contractor shall provide for the legal disposal of all waste products and debris and shall make necessary arrangements for such disposal.
Contractor shall implement dust control measures in accordance with MAG Specifications, Section 104.1, and the MAG Supplement. Installation and removal of fire hydrant meters should be scheduled at least three business days in advance through the City Water Billing Department. Watering shall conform to the provisions of MAG Specifications, Section 225. A deposit and installation fee in amounts set forth in the City’s fee schedule is required for each meter. The cost of the water is at the prevailing rate.
The Contractor shall provide ample toilet facilities with proper enclosures for the use of workers employed on the Work site. Toilet facilities shall be installed and maintained in conformity with all applicable State and local laws, codes, regulations and ordinances and shall be properly lit and ventilated, and kept clean at all times. Adequate and satisfactory drinking water shall be provided at all times and under no circumstances and under no conditions will the use of common cups be permitted. The Contractor must supply sanitary drinking cups for the benefit of all employees.
Unless otherwise specified, the Contractor shall make its own arrangements for electric power, water and telephone. Subject to the convenience of the utility, it may be permitted to connect to existing facilities where available, but Contractor shall meter and bear the cost of such power or water, and installation and disconnect of such power, water and telephone services.
Utility companies may maintain energized aerial electrical power lines in the immediate vicinity of this Project. Contractor shall not presume any such lines to be insulated. Construction personnel working in proximity to these lines may be exposed to an extreme hazard from electrical shock. Contractor shall ensure that its employees and all other construction personnel working on this Project are warned of the danger and instructed to take adequate protective measures, including maintaining a minimum ten feet of clearance between the lines and all construction equipment and personnel. (see: OSHA Std. 1926.550 (a) 15, as amended). As an additional safety precaution, Contractor shall call the affected utility companies to arrange, if possible, to have these lines de-energized or relocated when the Work reaches their immediate vicinity. The cost of such temporary arrangements shall be borne by the Contractor. Contractor shall account for the time necessary to cause such utility disconnection in the preparation of its Bid. Electrical utility companies may maintain energized underground electrical power lines in the immediate vicinity of this Project. These power lines represent an extreme hazard of electrical shock to any construction personnel or equipment coming in contact with them. Arizona law requires all parties planning excavations in public rights-of-way to contact all utility firms for locations of their underground facilities. Contractor shall ensure that its employees and all other personnel working near any underground power lines must be warned to take adequate protective measure. (see: OSHA Std. 1926-651 (A), as amended).
Contractor shall at all times, but not less than daily unless otherwise agreed by City Representative, keep the premises on which the Work is being performed clean and free from accumulation of any waste materials, trash, debris and excess dirt, and at all times shall remove Contractor’s implements, machinery, tools, apparatus and equipment from the jobsite when not needed on the jobsite. Should the City Representative find it necessary in his/her opinion to employ help to clean up, remove or store any of the foregoing due to failure of Contractor to do so, the expense thereof shall be charged to Contractor. Verbal notice from the City Representative on clean-up or removal is considered adequate notice hereunder, and failure to conform with his/her request within 24 hours thereof will be construed as a breach of this Contract by the Contractor and such charges will be made against Contractor’s account as are necessary to accomplish the clean-up or removal. The cost of cleanup, removal or storage by the City, if not deducted by the City from monies due Contractor, shall be paid by Contractor within five business days of written demand by the City.
Contractor shall at all times comply fully with all laws, orders, citations, rules, regulations, standards and statutes with respect to occupational health and safety, the handling and storage of hazardous materials, accident prevention and safety equipment and practices, including any accident prevention and safety program of the City; provided, however, that the City shall not be required to impose any safety requirements or administer any such programs and the review or requirement of any safety plan by the City shall not be deemed to release Contractor or in any way diminish its liability, by way of indemnity or otherwise, as assumed by it under this Contract. Contractor shall conduct inspections regularly to determine that safe working conditions and equipment exist and accepts sole responsibility for providing a safe place to Work for its employees and employees of its Subcontractors, laborers, suppliers of material and equipment and any other person visiting the Site, for adequacy of and required use of all safety equipment and for compliance herewith. When so ordered, Contractor shall stop any part of the Work that the City deems unsafe until corrective measures satisfactory to the City have been taken. Should Contractor neglect to adopt such corrective measures, the City may do so and deduct the cost from payments due Contractor. Contractor shall timely submit copies of all accident or injury reports to the City.
