subsectionUpdated April 16, 2026

    FAR 16.403-1Fixed-price incentive (firm target) contracts.

    Plain-English Summary

    FAR 16.403-1 explains the fixed-price incentive (firm target) contract type and how it is structured, used, and documented. It covers the required pricing elements—target cost, target profit, price ceiling, and profit adjustment formula—plus how the final price is determined after performance based on actual negotiated cost. It also explains the economic purpose of this contract type: to give the contractor a direct, calculable incentive to control costs while allowing the government to share risk through a ceiling and negotiated profit adjustment. The section further addresses when this contract type is appropriate, including the need for a firm target cost and profit formula that are fair and reasonable, and it limits use to situations where the contractor’s accounting system can support final cost negotiation and where adequate cost or pricing information exists up front. Finally, it requires the contracting officer to put the target cost, target profit, and target price in the contract schedule for each item subject to incentive price revision. In practice, this section matters because it determines how risk is allocated, how profit moves with performance, and whether the government can credibly negotiate and administer the contract.

    Key Rules

    Required pricing elements

    A fixed-price incentive (firm target) contract must include a target cost, target profit, price ceiling, and a profit adjustment formula. These are negotiated at the outset and define how the final price will be calculated after performance.

    Final price follows actual cost

    After performance, the parties negotiate the final cost and apply the agreed formula to establish the final price. If actual cost is below target, profit increases; if actual cost is above target, profit decreases, potentially to a loss.

    Price ceiling limits payment

    The price ceiling is the maximum amount payable to the contractor, except for any adjustment allowed under other contract clauses. If final negotiated cost exceeds the ceiling, the contractor absorbs the excess.

    Appropriate only with firm targets

    This contract type is appropriate only when the parties can negotiate a firm target cost, target profit, and a fair and reasonable incentive formula, along with a ceiling that makes the contractor assume an appropriate share of risk.

    Profit must match risk share

    When the contractor bears a considerable or major share of cost responsibility under the adjustment formula, the target profit should reflect that added responsibility. The profit structure should align with the level of risk the contractor is taking.

    Accounting system must support settlement

    The contractor may use this contract type only if its accounting system can provide adequate data to support negotiation of final cost and any incentive price revision. The system must be capable of producing reliable cost information for closeout and settlement.

    Adequate cost data must exist up front

    The contract type may be used only when adequate cost or pricing information is available at the time of initial negotiation to establish reasonable firm targets. The government must be able to set the targets on a sound factual basis.

    Schedule must state target terms

    The contracting officer must specify the target cost, target profit, and target price in the contract schedule for each item subject to incentive price revision. This ensures the incentive terms are clear and enforceable.

    Responsibilities

    Contracting Officer

    Determine whether the contract type is appropriate, negotiate the target cost, target profit, price ceiling, and profit adjustment formula, and ensure the targets are fair and reasonable. The contracting officer must also place the target cost, target profit, and target price in the contract schedule for each item subject to incentive price revision.

    Contractor

    Perform efficiently to control costs because profit decreases as final cost rises and increases as final cost falls. The contractor must maintain an accounting system capable of supporting final cost negotiation and provide cost data needed to settle the final price.

    Agency

    Use this contract type only when the acquisition circumstances support firm targets and adequate cost or pricing information exists. The agency must ensure the risk allocation and incentive structure are consistent with the procurement objective and the contractor’s assumed responsibility.

    Both Parties

    Negotiate the final cost after performance and apply the agreed formula to establish the final price. Both sides must understand how the ceiling, target profit, and adjustment formula interact so the settlement reflects the contract terms.

    Practical Implications

    1

    This contract type is designed to motivate cost control, so contractors should manage performance closely; overruns directly reduce profit and can turn into a loss if the ceiling is exceeded.

    2

    The price ceiling is a hard cap in most cases, so both sides need to model worst-case outcomes before award; failing to do so can leave the contractor exposed to unrecoverable costs.

    3

    A weak or unsupported target cost can undermine the entire incentive arrangement, so contracting officers should not use this type unless they have reliable cost or pricing data and a defensible formula.

    4

    Contractor accounting systems matter more here than in many other fixed-price arrangements because final cost must be negotiated and supported with credible records.

    5

    A common pitfall is setting target profit without matching it to the contractor’s risk share; if the contractor bears major cost responsibility, the profit structure should be adjusted accordingly to remain fair and reasonable.

    Official Regulatory Text

    (a) Description . A fixed-price incentive (firm target) contract specifies a target cost, a target profit, a price ceiling (but not a profit ceiling or floor), and a profit adjustment formula. These elements are all negotiated at the outset. The price ceiling is the maximum that may be paid to the contractor, except for any adjustment under other contract clauses. When the contractor completes performance, the parties negotiate the final cost, and the final price is established by applying the formula. When the final cost is less than the target cost, application of the formula results in a final profit greater than the target profit; conversely, when final cost is more than target cost, application of the formula results in a final profit less than the target profit, or even a net loss. If the final negotiated cost exceeds the price ceiling, the contractor absorbs the difference as a loss. Because the profit varies inversely with the cost, this contract type provides a positive, calculable profit incentive for the contractor to control costs. (b) Application . A fixed-price incentive (firm target) contract is appropriate when the parties can negotiate at the outset a firm target cost, target profit, and profit adjustment formula that will provide a fair and reasonable incentive and a ceiling that provides for the contractor to assume an appropriate share of the risk. When the contractor assumes a considerable or major share of the cost responsibility under the adjustment formula, the target profit should reflect this responsibility. (c) Limitations . This contract type may be used only when- (1) The contractor’s accounting system is adequate for providing data to support negotiation of final cost and incentive price revision; and (2) Adequate cost or pricing information for establishing reasonable firm targets is available at the time of initial contract negotiation. (d) Contract schedule . The contracting officer shall specify in the contract schedule the target cost, target profit, and target price for each item subject to incentive price revision.