SectionUpdated April 16, 2026

    FAR 49.404Surety-takeover agreements.

    Plain-English Summary

    FAR 49.404 addresses surety-takeover agreements after a contractor default, with special focus on fixed-price construction contracts. It explains when and how a contracting officer may consider a surety’s proposal to complete the work, the Government’s duty to protect its own interests, and the surety’s rights in completing the contract and seeking payment from undisbursed contract funds. The section also covers the use of takeover agreements, including possible tripartite agreements among the Government, the surety, and the defaulting contractor to resolve competing claims to retained percentages and unpaid progress estimates. It sets limits on what the surety may be paid, how liquidated damages apply, how assigned contract proceeds affect payment, and when the surety may be reimbursed for liabilities under the payment bond. In practice, this section is about balancing completion of the project, protection of Government claims, and orderly resolution of competing financial interests after default.

    Key Rules

    Applies mainly to construction defaults

    These procedures apply primarily, though not exclusively, to fixed-price construction contracts terminated for default. Contracting officers should recognize that the section is most relevant when a construction project must be completed after the original contractor fails.

    Government interest controls

    The contracting officer must evaluate surety proposals based on the Government’s interest, including the effect on the Government’s rights against the surety. The surety’s rights matter, but they do not override the Government’s need to protect completion, cost, and recovery interests.

    Consider surety completion offers

    The contracting officer should generally allow the surety to propose completion of the work unless the proposed completion team is not competent and qualified or the proposal is not in the Government’s best interest. This creates a presumption in favor of considering surety completion, not an automatic acceptance.

    Takeover agreements after termination

    The contracting officer may enter into a written takeover agreement with the surety, but not before the effective date of termination. The agreement can fix the surety’s rights to payment from unpaid contract funds and help resolve competing claims to the defaulting contractor’s residual interests.

    Unpaid earnings remain subject to Government debts

    Any unpaid earnings of the defaulting contractor, including retainage and unpaid progress estimates, remain subject to debts owed to the Government, except to the extent those funds may be used to pay the completing surety’s actual completion costs and expenses. The surety cannot use those funds to recover payment-bond obligations.

    Liquidated damages still apply

    The surety is bound by the contract’s liquidated damages clause for delays in completion unless the delays are excusable under the contract. A takeover does not erase delay liability simply because the surety steps in to finish the work.

    Assignment restrictions matter

    If contract proceeds were assigned to a financing institution, the surety may not be paid from unpaid earnings unless the assignee gives written consent. The contracting officer must check for financing assignments before agreeing to payment from those funds.

    Payment to surety is limited

    The contracting officer may not pay the surety more than the amount it actually expended to complete the work and discharge liabilities under the defaulting contractor’s payment bond. Reimbursement for payment-bond liabilities requires mutual agreement, a Comptroller General determination, or a court order.

    Responsibilities

    Contracting Officer

    Evaluate the surety’s completion proposal carefully, decide whether the proposed completion arrangement is in the Government’s best interest, and protect the Government’s rights against the surety. The contracting officer may enter a written takeover agreement only after termination becomes effective, must account for competing claims to unpaid earnings, must verify any assignment restrictions, and must limit payments to the amounts allowed by the rule.

    Surety

    If it proposes to complete the work, the surety must present a competent and qualified completion arrangement and, if a takeover agreement is executed, complete the contract. The surety may seek payment from unpaid contract funds only within the limits of the agreement and the rule, and it remains subject to liquidated damages unless excused.

    Defaulting Contractor

    The defaulting contractor may retain residual claims to unpaid earnings, but those claims are subordinate to Government debts and may be affected by a takeover agreement or tripartite agreement. The contractor’s interests may need to be resolved in a three-party agreement when unpaid earnings or other residual rights are disputed.

    Financing Institution / Assignee

    If contract proceeds have been assigned, the assignee must provide written consent before unpaid earnings can be used to pay the surety. The assignee’s rights must be checked before the Government disburses funds under a takeover arrangement.

    Government

    The Government must ensure completion of the work while preserving its claims, including rights against the surety and debts owed by the defaulting contractor. It must only authorize payment to the surety within the narrow limits stated in the section and use the proper legal authority for payment-bond reimbursements.

    Practical Implications

    1

    A surety takeover can be a practical way to finish a defaulted construction project faster than reprocurement, but the contracting officer must document why the arrangement serves the Government’s interest.

    2

    Retainage and unpaid progress payments often become contested funds, so the contracting officer should identify all potential claimants early, including the contractor, surety, and any financing assignee.

    3

    Do not assume the surety can be paid for everything it spends; the rule limits reimbursement to completion costs and certain liabilities, and it excludes ordinary payment-bond obligations unless special authority exists.

    4

    Liquidated damages remain a live issue after takeover, so the completion schedule and any excusable delay analysis should be tracked carefully from the start of the takeover arrangement.

    5

    A tripartite agreement can prevent later disputes, but only if it clearly addresses the defaulting contractor’s residual rights and the disposition of unpaid earnings.

    Official Regulatory Text

    (a) The procedures in this section apply primarily, but not solely, to fixed-price construction contracts terminated for default. (b) Since the surety is liable for damages resulting from the contractor’s default, the surety has certain rights and interests in the completion of the contract work and application of any undisbursed funds. Therefore, the contracting officer must consider carefully the surety’s proposals for completing the contract. The contracting officer must take action on the basis of the Government’s interest, including the possible effect upon the Government’s rights against the surety. (c) The contracting officer should permit surety offers to complete the contract, unless the contracting officer believes that the persons or firms proposed by the surety to complete the work are not competent and qualified or the proposal is not in the best interest of the Government. (d) There may be conflicting demands for the defaulting contractor’s assets, including unpaid prior earnings (retained percentages and unpaid progress estimates). Therefore, the surety may include a "takeover" agreement in its proposal, fixing the surety’s rights to payment from those funds. The contracting officer may (but not before the effective date of termination) enter into a written agreement with the surety. The contracting officer should consider using a tripartite agreement among the Government, the surety, and the defaulting contractor to resolve the defaulting contractor’s residual rights, including assertions to unpaid prior earnings. (e) Any takeover agreement must require the surety to complete the contract and the Government to pay the surety’s costs and expenses up to the balance of the contract price unpaid at the time of default, subject to the following conditions: (1) Any unpaid earnings of the defaulting contractor, including retained percentages and progress estimates for work accomplished before termination, must be subject to debts due the Government by the contractor, except to the extent that the unpaid earnings may be used to pay the completing surety its actual costs and expenses incurred in the completion of the work, but not including its payments and obligations under the payment bond given in connection with the contract. (2) The surety is bound by contract terms governing liquidated damages for delays in completion of the work, unless the delays are excusable under the contract. (3) If the contract proceeds have been assigned to a financing institution, the surety must not be paid from unpaid earnings, unless the assignee provides written consent. (4) The contracting officer must not pay the surety more than the amount it expended completing the work and discharging its liabilities under the defaulting contractor’s payment bond. Payments to the surety to reimburse it for discharging its liabilities under the payment bond of the defaulting contractor must be only on authority of- (i) Mutual agreement among the Government, the defaulting contractor, and the surety; (ii) Determination of the Comptroller General as to payee and amount; or (iii) Order of a court of competent jurisdiction.