Charlotte County Awards $29.3M Manasota Key Beach Renourishment Contract
Charlotte County approved a $29,348,880 award to Great Lakes Dredge & Dock Company, LLC, for renourishment at Manasota Key and South Beach, Florida. The project covers about 990,000 cubic yards of sand, with work expected to start November 23, 2026; supporting firms should monitor subcontracting channels and schedule updates.
Key Signals
- Charlotte County approved a $29.35M beach-renourishment award to Great Lakes Dredge & Dock
- Approximately 990,000 cubic yards of sand are planned for Manasota Key and South Beach
- Expected November 23, 2026 start creates near-term mobilization and subcontracting opportunities
- Conflicting completion estimates require contractors to verify the current schedule
- Sea-turtle protections and beach work windows are material environmental compliance considerations
"The contractor is very aware of the requirements of when they have to be completed and off of the beach."
Charlotte County has approved a $29,348,880 award to Great Lakes Dredge & Dock Company, LLC for beach renourishment at Manasota Key and South Beach in Florida. The work is intended to rebuild storm-battered shoreline and involves placing approximately 990,000 cubic yards of sand. With the prime award already made, this is not an open competition for the main contract. The procurement signal for other firms is in potential subcontracting, specialized support, and project-related services coordinated with the awardee or county.
Work is expected to begin on November 23, 2026, 13 days after the November 10 publication date. That short lead time makes near-term mobilization, equipment availability, staffing, and coordination especially relevant for firms seeking a role in the project. Dredging and marine-construction subcontractors, equipment providers, and environmental-compliance specialists may wish to track county updates and engage through the prime contractor where appropriate. The scale of the sand placement also offers a useful planning reference for firms supporting coastal restoration work.
The reported completion estimates are not consistent: one target is before March 1, 2027, while another estimate is April 30, 2027. The discrepancy should be treated as a schedule item to verify rather than as a settled contractual milestone. County Engineer Joanne Vernon said, “The contractor is very aware of the requirements of when they have to be completed and off of the beach.” The project schedule is also subject to coordination and sea-turtle protections, making environmental requirements and work windows material considerations for any supporting contractor.
The agencies identified in the source include Charlotte County, the Florida Department of Environmental Protection, the Federal Emergency Management Agency, and the Florida Department of Emergency Management. Their inclusion signals a broader public-sector and environmental context for the shoreline work, but the source does not specify each agency’s funding amount, contractual role, or approval responsibility. Businesses should therefore rely on official project documentation for those details and avoid assuming that agency involvement creates a separate solicitation. For GovCon market tracking, the immediate opportunity is to follow execution of the awarded project, identify any subcontract needs, and account for schedule and wildlife-protection requirements.
- Award value: Charlotte County approved $29,348,880 for the project; the prime award is complete, not an open bid.
- Awardee: Great Lakes Dredge & Dock Company, LLC is the named contractor.
- Project locations: Renourishment is planned for Manasota Key and South Beach, Florida.
- Work scale: The project covers approximately 990,000 cubic yards of sand.
- Expected start: Work is expected to begin November 23, 2026, just 13 days after the publication date.
- Schedule to verify: Reported completion targets differ—before March 1, 2027, versus April 30, 2027.
- Environmental constraint: Coordination and sea-turtle protections affect project execution and timing.
- Potential supporting work: Dredging, equipment mobilization, marine construction, and environmental-compliance firms can monitor for subcontracting needs through the awardee and county project updates.
- County statement: Engineer Joanne Vernon said the contractor understands the requirements for when work must be completed and crews must be off the beach.
Agencies
- Charlotte County
- Florida Department of Environmental Protection
- Federal Emergency Management Agency
- Florida Department of Emergency Management
Vendors
- Great Lakes Dredge & Dock Company, LLC
Locations
- Manasota Key, Florida
- South Beach, Florida
- Florida