The Contractor shall submit a public information and notification plan for this Project (the “Notification Plan”) to the City Representative at the first pre-construction meeting held prior to start of construction. The Notification Plan shall include, at a minimum, the items set forth in this Section; provided, however, that the Engineer may waive any portion of the requirements of this Section upon a written determination that the Project scope does not warrant such notification. Contractor shall provide Project information to affected residents and homeowners’ associations prior to and throughout the Project’s duration. The Contractor shall use the Notification Plan to inform the local citizens, businesses and City officials, not less than five business days in advance, of (A) necessary operations that create high noise levels, (B) street closures, (C) detour locations, (D) haul routes and material delivery routes and (E) disruption of bus routes, mail routes and other delivery/pick-up routes.
[END OF PART B]
PART C - MISCELLANEOUS
This Contract shall be governed by the laws of the State of Arizona and suit pertaining to this Contract may be brought only in courts in Maricopa County, Arizona.
This Contract is subject to the provisions of ARIZ. REV. STAT. § 38-511. The City may cancel this Contract without penalty or further obligations by the City or any of its departments or agencies if any person significantly involved in initiating, negotiating, securing, drafting or creating this Contract on behalf of the City or any of its departments or agencies is, at any time while this Contract or any extension of this Contract is in effect, an employee of any other party to this Contract in any capacity or a consultant to any other party of this Contract with respect to the subject matter of this Contract.
This Contract may be modified only by a written amendment signed by persons duly authorized to enter into contracts on behalf of the City and the Contractor; provided, however, that Change Orders may be issued and approved administratively by the City when such changes do not alter the Contract Price.
Each and every provision of law and any clause required by law to be in this Contract will be read and enforced as though it were included herein and, if through mistake or otherwise any such provision is not inserted, or is not correctly inserted, then upon the application of either party, this Contract will promptly be physically amended to make such insertion or correction.
The provisions of this Contract are severable to the extent that any provision or application held to be invalid by a Court of competent jurisdiction shall not affect any other provision or application of this Contract which may remain in effect without the invalid provision or application.
It is clearly understood that each party will act in its individual capacity and not as an agent, employee, partner, joint venturer, or associate of the other. An employee or agent of one party shall not be deemed or construed to be the employee or agent of the other for any purpose whatsoever. The Contractor acknowledges and agrees that the Services provided under this Agreement are being provided as an independent contractor, not as an employee or agent of the City. Contractor, its employees and subcontractors are not entitled to workers’ compensation benefits from the City. The City does not have the authority to supervise or control the actual work of Contractor, its employees or subcontractors. The Contractor, and not the City, shall determine the time of its performance of the services provided under this Agreement so long as Contractor meets the requirements of its agreed scope of work and the Specifications, Plans/construction drawings and Reference Documents as set forth in "Purpose/Scope of Work" within Article II of this IFB. Contractor is neither prohibited from entering into other contracts nor prohibited from practicing its profession elsewhere. City and Contractor do not intend to nor will they combine business operations under this Agreement.
This Contract represents the entire agreement of the parties with respect to its subject matter, and all previous agreements, whether oral or written, entered into prior to this Contract are hereby revoked and superseded by this Contract. No representations, warranties, inducements or oral agreements have been made by any of the parties except as expressly set forth herein, or in any other contemporaneous written agreement executed for the purposes of carrying out the provisions of this Contract. This Contract shall be construed and interpreted according to its plain meaning, and no presumption shall be deemed to apply in favor of, or against the party drafting this Contract. The parties acknowledge and agree that each has had the opportunity to seek and utilize legal counsel in the drafting of, review of, and entry into this Contract.
No right or interest in this Contract shall be assigned or delegated by Contractor without prior, written permission of the City, signed by the City Manager. Any attempted assignment or delegation by Contractor in violation of this provision shall be a breach of this Contract by Contractor.
No subcontract shall be entered into by the Contractor with any other party to furnish any of the Materials, Services or construction specified herein without the prior, written approval of the City. The Contractor is responsible for performance under this Contract whether or not Subcontractors are used.
No provision in this Contract shall be construed, expressly or by implication, as waiver by the City of any existing or future right and/or remedy available by law in the event of any claim of default or breach of this Contract. The failure of the City to insist upon the strict performance of any term or condition of this Contract or to exercise or delay the exercise of any right or remedy provided in this Contract, or by law, or the City’s acceptance of and payment for Materials or Services, shall not release the Contractor from any responsibilities or obligations imposed by this Contract or by law, and shall not be deemed a waiver of any right of the City to insist upon the strict performance of this Contract.
