samsearch
    Platform
    01InfluenceShape the requirement before it's on your competitor's radar.
    Signal
    Recompete window opens in 42 days
    Facilities maintenance IDIQ$8.4M
    Forecast
    Agency spend up 18% next FY
    DoD facilitiesQ3 window
    02CaptureFind and qualify the work across every market.
    Federal91%
    Network engineering support — GSA MAS
    GSA541512
    SLED88%
    Custodial services — Fairfax County Public Schools
    K-12561720
    DIBBS79%
    Aircraft hydraulic fitting — DLA Aviation
    DLANSN 5330
    03AnalyzeExtract requirements and build the compliance matrix.
    Compliance matrix
    L.2.1Technical approachVol I
    L.3.4Staffing planVol I
    M.1Past performanceEvaluated
    SOW breakdown
    Requirements extracted38
    Mapped to Section L/M38
    Every extractionCited
    Ask Sammy
    “Do we meet the small business set-aside?”
    04ManageRun the pursuit through to award.
    Pipeline
    QualifyFacilities support · USACE
    CaptureComms upgrade · DLA
    ProposalShipyard dredging · NAVSEA
    PriyaAlex
    This week
    Submit past performance refsThu
    Confirm subK teamingFri
    Upload SF 33Mon
    05RespondDraft and submit your response.
    Drafting · Volume I
    247 words
    RFI response
    CompanyAcme Robotics LLC
    UEIJK4M8…
    Capability narrativeDrafted
    06FinanceGet paid faster on what you win.
    Capital available
    $2.4M against your award
    Facilities maintenance IDIQAwarded
    Partner matched
    LenderFederal Capital Partners
    Draw available$2.4M
    UnderwritingCleared
    The platform
    Influence
    Capture
    Analyze
    Manage
    Respond
    Finance
    One pipeline, six stages, start to award.
    See the whole platform
    Solutions
    By industry
    Tech & softwareSoftware and SaaS companies entering GovCon.Defense contractorsPrimes and subs in the defense industrial base.ConstructionBuilders bidding federal, state, and local work.CybersecuritySecurity vendors pursuing federal mandates.
    By team
    Capture managers & BDPipeline, qualification, and win strategy.Proposal teamsCompliance matrices and proposal drafting.Subcontractors & primesTeaming, subcontracting, and partner fit.
    By company size
    Small businessesSet-aside and small business contractors.EnterpriseLarge contractors running multiple pursuits.ConsultantsAdvisors and capture consultants.
    Browse all industries
    CustomersPricing
    ResourcesNew
    Learn
    AcademyCourses, guides, and playbooks.WebinarsLive sessions and recordings.DocsProduct documentation and setup guides.Implementation planOperational rollout guidance.
    Tools & data
    Free GovCon toolsCalculators, lookups, and more.Gov ExploreContracts, agencies, and NAICS codes.GovCon eventsConferences, training, and set-aside events.
    Latest blogIntroducing the New SamSearch: The Operating System for Government ContractingSamSearch has a new brand, a new site, and a new way of explaining what the platform actually does — the operating system for government contracting, organized around six stages instead of a single search box. Here's what changed and why.Read the post →
    All resources and tools
    Sign inRequest a demo
    Home/News/FERC Reforms Target Grid Interconnection Backlog as Storage Delays Persist
    federal_newspolicy

    FERC Reforms Target Grid Interconnection Backlog as Storage Delays Persist

    U.S. interconnection queues fell to about 2,061 GW by the end of 2025 but remain above 2,000 GW, leaving battery storage projects exposed to multi-year delays. FERC Order No. 2023 has yielded measurable progress, including 1.9 GW of battery agreements in PJM’s first transition cycle, while developers and suppliers must continue tracking tariff and grid-operator changes.

    November 7, 2026Federal Energy Regulatory Commission, Lawrence Berkeley National Laboratory, PJM Interconnection

    Key Signals

    • U.S. interconnection queue remains at approximately 2,061 GW despite year-over-year declines
    • PJM first transition cycle produced 1.9 GW of battery storage agreements
    • FERC ordered PJM to revise its interconnection study process on July 24, 2025
    • Plan for multi-year battery interconnection delays in project and procurement schedules
    • Order No. 2023 co-location standards may shape storage project configurations

    The U.S. queue of generation and storage projects seeking permission to connect to the electric grid remained at approximately 2,061 gigawatts (GW) at the end of 2025, according to Lawrence Berkeley National Laboratory’s annual Queued Up tracking. Although the total has declined from roughly 2,600 GW at the end of 2023 and about 2,290 GW at the end of 2024, it is still above 2,000 GW and roughly comparable to all operating U.S. generating capacity combined. For developers, contractors, and suppliers, this backlog is a material delivery constraint: projects can face years between development and grid access, complicating schedules, financing assumptions, equipment planning, and the timing of procurement demand.

