San Antonio Awards North Frio Street Bike and Pedestrian Construction Contract
San Antonio City Council awarded E-Z Bel Construction, LLC a contract for bike and pedestrian improvements along North Frio Street, from Interstate 10 to West Houston Street. Construction is expected to run from November 2026 through December 2027, creating coordination considerations for suppliers and nearby businesses; the contract value was not reported and no further bidding opportunities were identified.
Key Signals
- San Antonio awarded North Frio Street improvements to E-Z Bel Construction, LLC
- Five-foot bike lanes and sidewalk reconstruction define the project scope
- Construction scheduled for November 2026 through December 2027
- Phased lane closures will maintain two-way traffic
- No contract value or additional bidding opportunities were reported
"This project represents a critical first step towards the revitalization of Cattleman Square."
In October 2026, San Antonio City Council approved a construction contract with E-Z Bel Construction, LLC for bike and pedestrian improvements on North Frio Street. The project corridor runs from Interstate 10 to West Houston Street and is a municipal transportation and public works award. The contract value was not reported in the available information. Because the construction contract has already been awarded, this announcement is a project-execution signal rather than an open solicitation for the same scope of work.
The work includes five-foot bike lanes and widened or reconstructed sidewalks. These improvements place the project within the city’s broader investment in transportation infrastructure and street accessibility. The project is also tied to the revitalization of Cattleman Square. District 5 Councilwoman Teri Castillo described it as “a critical first step towards the revitalization of Cattleman Square.” That framing gives contractors and local suppliers useful context about the project’s neighborhood objectives, in addition to its defined roadway and sidewalk scope.
Construction is expected to begin in November 2026 and finish by December 2027. Work will proceed in phases, with temporary lane closures while maintaining two-way traffic. The schedule and traffic plan may matter to suppliers, subcontractors, service providers, and businesses coordinating deliveries or work near the corridor. Firms tracking San Antonio infrastructure spending can use the project as an indicator of active municipal construction demand, while recognizing that the reported material does not identify additional bidding opportunities.
For GovCon and public works market monitoring, the key near-term distinction is between an awarded project and a prospective procurement. E-Z Bel Construction is identified as the awardee, so firms interested in participating should monitor project execution and any separately announced subcontracting or supply needs rather than assume the prime construction package remains available. The City of San Antonio Capital Delivery & Public Works Department is identified in connection with the project. No contract amount, detailed procurement schedule, or additional solicitation was provided, limiting conclusions about project scale and follow-on opportunities.
- Awardee: E-Z Bel Construction, LLC received the construction contract approved by San Antonio City Council.
- Project location: North Frio Street, from Interstate 10 to West Houston Street, in San Antonio.
- Scope: Five-foot bike lanes and widened or reconstructed sidewalks.
- Schedule: Construction is expected to start in November 2026 and conclude by December 2027.
- Traffic management: Phased construction will include temporary lane closures, with two-way traffic maintained.
- Community context: Councilwoman Teri Castillo called the project “a critical first step towards the revitalization of Cattleman Square.”
- Procurement status: The construction contract has been awarded; no further bidding opportunities were identified in the available source information.
- Market takeaway: Suppliers and local businesses can use the schedule and phased traffic impacts to plan coordination near the project corridor.
- Price information: The contract value was not reported, so the award’s financial scale cannot be assessed from the available details.
Agencies
- City of San Antonio
- City of San Antonio Capital Delivery & Public Works Department