In the event either party brings any action for any relief, declaratory or otherwise, arising out of this Contract or on account of any breach or default hereof, the prevailing party shall be entitled to receive from the other party reasonable attorneys’ fees and reasonable costs and expenses, determined by the court sitting without a jury, which shall be deemed to have accrued on the commencement of such action and shall be enforced whether or not such action is prosecuted through judgment.
Any notice or other communication required or permitted to be given under this Contract shall be in writing and shall be deemed to have been duly given if (A) delivered to the party at the address set forth below, (B) deposited in the U.S. Mail, registered or certified, return receipt requested, to the address set forth below or (C) given to a recognized and reputable overnight delivery service, to the address set forth below:
| If to the City: | City of Avondale |
| 11465 West Civic Center Drive | |
| Avondale, Arizona 85323 | |
| Attn: Procurement Manager | |
| With copies to: | City of Avondale |
| 11465 West Civic Center Drive | |
| Avondale, Arizona 85323 | |
| Attn: City Attorney | |
| If to Contractor: | _____________________________ |
| _____________________________ | |
| _____________________________ | |
| Attn: _________________________ |
or at such other address, and to the attention of such other person or officer, as any party may designate in writing by notice duly given pursuant to this Section. Notices shall be deemed received (A) when delivered to the party, (B) three business days after being placed in the U.S. Mail, properly addressed, with sufficient postage or (C) the following business day after being given to a recognized overnight delivery service, with the person giving the notice paying all required charges and instructing the delivery service to deliver on the following business day. If a copy of a notice is also given to a party’s counsel or other recipient, the provisions above governing the date on which a notice is deemed to have been received by a party shall mean and refer to the date on which the party, and not its counsel or other recipient to which a copy of the notice may be sent, is deemed to have received the notice.
The City maintains that, in practice, overcharges resulting from antitrust violations are borne by the purchaser. Therefore, to the extent permitted by law, the Contractor hereby assigns to the City any and all claims for such overcharges as to the goods and services used to fulfill this Contract.
Except for payment for sums due, neither party shall be liable to the other nor deemed in default under this Contract if and to the extent that such party’s performance of this Contract is prevented by reason of force majeure. The term “force majeure” means an occurrence that is beyond the control of the party affected and occurs without its fault or negligence. Without limiting the foregoing, force majeure includes acts of God; acts of the public enemy; war; riots; strikes; mobilization; labor disputes; civil disorders; fire; floods; lockouts, injunctions-intervention-acts, or failures or refusals to act by government authority; and other similar occurrences beyond the control of the party declaring force majeure which such party is unable to prevent by exercising reasonable diligence. The force majeure shall be deemed to commence when the party declaring force majeure notifies the other party, in accordance with the "Notices and Requests" Section of this IFB, of the existence of the force majeure and shall be deemed to continue as long as the results or effects of the force majeure prevent the party from resuming performance in accordance with this Contract. Force majeure shall not include the following occurrences:
Any delay or failure in performance by either party hereto shall not constitute default hereunder or give rise to any claim for damages or loss of anticipated profits if, and to the extent that such delay or failure is caused by force majeure. If either party is delayed at any time in the progress of the Work by force majeure, then the delayed party shall notify the other party in accordance with the "Notices and Requests" Section of this IFB and shall make a specific reference to this Section, thereby invoking its provisions. The delayed party shall cause such delay to cease as soon as practicable and shall notify the other party in writing. The time of Substantial Completion or Final Completion shall be extended by written Contract amendment for a period of time equal to the time that the results or effects of such delay prevent the delayed party from performing in accordance with this Contract.
The Contractor shall establish and maintain procedures and controls that are acceptable to the City for the purpose of ensuring that information contained in its records or obtained from the City or from others in carrying out its obligations under this Contract shall not be used or disclosed by it, its agents, officers, or employees, except as required to perform Contractor’s duties under this Contract. Persons requesting such information should be referred to the City. Contractor also agrees that any information pertaining to individual persons shall not be divulged other than to employees or officers of Contractor as needed for the performance of duties under this Contract.