    Battery storage is a growing part of the queue and faces the same extended interconnection timelines as other generation projects, despite its potential to support grid reliability. Batteries can be paired with solar generation or developed as standalone assets and dispatched quickly when needed. The source cites Dominion Energy’s storage plan in Virginia as an example of the technology’s role in the market. Yet the system’s technical value does not remove the need to complete studies, secure agreements, and satisfy grid-operator requirements before projects can connect. The source also notes that most projects entering interconnection queues ultimately are not built, reinforcing the importance of distinguishing early-stage queue capacity from projects likely to proceed.

    The Federal Energy Regulatory Commission (FERC) has been working for roughly three years to address the bottleneck through Order No. 2023, a broad overhaul of generator interconnection rules. On July 24, 2025, FERC ordered PJM Interconnection to change how it studies developer requests to connect to the grid after finding that PJM’s existing compliance plan did not fully satisfy Order No. 2023. That intervention illustrates that implementation is not simply a matter of adopting a federal rule: regional grid operators may need further revisions, and FERC oversight can shape the timing and details of those changes. Order No. 2023 also established co-location standards that allow a battery storage project to share a single interconnection request with a co-located generation asset, potentially changing how developers structure projects and prepare submissions.

    Early results show progress, but not a resolution of the nationwide backlog. In PJM’s first transition cycle, 84 generation and storage projects totaling 14.3 GW received interconnection agreements. Of those, 21 were battery energy storage resources, representing 1.9 GW. Those agreements demonstrate that battery projects are advancing under the transition process, while the overall queue remains exceptionally large and delays remain a planning concern. For the GovCon and energy supply base, the practical implication is to monitor FERC tariff proceedings and grid-operator reform deadlines, incorporate multi-year interconnection uncertainty into project schedules, and align equipment, construction, and support-service planning with realistic milestones rather than queue position alone.

    • National backlog: Queue capacity was approximately 2,061 GW at the end of 2025, down from 2,600 GW in 2023 and 2,290 GW in 2024, but still above 2,000 GW.
    • Scale of the constraint: The backlog is roughly equal to all operating U.S. generating capacity combined, making interconnection a major bottleneck for new grid resources.
    • Regional distribution: Active queue capacity is highest in the non-ISO West, followed by ERCOT. Queue capacity declined in 2025 in all regions except ERCOT and SPP.
    • PJM transition results: 84 projects totaling 14.3 GW received agreements in PJM’s first transition cycle; 21 battery projects accounted for 1.9 GW.
    • FERC oversight: On July 24, 2025, FERC directed PJM to revise its study process after determining its compliance plan did not fully meet Order No. 2023.
    • Project-design consideration: Order No. 2023’s co-location standards allow storage and a co-located generation asset to use a single interconnection request, a potential factor in project configuration and submission planning.
    • Schedule and supply-chain exposure: Developers, contractors, and energy-sector suppliers should account for multi-year delays when forecasting construction starts, equipment demand, and related procurement needs.
    • Action for market participants: Track FERC tariff proceedings and grid-operator implementation deadlines, and distinguish queue capacity from projects with executed agreements and credible paths to construction.

    Agencies

    • Federal Energy Regulatory Commission
    • Lawrence Berkeley National Laboratory
    • PJM Interconnection

    Vendors

    • Dominion Energy

    Locations

    • United States
    • Virginia
    • PJM
    • non-ISO West
    • ERCOT
    • SPP

    Sources

    • Battery storage queue backlog remains above 2,000 gigawatts despite FERC reformsgcn.com · Nov 07
    Energy & UtilitiesGrid InterconnectionBattery StorageFERCSupply ChainRegulatory Compliance
    ← Back to News
    samsearch

    The Complete AI Platform for Government Contracting

    Platform
    • Product
    • Pricing
    • ROI calculator
    • Integrations
    • Changelog
    Solutions
    • Solutions
    • Customers
    • Comparisons
    • Market watch
    Resources
    • Blog
    • Free GovCon tools
    • Glossary
    • Docs
    Company
    • API & partnerships
    • Careers
    • Support
    • Compliance
    • Trust centre
    • Contact
    Recognised & verified
    SOC 2 Type II Compliant, SamSearchAWS Partner - Advanced, SamSearch on AWS MarketplaceGartner Peer Insights Customer First, SamSearchUsers Love Us
    Ask AI about samsearch
    Ask ChatGPTAsk ClaudeAsk Perplexity
    Follow

    © 2026 samsearch. All rights reserved.

    Terms of usePrivacy policy