subsectionUpdated April 16, 2026

    FAR 49.109-1General.

    Plain-English Summary

    FAR 49.109-1 explains how a negotiated termination settlement is finalized after the parties have reached agreement and all required internal reviews are complete. It requires the contractor and the Termination Contracting Officer (TCO) to execute a settlement agreement on Standard Form 30, using the form prescribed in FAR 49.603. The section also defines what the settlement agreement must cover: any Government setoffs that may be applied against the terminated contract, and all subcontractor settlement proposals unless a proposal is specifically excluded and reserved for separate settlement. In practice, this provision turns a negotiated termination settlement into a formal, enforceable contract modification and ensures that the Government’s financial claims and subcontractor-related amounts are addressed in one integrated document unless expressly carved out. It matters because it reduces later disputes, clarifies the final amount due, and establishes the administrative record for closing out the termination settlement.

    Key Rules

    Execute a formal settlement

    Once the termination settlement is negotiated and all required reviews are obtained, the contractor and the TCO must sign a settlement agreement. The agreement must be on Standard Form 30, which is the required modification instrument referenced in FAR 49.603.

    Settlement follows completed reviews

    The agreement cannot be executed until the negotiated settlement has gone through all required reviews. This means the parties must complete any internal approvals or oversight steps before the settlement becomes final.

    Include Government setoffs

    The settlement must address any Government setoffs against the contractor that can be applied to the terminated contract. These offsets are part of the final settlement and should be resolved in the agreement rather than left open.

    Capture subcontractor proposals

    All subcontractor settlement proposals must be included in the settlement agreement unless a proposal is specifically excepted. The default rule is inclusion, so exclusions must be clearly identified.

    Reserve excluded items separately

    If a subcontractor proposal is specifically excepted from the agreement, it must be reserved for separate settlement. This prevents confusion over whether the item was resolved and preserves it for later handling.

    Responsibilities

    Termination Contracting Officer (TCO)

    Ensure the negotiated settlement has received all required reviews, prepare or approve the settlement agreement on Standard Form 30, include applicable Government setoffs and subcontractor settlement proposals, and execute the agreement with the contractor.

    Contractor

    Participate in the negotiated settlement, review the final agreement, and execute the settlement agreement on Standard Form 30 once all required reviews are complete.

    Government reviewers/approving officials

    Complete any required reviews of the negotiated settlement before execution so the TCO and contractor can finalize the agreement.

    Subcontractors

    Submit settlement proposals that may be included in the prime contractor’s termination settlement, unless a proposal is specifically excepted and reserved for separate settlement.

    Practical Implications

    1

    This section makes the settlement agreement the formal closing document for a negotiated termination settlement, so parties should treat it as the final written record of what is resolved and what remains open.

    2

    A common pitfall is overlooking Government setoffs; if they are not identified and applied in the agreement, the final settlement amount may be incorrect or later disputed.

    3

    Another frequent issue is failing to clearly list subcontractor proposals that are excluded from the agreement. If an item is meant for separate settlement, it should be expressly reserved to avoid accidental waiver or double payment.

    4

    Because the agreement must be on SF 30, using the wrong form or omitting required modification language can create administrative problems and delay closeout.

    5

    Contractors should verify that all required reviews are complete before signing, since premature execution can lead to rework or questions about the validity of the settlement.

    Official Regulatory Text

    When a termination settlement has been negotiated and all required reviews have been obtained, the contractor and the TCO shall execute a settlement agreement on Standard Form 30 (Amendment of Solicitation/Modification of Contract) (see 49.603 ). The settlement shall cover- (a) Any setoffs that the Government has against the contractor that may be applied against the terminated contract and (b) All settlement proposals of subcontractors, except proposals that are specifically excepted from the agreement and reserved for separate settlement.