To ensure that the Contractor and its Subcontractors are complying with the warranty under the "E-verify Requirements" Section of this IFB, Contractor’s and its Subcontractors’ books, records, correspondence, accounting procedures and practices, and any other supporting evidence relating to this Contract, including the papers of any Contractor and its Subcontractors’ employees who perform any Work or Services pursuant to this Contract (all of the foregoing hereinafter referred to as “Records”), shall be open to inspection and subject to audit and/or reproduction during normal working hours by the City, to the extent necessary to adequately permit (1) evaluation and verification of any invoices, payments or claims based on Contractor’s and its Subcontractors’ actual costs (including direct and indirect costs and overhead allocations) incurred, or units expended directly in the performance of Work under this Contract and (2) evaluation of the Contractor’s and its Subcontractors’ compliance with the Arizona employer sanctions laws referenced in the "E-verify Requirements" Section of this IFB. To the extent necessary for the City to audit Records as set forth in this Section, Contractor and its Subcontractors hereby waive any rights to keep such Records confidential. For the purpose of evaluating or verifying such actual or claimed costs or units expended, the City shall have access to said Records, even if located at its Subcontractors’ facilities, from the effective date of this Contract for the duration of the Work and until three years after the date of final payment by the City to Contractor pursuant to this Contract. Contractor and its Subcontractors shall provide the City with adequate and appropriate workspace so that the City can conduct audits in compliance with the provisions of this Section. The City shall give Contractor or its Subcontractors reasonable advance notice of intended audits. Contractor shall require its Subcontractors to comply with the provisions of this Section by insertion of the requirements hereof in any subcontract pursuant to this Contract.
To the extent applicable under ARIZ. REV. STAT. § 41-4401, the Contractor and its Subcontractors warrant compliance with all Federal immigration laws and regulations that relate to their employees and their compliance with the E-verify requirements under ARIZ. REV. STAT.§ 23-214(A). Contractor’s or its Subcontractors’ failure to comply with such warranty shall be deemed a material breach of this Contract and may result in the termination of this Contract by the City.
For Contracts in excess of One Hundred Thousand ($100,000) Dollars, Contractor certifies that it is not currently engaged in, and agrees for the duration of this Agreement that it will not engage in a “boycott,” as that term is defined in ARIZ. REV. STAT. § 35-393, of Israel.
Contractor certifies that it does not, and agrees for the duration of this Agreement that it, its subcontractors, and its suppliers will not, use the forced labor of ethnic Uyghurs in the People’s Republic of China nor any products or services derived from the force labor of ethnic Uyghurs.
The City may, at reasonable times, inspect the part of the plant or place of business of the Contractor or Subcontractor that is related to the performance of this Contract.
Contractor warrants to the City that all Materials and equipment furnished shall be new unless otherwise specified and agreed by the City and that all Work shall be of first class quality, free from faults and defects and in conformance with this Contract. If at any time within one year following the date of Final Completion and acceptance of the entire Project (or such longer period as may be provided under warranties for equipment or Materials): (A) any part of the Materials furnished in connection with the Work shall be or become defective due to defects in either labor or Materials, or both, or (B) Contractor’s Work or Materials, or both, are or were not in conformance with original or amended Plans and Specifications, or supplementary shop drawings, then the Contractor shall upon written notice from the City immediately replace or repair such defective or non-conforming Material or workmanship at no cost to the City. Contractor further agrees to execute any special guarantees as provided by this Contract or required by law. Contractor shall require similar guarantees from all vendors and from all its Subcontractors. Contractor further agrees, upon written demand of the City and during the course of construction, to immediately re-execute, repair or replace any Work that fails to conform to the requirements of this Contract, whether caused by faulty Materials or workmanship, or both. In the event Contractor shall fail or refuse to make such change upon the City’s written demand, the City shall have the right to have such Work re-executed, repaired or replaced, to withhold from or back charge to Contractor all costs incurred thereby.
All Materials and/or Services are subject to final inspection and acceptance by the City. Materials and/or Services failing to conform to the Specifications of this Contract will be held at Contractor’s risk and may be returned to the Contractor. If so returned, all costs are the responsibility of the Contractor. Upon discovery of non-conforming Materials or Services, the City may elect to do any or all of the following by written notice to the Contractor: (A) waive the non-conformance; (B) stop the Work immediately; or (C) bring material or service into compliance and withhold the cost of same from any payments due to the Contractor.
Every tender of Materials shall fully comply with all provisions of this Contract. If a tender is made which does not fully conform, this shall constitute a breach of this Contract as a whole.
Contractor is not authorized to ship Materials under reservation and no tender of a bill of lading will operate as a tender of the Materials.
All Materials, Service or construction shall be free of all liens and, if the City requests, a formal release of all liens shall be delivered to the City.
Contractor shall maintain in current status all Federal, State and Local licenses and permits required for the operation of the business conducted by the Contractor as applicable to this Contract.
All Services, information, computer program elements, reports and other deliverables, which may be patented or copyrighted and created under this Contract are the property of the City and shall not be used or released by the Contractor or any other person except with the prior written permission of the City.
All Specifications shall seek to promote overall economy for the purposes intended and encourage competition and not be unduly restrictive in satisfying the City’s needs. No person preparing Specifications shall receive any direct or indirect benefit from the utilization of Specifications, other than fees paid for the preparation of Specifications.
Contractor shall not advertise or publish information concerning this Contract without prior, written consent of the City.
When Federal funds are used to fund the purchase of goods and services, 2CFR PART 200 and other applicable federal terms and conditions shall apply.
[END OF PART C]
PART D - ALTERNATIVE DISPUTE RESOLUTION
Notwithstanding anything to the contrary provided elsewhere in the Contract Documents, except for subsection (G) of "Binding Arbitration Procedure" in this IFB, the alternative dispute resolution (“ADR”) process provided for herein shall be the exclusive means for resolution of claims or disputes arising under, relating to or touching upon this Contract, the interpretation thereof or the performance or breach by any party thereto, including but not limited to original claims or disputes asserted as cross claims, counterclaims, third party claims or claims for indemnity or subrogation, in any threatened or ongoing litigation or arbitration with third parties, if such disputes involve parties to contracts containing this ADR provision.
The City will select a Neutral Evaluator to serve as set forth in this ADR process, subject to the Contractor’s approval, which approval shall not be unreasonably withheld. In the event that the City and the Contractor are unable to agree upon a Neutral Evaluator, the neutral evaluation process shall be eliminated and the parties shall proceed with the binding arbitration process set forth in in the "Binding Arbitration Procedure" Section of this IFB. The City and Contractor shall each select an arbitrator to serve as set forth in this ADR process. Each arbitrator selected shall be a member of the State Bar of the State of Arizona and shall have experience in the field of construction law. None of the arbitrators nor any of the arbitrator’s firms shall have presently, or in the past, represented any party to the arbitration.
If the parties have been unable to resolve the disputes after discussions and partnering, but the parties have agreed to a Neutral Evaluator, the following neutral evaluation process shall be used to resolve any such dispute.
The following binding arbitration procedure, except as provided in subsection (G) below, shall serve as the exclusive method to resolve a dispute if (A) the parties cannot agree to a Neutral Evaluator as set forth in the "Neutral Evaluator, Arbitrators" Section of this IFB or (B) any party chooses not to accept the decision of the Neutral Evaluator. The party requesting binding arbitration shall notify the Neutral Evaluator of a request for arbitration in writing within three business days’ of receipt of the Neutral Evaluator’s decision. If the Contractor requests arbitration or if Contractor rejects the City’s selection of a Neutral Evaluator, it shall post a cash bond with the Neutral Evaluator in an amount agreed upon by the parties or, in the event of no agreement, the Neutral Evaluator shall establish the amount of the cash bond to defray the cost of the arbitration as set forth in subsection (M) below and the proceeds from the bond shall be allocated in accordance with subsection (M) by the Arbitration Panel.
Please provide a point of contact for IFB for follow-up questions or notifications. (Name, email & phone number).
Vendor certifies that it has reviewed and verified the plans and specifications included as part of this IFB, and that the information contained therein has been incorporated in formulating the Vendor’s Offer.
Is your firm currently registered and showing Active status in SAM.gov?
Note: Vendor must be registered on System for Award Management (“Sam.gov”) before submitting an offer, provide a valid Unique Entity Identifier Number and continue to maintain an active SAM registration during which it has an active Federal award.
Please provide your Unique Entity Identifier Number.
Because this solicitation is funded in whole or in part with federal grant funds, you are required to be registered in SAM.gov with an Active status.
Failure to obtain and maintain an Active SAM.gov registration by the required deadline may result in your bid being deemed non-responsive, and the City may proceed with award to the next lowest, responsive and responsible bidder.
Byrd Anti-Lobbying Amendment (31 U.S.C. 1352) - Contractors that apply or bid for an award exceeding $100,000 must file the required certification.
Are you submitting a bid for an award exceeding $100,000?
The Bidder certifies, to the best of his or her knowledge and belief, that:
This confirmation is a material representation of fact upon which reliance was placed when this transaction was made or entered into. Submission of this certification is a prerequisite for making or entering into this transaction imposed by section 1352, title 31, U.S. Code. Any person who fails to file the required certification shall be subject to a civil penalty of not less than $10,000 and not more than $100,000 for each such failure.
Businesses that are located in the City of Avondale are required to obtain and maintain City of Avondale business license. Is your business located in Avondale?
Has your firm been certified by any jurisdiction in Arizona as a minority or woman owned business enterprise?
You indicated that your firm has been certified in Arizona as a minority or woman owned business enterprise.
Please upload details and documentation of the certification
Please download the below documents, complete, and upload.
Please download the below documents, complete, and upload.
Please provide all key personnel and subcontractors that you are planning on utilizing on this Project.
Please download the below documents, complete, and upload.
Please upload a copy of your signed W-9 using the most current W-9 form. Form W-9 (Rev. March 2024) (irs.gov)
Per section titled "Bid Bond", all Vendors desiring to prepare a responsive Bid shall submit a non-revocable bid security payable to the City in the amount of ten percent (10%) of the total Bid Price. This security shall be in the form of a bid bond, certified check or cashier’s check and must be in the possession of the City Representative by the Bid Deadline.
Are you submitting a certified check or cashier's check?
It is the Bidder's responsibility to ensure that the certified check or cashier’s check is in the possession of the City Representative by the Bid Deadline. If the check is not in possession of the City Representative by the Bid Deadline, the offer will be deemed non-responsive.
Please download the below documents, complete, and upload.
All bid bonds shall be executed in the form attached hereto, duly executed by the Bidder as Principal and having as Surety thereon a Surety company holding a Certificate of Authority from the Arizona Department of Insurance to transact surety business in the State of Arizona. Individual sureties are unacceptable. All insurers and sureties shall have, at the time of submission of the proposal, an A.M. Best’s Key Rating Guide of “A-” or better as currently listed in the most recent Best Key Guide, published by the A.M. Best Company.
Please submit the completed Bid Tabulation.
Please download the below documents, complete, and upload.
I acknowledge that I have read and reviewed the Avondale City Artificial Intelligence Use Policy. I understand and agree to comply with all requirements outlined in this policy.
The Bidder hereby offers this Bid as an offer to contract with the City under the terms and conditions and certifies that Bidder has read, understands and agrees to fully comply with, and be contractually bound by, all terms and conditions as set forth in this Invitation For Bids (“IFB”), the Contract formed hereby and any amendments thereto, together with all Exhibits, Specifications, Plans and other documents included as part of this Contract (the “Contract Documents”).
Complete the following sentence (specifically fill in the blank highlighted section):
The Work included in this Project consists of ____________.
Based on the project, please fill in the address of the site location.
Site Location: ____________
EXAMPLE:
11320 West Civic Center Drive, Avondale, Arizona
Complete the following highlighted area as appropriate based on the requirements of this project.
The City is issuing this IFB to secure a qualified and licensed __________ Class __ Contractor to perform the Work...
EXAMPLE:
Engineering Contracting (Commercial) Class A
Complete the following sentence, specifically the highlighted area as appropriate for this project. (Be sure to specify calendar days or weeks or months).
The Contract Time for this Project shall be __ weeks/months from the Notice to Proceed.
EXAMPLE 1:
three (3) months
EXAMPLE 2:
ninety (90) calendar days
EXAMPLE 3:
twelve (12) weeks
Based on the project, please fill in a number for minimum number of project signs required to be posted prior to beginning construction.
Unless otherwise directed by the Engineer, the Contractor shall furnish and install at least ____ Project signs, not less than five business days before beginning construction...
EXAMPLE:
five (5)
Is any federal or state grant intended for the funding of this procurement?
Given the nature of this construction project, does the City accept only public sector references? Based on your response, the appropriate reference form will be provided to bidders in the Vendor Questionnaire.
SLED stands for State, Local, and Education. These are solicitations issued by state governments, counties, cities, school districts, utilities, and higher education institutions — as opposed to federal agencies.
SamSearch Platform
AI-powered intelligence for the right opportunities, the right leads, and the right time.